Home / Browse projects / Pune, Maharashtra / 7 Plumeria Drive- Phase 3
7 Plumeria Drive- Phase 3
RG-MH-67089 · RERA P52100050087 · Last updated on MahaRERA portal: 23 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Litigation declared, 1 case
- Completion date moved by 6 months
- 1 extension taken
- Rs 60.00 crore secured on the land, in favour of Bajaj Housing Finance Co Ltd
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
7 Plumeria Drive- Phase 3 is a Residential / Group Housing project by B A Consulting in Pune, Maharashtra, registered with MahaRERA as P52100050087 on 15 Mar 2023. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 6 months from the original filing. 177 of the 275 units on this registration are recorded sold or booked, and 21 of 33 construction stages are filed complete.
At a glance
Project
- Name7 Plumeria Drive- Phase 3
- TypeResidential / Group Housing
- Location
- Aundh Ravet BRT Road
- Punawale
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100050087
- ReraGenie IDRG-MH-67089
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Mar 2023
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 31 Mar 2026)
- Buildings3 building records
- Documents filed195 files
Current status
Figures as on 23 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| H | NA | 32 | 31 | 122 | 0 | 122 |
| I | NA | 32 | 31 | 124 | 0 | 124 |
| L | NA | 5 | 5 | 29 | 0 | 29 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
21 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 96%.
H88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 96% |
| Sanitary Fittings within the flats / premises | 85% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
I88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 96% |
| Sanitary Fittings within the flats / premises | 86% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
L79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 81% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 20% |
| Street Lighting | Yes | 80% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed500
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| H | 42 | 189 | 231 |
| I | 33 | 207 | 240 |
| L | 16 | 13 | 29 |
Land and ownership7
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Mayur Kashinath Dhavale | Baner | Pune |
| Kumar Kashinath Dhavale | Baner | Pune |
| Sulbha Kashinath Dhavale | Baner | Pune |
| Amar Kashinath Dhavale & Others | Baner | Pune |
| Umesh Raghunath Borage & Others | Baner | Pune |
| Dattatray Maruti Dhavale & Others | Baner | Pune |
| Ganesh Raghunath Borage & Others | Baner | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| I | NA | Rs 80.56 cr | Rs 68.27 cr |
| H | NA | Rs 61.44 cr | Rs 52.48 cr |
| - | NA | Rs 25.24 cr | Rs 18.30 cr |
| L | NA | Rs 3.53 cr | Rs 3.35 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Milind Patil |
| Engineer | Rakesh Kumar |
| Engineer | Mangesh Deokar |
| Chartered Accountant | A S Jinturkar & Co. |
| Chartered Accountant | S P C M & Associates |
| Partner | Role in project |
|---|---|
| B A Consulting | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRespected Sir/Madam, We, the Promoter of the below-mentioned project, hereby state and confirm that the project has been delayed by approximately 3-4 months due to circumstances beyond our control. The primary reasons for the delay are as follows: Adverse Weather Conditions Material and Supply Chain Issues Regulatory Delays Financial and Sales-Related Impact In view of the above unavoidable circumstances, we are hereby applying for an extension of the project completion date as per MahaRERA Order No. 40. We kindly request an extension up to 30-09-2026, by which time we are confident that we wi
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 194/2023 | CIvil Judge Senior Divison Pune | Pending |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed195
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 195 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - 7PD-Phase III-June 2026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - 7PD-Phase III-June 2026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - 7PD-Phase III-June 2026_11zon.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - 7PD-Phase III-March 2026 111.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - 7PD-Phase III-March 2026 111.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - 7PD-Phase III-March 2026 111_compressed.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 March 2026.pdf | 31 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 March 2026.pdf | 31 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 March 2026.pdf | 31 Mar 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 for June 2025 Final.pdf | 28 Feb 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 for September 2025 Final.pdf | 28 Feb 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 for December 2025 Final.pdf | 28 Feb 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 for June 2025 Final.pdf | 28 Feb 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 for September 2025 Final.pdf | 28 Feb 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 for December 2025 Final.pdf | 28 Feb 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 for June 2025 Final .pdf | 28 Feb 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 for September 2025 Final.pdf | 28 Feb 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 for December 2025 Final.pdf | 28 Feb 2026 |
| Form 2A (FY 2024-2025)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2024-25).pdf | 28 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-Q4-31-03-2023.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-March 2023.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III March 2023.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 March 2023.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-Q1-30-06-2023.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-Q1-30-06-2023.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III-Q1-30-06-2023.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 june 23.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-Q2-30-09-2023.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-Q2-30-09-2023.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III-Q2-30-09-2023.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 sept 23.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-Q3-31-12-2023.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-Q3-31-12-2023.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III-Q3-31-12-2023.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 dec 23.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-March 2024.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III- March 2024.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III- March 2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 March 2024.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-30-06-2024.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-30-06- 2024.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III-30-06-2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 June 2024.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-30-09-2024.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-30-09-2024.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III-30-09-2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 sept 24.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III-31-12-2024.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-31-12-2024.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III-31-12-2024.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 dec 24.pdf | 27 Feb 2026 |
| Form 1File: Form 1 - 7PD-Phase III- 31-03-2025.pdf | 27 Feb 2026 |
| Form 2File: Form 2 - 7PD-Phase III-31-03- 2025.pdf | 27 Feb 2026 |
| Form 3File: Form 3 - 7PD-Phase III-31-03-2025.pdf | 27 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 march 25.pdf | 27 Feb 2026 |
| Form 2A (FY 2022-2023)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf | 27 Feb 2026 |
| Form 2A (FY 2023-2024)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf | 27 Feb 2026 |
| Form 5 (FY 2022-2023)File: Form 5 - B A Consulting - 7 PD - Phase III - FY-2022-23.pdf | 27 Feb 2026 |
| Form 5 (FY 2023-2024)File: Form 5 - 7PD- Phase III -2023-24.pdf | 27 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - B A Consulting - 7PD-Phase III-FY-2024-25.pdf | 27 Feb 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 7PD-Phase III-December 2024.pdf | 8 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 7PD-Phase III-December 2024.pdf | 8 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 7PD-Phase III-December 2024.pdf | 5 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 7PD-Phase III-June 2024.pdf | 5 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 7PD-Phase III-Septembr 2024.pdf | 5 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 7PD-Phase III-June 2024.pdf | 5 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 7PD-Phase III-September 2024-compressed.pdf | 5 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 7PD-Phase III-June 2024.pdf | 5 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 7PD-Phase III-Septembr 2024.pdf | 5 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 7PD- Phase III -2023-24.pdf | 4 Nov 2024 |
| Building plan approvalFile: 1-11_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 2-11_1_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 3-11_2_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 4-11_3_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 5-11_4_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 6-11_5_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 7-11_1_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 8-11_2_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 9-11_3_11zon.pdf | 28 Oct 2024 |
| Building plan approvalFile: 10-11_4_11zon.pdf | 28 Oct 2024 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| 43 Privet Drive Phase 1 | Balewadi Pune | 204 | Completed | Oct 2015 | Late, Dec 2015 |
| Latitude | Wakad Pune | 165 | Completed | May 2012 | Mar 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 195 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep 7 Plumeria Drive- Phase 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Punawale13,700+ in Pune
Filed coordinates, straight-line distance. 227 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: B A Consulting
B A Consulting has 3 registrations on MahaRERA, including 7 Plumeria Drive- Phase 1 and 7 Plumeria Drive- Phase 2. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if 7 Plumeria Drive- Phase 3 is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 7 Plumeria Drive- Phase 3?
The registered promoter entity is B A Consulting, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 7 Plumeria Drive- Phase 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for 7 Plumeria Drive- Phase 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 7 Plumeria Drive- Phase 3?
The professionals named in the filing: Architect: Milind Patil; Engineer: Rakesh Kumar; Engineer: Mangesh Deokar; Chartered Accountant: A S Jinturkar & Co.; Chartered Accountant: S P C M & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 7 Plumeria Drive- Phase 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback