Home / Browse projects / Pune, Maharashtra / 55 Shashwat Avenue

Registered No litigation declared Residential / Group Housing project

55 Shashwat Avenue

By Shashwat Landmark

RG-MH-82836 · RERA P52100046357 · Last updated on MahaRERA portal: 23 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 36 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 65%
10 of 19Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

55 Shashwat Avenue is a Residential / Group Housing project by Shashwat Landmark in Pune, Maharashtra, registered with MahaRERA as P52100046357 on 22 Jun 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 36 months from the original filing. 9 of the 19 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • Name55 Shashwat Avenue
  • TypeResidential / Group Housing
  • Location
    • Hissa No. 6A/1
    • Vadgaon Budruk
    • Wadgaon Bk
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046357
  • ReraGenie IDRG-MH-82836

Builder

  • NameShashwat Landmark
  • Entity typePartnership
  • PartnersShrikant Bhaskarrao Suryavanshi, Sukdev Pandit Patil

Key dates

this monthRegisteredJun 2022First promiseDec 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jun 2022
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed77 files

Current status

47%9 of 19 units booked
49.3%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
55 Shashwat AvenueNA6419019

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 65%.

55 Shashwat Avenue: 52% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises57%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered11

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area946 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Jun 2025
LandownerVillageDistrict
Pallavi Prakash KerkarPune (M Corp.)Pune
Prakash Sonu KerkarPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2811.04
Proposed, not sanctioned1,579 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBalevadi Pune
Estimated costRs 8.20 cr
Cost incurredRs 4.04 cr
Work done49.3%
BuildingWingEstimatedIncurred
55 Shashwat AvenueNARs 7.79 crRs 3.81 cr
-NARs 41.00 lakhRs 23.69 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVista Architects
EngineerSK Consultants & Engineers
EngineerAkshay Londhe
Chartered AccountantNB Sayed & Associates
Chartered AccountantPranav Bhaskaran & Associates
PartnerRole in project
Shashwat Landmark-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024678Dec 2024 → Dec 2025

Reason as filed by the promotern accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EA02122518487Dec 2024 → Dec 2027

Reason as filed by the promoterThe recent increase in the Floor Space Index (FSI) has led to a substantial expansion of the project's scope. To ensure that we continue to uphold the highest standards of quality and deliverables, additional time is essential. Given the circumstances, we kindly request an extension until 31-12-2027 to complete the project and fulfil all regulatory requirements.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - 55 Shashwat Avenue June 2026.pdf23 Jul 2026
Withdrawal Update Form 2File: Form 2 - 55 Shashwat Avenue June 2026.pdf23 Jul 2026
Withdrawal Update Form 3File: Form 3 - 55 Shashwat Avenue June 2026.pdf23 Jul 2026
Form 2A (FY 2024-2025)File: FORM 2A - 55 Shashwat Avenue - 2024-25.pdf20 Jun 2026
Form 2A (FY 2025-2026)File: FORM 2A - 55 Shashwat Avenue - 2025-26.pdf20 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 - 55 Shashwat Avenue for FY 2024-25.pdf6 Jun 2026
Withdrawal Update Form 1File: Form 1 55 Shashwat Avenue 31st March 2026.pdf20 May 2026
Withdrawal Update Form 2File: Form 2 - 55 Shashwat Avenue as on March 2026.pdf20 May 2026
Withdrawal Update Form 3File: Form 3 55 Shashwat Avenue 31-03-2026.pdf20 May 2026
Withdrawal Update Form 1File: Form 1 55 Shashwat Avenue 31st Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 - 55 Shashwat Avenue as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 - 55 Shashwat Avenue as on Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 - 55 Shashwat Avenue as on Sep 2025.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2 - 55 Shashwat Avenue as on Sep 2025.pdf16 Oct 2025
Withdrawal Update Form 3File: Form 3 - 55 Shashwat Avenue as on Sep 2025.pdf16 Oct 2025
Form 1File: Form 1 - 55 Shashwat Avenue as on June 2025.pdf17 Jul 2025
Form 2File: Form 2 - 55 Shashwat Avenue as on June 2025.pdf17 Jul 2025
Form 3File: Form 3 - 55 Shashwat Avenue as on June 2025.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - 55 Shashwat Avenue.pdf17 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 55 Shashwat Avenue as on March 2025.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 55 Shashwat Avenue as on Dec 2024.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 55 Shashwat Avenue as on Dec 2024.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 55 Shashwat Avenue as on Dec 2024.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 55 Shashwat Avenue as on Sept 2024.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 55 Shashwat Avenue as on Sept 2024.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 55 Shashwat Avenue as on Sept 2024.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 55 Shashwat Avenue as on Sept 2024.pdf14 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 55 Shashwat Avenue for FY 2023-24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 55 Shashwat Avenue for FY 2023-24.pdf9 Oct 2024
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Cirecular 29.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A_22-23.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_23-24.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineers Certificate (1).pdf7 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_55 Shashwat Avenue (1).pdf7 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf7 Oct 2024
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf7 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_55 Shashwat Avenue (1).pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineers Certificate (1).pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Cirecular 29.pdf7 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A_22-23.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_23-24.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: IMG_20240704_0001 (1).pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 55 Shashwat Avenue as on June 2024.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Final Form 3 55 Shashwat Avenue 30-06-2024.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 55 Shashwat Avenue as on 31st Dec 2023.pdf12 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 55 Shashwat Avenue as on 31st March 2024.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New format- Final Form 3 55 Shashwat Avenue 31-12-2023.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 55 Shashwat Avenue as on 31st March 2024.pdf12 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 55 Shashwat Avenue as on March 2024.pdf6 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 55 Shashwat Avenue as on Dec 2023.pdf5 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 55 Shashwat Avenue (22-23).pdf2 Mar 2024
Proforma of Allotment letterFile: UPDATED RERA AGREEMENT TO SALE-55 SHASHWAT 08092022.pdf17 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: Badgaon Bk.pdf18 Jul 2022
CERSAI detailsFile: 55 Shaswat Avenue.pdf18 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Signed_compressed.pdf18 Jun 2022
Proforma of Allotment letterFile: Allotment Letter Shashwat Landmark.pdf18 Jun 2022
Copy of the legal title reportFile: Title Shaswat.pdf17 Jun 2022
Proforma of Allotment letterFile: Agreement For Sale.pdf17 Jun 2022
Details of encumbrancesFile: SL encumbrance.pdf16 Jun 2022
Declaration about Commencement CertificateFile: Declaration SL.pdf16 Jun 2022
Declaration in FORM BFile: Affidavit cum declaration (SL) for Rera (1).pdf16 Jun 2022
Layout approvalFile: Shashwat Landmark Layout Plan_compressed.pdf9 Jun 2022
Building plan approvalFile: Shashwat Landmark 1,3_compressed.pdf9 Jun 2022
Building plan approvalFile: Shashwat Landmark 2,4_compressed_rotated.pdf9 Jun 2022
PAN CardFile: Shashwat Landmark PAN.pdf9 Jun 2022
Copy of Layout Approval (in case of layout)File: Shashwat Landmark Layout Plan_compressed.pdf9 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Shashwat Landmark 1,3_compressed.pdf9 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Shashwat Landmark 2,4_compressed_rotated.pdf9 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Shashwat Landmark Commencement 1st_compressed.pdf9 Jun 2022

How this compares with Pune

47%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 55 Shashwat Avenue on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vadgaon Budruk13,700+ in Pune

2 km55 Shashwat AvenueCompleted 39Lapsed / revoked 31Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: Shashwat Landmark

Shashwat Landmark has 1 registration on MahaRERA, including 55 Shashwat Avenue. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if 55 Shashwat Avenue is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 55 Shashwat Avenue?

The registered promoter entity is Shashwat Landmark, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 55 Shashwat Avenue?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 55 Shashwat Avenue?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 55 Shashwat Avenue?

The professionals named in the filing: Architect: Vista Architects; Engineer: SK Consultants & Engineers; Engineer: Akshay Londhe; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 55 Shashwat Avenue?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 55 Shashwat Avenue. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 55 Shashwat Avenue to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.