Home / Browse projects / Pune, Maharashtra / 41 CITY HUB
41 CITY HUB
RG-MH-22381 · RERA P52100030903 · Last updated on MahaRERA portal: 24 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 9 cases
- 1 complaint at MahaRERA
- Completion date moved by 28 months
- 2 extensions taken
Clear
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
41 CITY HUB is a Commercial project by M/s WONDER SKYLINE LLP in Pune, Maharashtra, registered with MahaRERA as P52100030903 on 29 Sep 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 28 months from the original filing. 244 of the 285 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- Name41 CITY HUB
- TypeCommercial
- Location
- PUNE- SOLAPUR HIGHWAY
- HADAPSAR
- Haveli
- Pune
- 411028
- Pincode411028
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100030903
- ReraGenie IDRG-MH-22381
Builder
- NameM/s WONDER SKYLINE LLP
- Entity typePartnership
- PartnersVISHAL OMPRAKASH AGARWAL, SAGAR OMPRAKASH AGARWAL, MANOJ VIJAYKUMAR AGARWAL, ANUJ RAJESH AGARWAL, ANSH MUKESH AGARWAL
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Sep 2021
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 30 Nov 2024)
- Buildings1 building record
- Documents filed107 files
Current status
Figures as on 24 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 41 CITY HUB K BUILDING | NA | 16 | 10 | 0 | 285 | 285 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
41 CITY HUB K BUILDING: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership30
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S KUMAR BEHERAY RATHI | Pune (M Corp.) | Pune |
| YASHWANT MORESHWAR PARANJAPE | Pune (M Corp.) | Pune |
| SUMATIBAI MROESHWAR PARANAJAPE | Pune (M Corp.) | Pune |
| MADHAV NARAYAN PARANJAPE | Pune (M Corp.) | Pune |
| MOHINI MADHAV PARANJAPE | Pune (M Corp.) | Pune |
| ANAPLA RAJIV PARANJAPE | Pune (M Corp.) | Pune |
| KUNAL RAJIV PARANJAPE | Pune (M Corp.) | Pune |
| RAJIV MADHAV PARANJAPE | Pune (M Corp.) | Pune |
| RADHA ALIAS MEDHA RAJU RAJE | Pune (M Corp.) | Pune |
| PRABHA YAHSWANT PARANJAPE | Pune (M Corp.) | Pune |
| SHUBHADA SANJIV PARANAJAPE | Pune (M Corp.) | Pune |
| AJAY YASHWANT PARANJAPE | Pune (M Corp.) | Pune |
| DHANANJAY YASHWANT PARANJAPE | Pune (M Corp.) | Pune |
| SHILA VISHWANATH GOKHALE | Pune (M Corp.) | Pune |
| SANJIV YASHWANT PARANJAPE | Pune (M Corp.) | Pune |
| KUMAR BEHERAY RATHI | Pune (M Corp.) | Pune |
| PARANJAPE YASHWANT MORESHWAR | Pune (M Corp.) | Pune |
| PARANAJAPE SUMATIBAI MROESHWAR | Pune (M Corp.) | Pune |
| PARANJAPE MADHAV NARAYAN | Pune (M Corp.) | Pune |
| PARANJAPE MOHINI MADHAV | Pune (M Corp.) | Pune |
| PARANJAPE ANAPLA RAJIV | Pune (M Corp.) | Pune |
| PARANJAPE KUNAL RAJIV | Pune (M Corp.) | Pune |
| PARANJAPE RAJIV MADHAV | Pune (M Corp.) | Pune |
| RAJE MEDHA (RADHA) RAJU | Pune (M Corp.) | Pune |
| PARANJAPE PRABHA YAHSWANT | Pune (M Corp.) | Pune |
| PARANAJAPE SHUBHADA SANJIV | Pune (M Corp.) | Pune |
| PARANJAPE AJAY YASHWANT | Pune (M Corp.) | Pune |
| PARANJAPE DHANANJAY YASHWANT | Pune (M Corp.) | Pune |
| GOKHALE SHILA VISHWANATH | Pune (M Corp.) | Pune |
| PARANJAPE SANJIV YASHWANT | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| 41 CITY HUB K BUILDING | NA | Rs 43.14 cr | Rs 42.69 cr |
| - | NA | Rs 10.79 cr | Rs 7.53 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CUBIX ARCHITECTS ASSOCIATES |
| Engineer | MAYUR ANAND AKHADE |
| Chartered Accountant | V A DUDHEDIA & CO |
| Chartered Accountant | ROHIT JADHAV & ASSOCIATES |
| Chartered Accountant | A S A K & Co Chartered Accountants |
| Chartered Accountant | Agarwal Sarawgi and Associates |
| Chartered Accountant | Patel and Sharma |
| Chartered Accountant | Dipali Shelar and Company |
| Partner | Role in project |
|---|---|
| M/s WONDER SKYLINE LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is facing delays due to a severe labour shortage, resulting in the unavailability of skilled workers. Additionally, the contractor’s performance has been adversely affected, leading in inefficiencies and compromised work quality. Given these challenges, requesting an extension becomes imperative to ensure the project’s successful completion while maintaining the desired standards and mitigating the impact of unforeseen workforce constraints.
Reason as filed by the promoterhe project has encountered unforeseen challenges that have significantly impacted its timeline and progress. These challenges include- Severe Labor Shortage,Impact on Contractor's Performance,Ensuring Quality and Compliance.
Litigation declared9
| Case | Court | Status |
|---|---|---|
| 2617/2007 /2007 | Criminal Court | Ongoing |
| 131/2014/2014 | The Honorable State Consumer Disputes Redressal Commission at Pune | Ongoing |
| 71/2015/2015 | Civil Court | Closed |
| 724/2019/2019 | High Court Bombay | Ongoing |
| 380/2018/2018 | High Court Bombay | Closed |
| 206/2020/2020 | Civil Court | Ongoing |
| 207/2020/2020 | Civil Court | Ongoing |
| 782/2017/2017 | Civil Court | Closed |
| 131/2014/2014 | The Honorable State Consumer Disputes Redressal Commission at Pune | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12401114 | CHETAN NANDKISHOR NOGAJA | M/s WONDER SKYLINE LLP | 13/12/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Dec 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2027
Documents filed107
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_Architect Certificate_QPR1-26-27_WSLLP.pdf | 24 Jul 2026 |
| Withdrawal Update Form 2File: Form 2_Enggineer Certificate_QPR1-26-27_WSLLP.pdf | 24 Jul 2026 |
| Withdrawal Update Form 3File: Form 3_C A Certificate_QPR1-26-27_WSLLP.pdf | 24 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_Architect Certificate_QPR4_WSLLP.pdf | 1 May 2026 |
| Withdrawal Update Form 2File: Form 2_Engg Certificate_QPR4_WSLLP.pdf | 1 May 2026 |
| Withdrawal Update Form 3File: Form 3_C A Certificate_QPR4_WSLLP compressed.pdf | 1 May 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 25 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Engg Certificate.pdf | 25 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate Signed.pdf | 25 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form 2 A_WSLLP.pdf | 30 Dec 2025 |
| Withdrawal Update Form 1File: Form 1_Architect Certificate_Sep25_WSLLP.pdf | 5 Dec 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 5 Dec 2025 |
| Withdrawal Update Form 3File: org-Form 3_11zon.pdf | 5 Dec 2025 |
| Form 5 (FY 2024-2025)File: Sign-Form 5_Wonder Skyline LLP.pdf | 29 Sep 2025 |
| Withdrawal Update Form 1File: Form 1_Architect certificate_WSLLP.pdf | 23 Sep 2025 |
| Withdrawal Update Form 1File: Form 1_Architect certificate_WSLLP.pdf | 23 Sep 2025 |
| Withdrawal Update Form 2File: Form 2_Engg Certificate_WSLLP.pdf | 23 Sep 2025 |
| Withdrawal Update Form 2File: Form 2_Engg Certificate_WSLLP.pdf | 23 Sep 2025 |
| Withdrawal Update Form 3File: Form 3_CA Certificate_WSLLP_11zon.pdf | 23 Sep 2025 |
| Withdrawal Update Form 3File: Form 3_CA Certificate_WSLLP_11zon.pdf | 23 Sep 2025 |
| Form 1File: Form1_Architect Certificate_Wsllp.pdf | 16 Jun 2025 |
| Form 2File: Form2_Engg certificate_Wsllp.pdf | 16 Jun 2025 |
| Form 3File: Form3_CA Certificate_Wsllp.pdf | 16 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold inventory_wsllp.pdf | 16 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_C A Certificate sign_WSLLP.pdf | 13 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1_Architect certificate _Wsllp.pdf | 5 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate_WSLLP.pdf | 31 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventary_WSLLP.pdf | 31 Jan 2025 |
| Copy of the legal title reportFile: Title Certificate_WSLLP.pdf | 3 Dec 2024 |
| Details of encumbrancesFile: Declaration Concerned to Finance_WSLLP.pdf | 3 Dec 2024 |
| Declaration in FORM BFile: Form B_compressed.pdf | 3 Dec 2024 |
| CERSAI detailsFile: Asset Based CERSAI report.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Annual Report_WSLLP- Final.pdf | 13 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Wonder Skyline.pdf | 12 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_C A Certificate_WSLLP.pdf | 12 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_WSLLP.pdf | 12 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Wonder.pdf | 12 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventary_WSLLP.pdf | 12 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf | 12 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 31323.pdf | 15 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 31324.pdf | 15 Jun 2024 |
| Declaration in FORM BFile: Form B_Wonder Skyline.pdf | 14 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1- Architect Certificate_WSLLP.pdf | 13 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Engineer Certificate.pdf | 13 May 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventary_Mar24_WSLLP.pdf | 13 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - C A certificate uploaded.pdf | 13 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Wonder Skyline.pdf | 4 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer certificate -41 city hub.pdf | 4 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventary_Dec23_WSLLP_compressed.pdf | 4 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA Certificate_WSLLP.pdf | 4 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_30-09-2023_Wonder LATEST.pdf | 1 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Annual report of Statement of Accounts_WonderSkyline.pdf | 29 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Architect Certificate.pdf | 7 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Engineer Certificate.pdf | 7 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Declaration of Sold Unsold Inventary.pdf | 7 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsol Inventary.pdf | 7 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA Certifiacte.pdf | 7 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-C A Certificate-WSLLP_11zon.pdf | 31 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Architect Certificate.pdf | 12 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Engineer Certificate.pdf | 12 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_C A Certificate.pdf | 2 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Architect Certificate.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Declaration for sold unsold 03-04-2023.pdf | 20 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5-Annual Audit Report.pdf | 15 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-Annual Audit Report.pdf | 15 Mar 2023 |
| Proforma of Agreement for saleFile: RERA Draft Agreement dated.pdf | 13 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Declaration of Sold and Unsold Inventary.pdf | 12 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 11 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 11 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate_WSLLP.pdf | 5 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate.pdf | 18 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventary 05-10-2022.pdf | 18 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_June 2022.pdf | 14 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate_June 2022.pdf | 14 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventary 05-07-2022_June 2022_compressed.pdf | 14 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ C A Certificate_March 2022_compressed.pdf | 14 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_C A Certificate_June 2022.pdf | 14 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_01-04-2022.pdf | 2 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31-03-2022.pdf | 18 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 107 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep 41 CITY HUB on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near HADAPSAR13,700+ in Pune
Filed coordinates, straight-line distance. 87 registered projects within 2 km.
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc Residences - A2
Kumar Properties Infratech Developers Pvt
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Builder: M/s WONDER SKYLINE LLP
M/s WONDER SKYLINE LLP has 1 registration on MahaRERA, including 41 CITY HUB. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if 41 CITY HUB is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 41 CITY HUB?
The registered promoter entity is M/s WONDER SKYLINE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 41 CITY HUB?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against 41 CITY HUB?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for 41 CITY HUB?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 41 CITY HUB?
The professionals named in the filing: Architect: CUBIX ARCHITECTS ASSOCIATES; Engineer: MAYUR ANAND AKHADE; Chartered Accountant: V A DUDHEDIA & CO; Chartered Accountant: ROHIT JADHAV & ASSOCIATES; Chartered Accountant: A S A K & Co Chartered Accountants; Chartered Accountant: Agarwal Sarawgi and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 41 CITY HUB?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback