Registration lapsed No litigation declared Residential / Group Housing project

19 Grand West Wing A

By Shivam Development Ventures LLP

RG-MH-52769 · RERA P52100018030 · Last updated on MahaRERA portal: 13 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 31 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 174 documents Report an error

19 Grand West Wing A is a Residential / Group Housing project by Shivam Development Ventures LLP in Pune, Maharashtra, registered with MahaRERA as P52100018030 on 5 Oct 2018. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 31 months from the original filing.

At a glance

Project

  • Name19 Grand West Wing A
  • TypeResidential / Group Housing
  • Location
    • Aditrya Birla Hospital Road
    • Thergaon
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • RERA no.P52100018030
  • ReraGenie IDRG-MH-52769

Builder

  • NameShivam Development Ventures LLP
  • Entity typePartnership
  • PartnersRajendra Popat Ghanwat, Popat Maruti Ghanwat, Changuna Popat Ghanwat
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

22 months past promisethis monthRegisteredOct 2018First promiseMay 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Oct 2018
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 31 May 2022)
  • Buildings1 building record
  • Documents filed174 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
19 Grand West Wing ANA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

19 Grand West Wing A: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,702 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI52454.0
Proposed, not sanctioned10,973 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPB NO 7 KASARWADI NR DAI CHI CO OPP HOTEL KALASAGAR PUNE 411034

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKimaya Associates Liasoning Architect
ArchitectAdvantage Architects Planning Architects
EngineerG.A.Bhilare Consultants Pvt.Ltd.
PartnerRole in project
Shivam Development Ventures LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012949May 2022 → Nov 2023

Reason as filed by the promoterNon availability of raw material and Labor due to Covid-19 Pandemic

EXT52100018821May 2022 → Dec 2024

Reason as filed by the promoterProject Work is near completion and only finishing work is remaining.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Jun 2024

Documents filed174

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 174 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Proforma of Allotment letterFile: Form 5 SDVLLP A Wing.pdf13 Mar 2025
Certificates of CA (Form 3)File: Form3-19GrandWestA-dt2024Dec31DSC.pdf15 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Wing A_2023-24.pdf11 Jan 2025
Status of ConveyanceFile: Conveyance Index II (1).pdf1 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA-F1-JUN 2024.pdf15 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2b-19GWA - F2 -MARCH 22_11zon.pdf15 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2c-19GWA-F2-DEC-2022.pdf15 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19GWA-F2-JUN 2024.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 19GWA-F2A-JUN 2024.pdf15 Jul 2024
Certificates of CA (Form 3)File: 3-19GWA-F3-MAR 2022.pdf15 Jul 2024
Certificates of CA (Form 3)File: 19GWA-F3-JUN 2024.pdf15 Jul 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: 5-19GRAND WEST SOCIETY REGISTRATION CERTIFICATE.pdf15 Jul 2024
Status of ConveyanceFile: 6-CONVEYANCE DEED DRAFT FOR 19 GRAND WEST.pdf15 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A and B Wing Part Completion 2022 (1).pdf28 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA-FORM1-MARCH 2024.pdf16 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19GWA-FORM2-MARCH 2024.pdf16 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 19GWA-FORM2A-MARCH 2024.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: S-U-19GWA-MAR 2024.pdf16 Apr 2024
Certificates of CA (Form 3)File: 19GWA-FORM3-MARHCH 2024.pdf16 Apr 2024
Declaration in FORM BFile: 5 (13).pdf15 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA-F1-DEC 23.pdf7 Feb 2024
CERSAI detailsFile: Declaration for Bank details (1) (1).pdf5 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Bank details a wing.pdf5 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Rajendra Ghanwat.pdf2 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Changuna Ghanwat.pdf2 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Popat Ghanwat.pdf2 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19GWA-F2-DEC 2023.pdf17 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 19GWA-2A-DEC 2023.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: S-U-19GWA-DEC 2023.pdf17 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 19GWA-F5-FY 2022-2023.pdf30 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA-F1-SEP 2023.pdf28 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA-F1-JUN 23.pdf8 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19GWA-F2-JUN 23.pdf8 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 19GWA-F2A-JUN 23.pdf8 Sep 2023
Disclosure of sold/ booked inventoryFile: 19GWA-S-U-JUN23.pdf8 Sep 2023
Certificates of CA (Form 3)File: 19GWA-F3-JUN23.pdf8 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (3).pdf15 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA- FORM1 Architect Certificate-MARCH 2023-111.pdf20 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19GWA-FORM2 Engineer Certificate -MARCH 2023-1111.pdf20 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 19GWA-FORM2A Quality Assurance-MARCH 2023 -11111.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: S-U-19GWA- Sold Unsold Inventory MARCH 2023-112333.pdf20 Apr 2023
Certificates of CA (Form 3)File: 19GWA-FORM 3 CA Certificate-MARCH 2023.pdf20 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annaul Audit Report 19 GW-FROM 5-A WING.pdf1 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA-F1-DEC 2022.pdf4 Feb 2023
Disclosure of sold/ booked inventoryFile: A WING SOLD_UNSOLD LIST.pdf21 Jan 2023
Certificates of CA (Form 3)File: 19GW A-FORM 3-DEC 22.pdf21 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA FORM 5 WING A.pdf24 Nov 2022
Disclosure of sold/ booked inventoryFile: A Wing Sold Unsold list.pdf21 Nov 2022
Certificates of CA (Form 3)File: 19 GWA - 30 SEP 2022.pdf21 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 A WING.pdf11 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A- WING-FORM 2.pdf5 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A- WING-FORM 2A.pdf5 Nov 2022
Disclosure of sold/ booked inventoryFile: 19GW A WING - JUN22 (1).pdf15 Aug 2022
Certificates of CA (Form 3)File: Form3-19Grand-WingA-Dt2022Jul31-DSC (1).pdf15 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A BLDG FROM 1 (1).pdf30 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A wing Form 2 compressed.pdf30 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A wing Form 2a compressed.pdf30 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A wing Form 1 - compressed.pdf23 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A wing Form 2A - compressed.pdf23 Apr 2022
Disclosure of sold/ booked inventoryFile: 19GWA sold unsold compressed.pdf23 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A wing Form 2 Engineer Certificate.pdf19 Feb 2022
Certificates of CA (Form 3)File: Form3-19GrandW-Wing A-Dec21-DSC.pdf9 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19 gw Awing f1 Dec 21.pdf20 Jan 2022
Disclosure of sold/ booked inventoryFile: A WING SOLD UNSOLD.pdf4 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19GW A wing -19-20 F-5.pdf24 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 19GW A wing -20-21 F-5.pdf24 Nov 2021
Declaration about Commencement CertificateFile: 19GWA CCD.pdf27 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19GW A wing Form2.pdf8 Oct 2021
Certificates of CA (Form 3)File: Form3-Grand West A-Sep21-DSC[1340].pdf7 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: B wing Architect Certificate.pdf5 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A wing Architect Certificate.pdf5 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Rera Form 2A A wing.pdf5 Oct 2021
Disclosure of sold/ booked inventoryFile: 19gwa- soldunsold.pdf5 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 19gwa f2 jun21.pdf27 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19GWA -F1 - 31-06-2021.pdf25 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 19gwa f2a jun21.pdf25 Aug 2021
Certificates of CA (Form 3)File: 19gwa f3 jun21.pdf25 Aug 2021
Certificates of CA (Form 3)File: 19gwa march 21-compressed.pdf25 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19 GWA - F1 - 31-12-2020-min.pdf4 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A QUALITY ASSURANCE (A WING) 31-12-20.pdf4 Jun 2021

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SHIVAM CASAS No 127 1 30 Nr Shivam Majestica Choudhary Park Area Wakad Pune 411 0578CompletedOct 2015Late, Oct 2016
SHIVAM NITYAS No 127 56 Plot no 32 Nr Shivam Majestica Choudhary Park Area Wakad Pune 411 0578CompletedJan 2015Late, Jul 2015
GHANWAT PLAZAGat no 482 Chakan Talegaon Road Nanekar Wadi Chakan 411 501111CompletedSep 2013Late, Aug 2016
GHANWAT PLAZAGat no 482 Chakan Talegaon Road Nanekar Wadi Chakan 411 501111CompletedSep 2013Late, Aug 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 31 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 19 Grand West Wing A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thergaon13,700+ in Pune

Builder: Shivam Development Ventures LLP

Shivam Development Ventures LLP has 3 registrations on MahaRERA, including 19 Grand West Wing A and 19 Grand West Wing B. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that 19 Grand West Wing A shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if 19 Grand West Wing A is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 19 Grand West Wing A?

The registered promoter entity is Shivam Development Ventures LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 19 Grand West Wing A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 19 Grand West Wing A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 19 Grand West Wing A?

The professionals named in the filing: Architect: Kimaya Associates Liasoning Architect; Architect: Advantage Architects Planning Architects; Engineer: G.A.Bhilare Consultants Pvt.Ltd.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 19 Grand West Wing A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 19 Grand West Wing A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 19 Grand West Wing A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.