Home / Browse projects / Pune, Maharashtra / 18 LONGITUDE PHASE 3

Registration lapsed No litigation declared Others project

18 LONGITUDE PHASE 3

By G D SQUARE PROMOTERS LLP

RG-MH-82804 · RERA P52100019292 · Last updated on MahaRERA portal: 17 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
14 of 34Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

18 LONGITUDE PHASE 3 is a Others project by G D SQUARE PROMOTERS LLP in Pune, Maharashtra, registered with MahaRERA as P52100019292 on 21 Jan 2019. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 48 months from the original filing. 20 of the 34 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete.

At a glance

Project

  • Name18 LONGITUDE PHASE 3
  • TypeOthers
  • Location
    • LATITUDE ROAD
    • NEAR BALAJI MANDIR
    • Punawale
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100019292
  • ReraGenie IDRG-MH-82804

Builder

  • NameG D SQUARE PROMOTERS LLP
  • Entity typePartnership
  • PartnersMRIGENDRA SURYAKANT GOWARDHAN, DHANANJAY MADHAVRAO BUDUKH, SANDEEP DAYANAND SHARMA
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

16 months past promisethis monthRegisteredJan 2019First promiseJun 2021Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Jan 2019
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 12 Jun 2021)
  • Buildings2 building records
  • Documents filed79 files

Current status

59%20 of 34 units booked

Figures as on 17 Apr 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
18 LONGITUDE PHASE 3 - ENA5510717
18 LONGITUDE PHASE 3 - FNA5510717

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

18 LONGITUDE PHASE 3 - E100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
18 LONGITUDE PHASE 3 - F100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,213 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jun 2025
LandownerVillageDistrict
MATHEW ANTONY PUDUSSERYwanwadiPune

Approvals and building plan

Sanctioning authorityPimpri-Chinchwad Municipal Corporation
Permissible FSI1031.05
Proposed, not sanctioned1,031 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSNo 182 1 1 Atria Building Near Shivsagar Hotel Near Sai Empress Building Baner Rd Baner Pune Mahara

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerAkshay Sunil Chordiya
EngineerKaustubh Dhanaji Pawar
Chartered AccountantVinit D Achha
PartnerRole in project
G D SQUARE PROMOTERS LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012801Jun 2021 → Dec 2024

Reason as filed by the promoterDue to revised sanction plan.

EXT52100009657Jun 2021 → May 2022

Reason as filed by the promotersecond covid-19 wave- seems to strenuous to resume construction activity such as material supply activity, labor shortage.

EXT52100025624Jun 2021 → Jun 2025

Reason as filed by the promoterThe delay in the completion of the project has arisen due to unforeseen circumstances, specifically the restructuring of the management owing to internal disputes among partners. The resolution of these disputes necessitated significant administrative and operational adjustments, including the replacement of key decision-makers and reallocation of responsibilities. Consequently, this transition period disrupted critical project timelines and delayed execution. With the disputes now amicably resolved and the restructuring completed, we have resumed work on the project with full diligence and co

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jan 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30 06 2023.pdf17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30 09 2023.pdf17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31 12 2023.pdf17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31 03 2024.pdf17 Apr 2025
Certificates of CA (Form 3)File: 30 6 23.pdf17 Apr 2025
Certificates of CA (Form 3)File: 30 9 23.pdf17 Apr 2025
Certificates of CA (Form 3)File: 31 12 23.pdf17 Apr 2025
Certificates of CA (Form 3)File: 31 3 24.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 06 2023.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 09 2023.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 31 12 2023.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 31 03 2024.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 A.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Document 540.pdf14 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 2023.pdf9 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 2024.pdf9 Feb 2025
Declaration in FORM BFile: FORM B.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30 06 2023.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30 09 2023.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31 12 2023.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31 03 2024.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30 06 2024.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30 09 2024.pdf7 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 06 2023.pdf7 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 09 2023.pdf7 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 31 12 2023.pdf7 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 31 03 2024.pdf7 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 06 2024.pdf7 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 09 2024.pdf7 Feb 2025
Declaration about Commencement CertificateFile: FORMAT D.pdf7 Feb 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A PHASE 3.pdf14 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 phase 3.pdf20 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase 3.pdf10 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FROM 5.pdf11 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf9 Nov 2022
Layout approvalFile: IOD.pdf8 Nov 2022
Building plan approvalFile: scan.pdf8 Nov 2022
Copy of Layout Approval (in case of layout)File: IOD.pdf8 Nov 2022
Building Plan Approval (IOD)File: scan.pdf8 Nov 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf8 Nov 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf8 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 18 LONGITUDE PHASE 3.pdf2 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf23 Nov 2021
Certificates of CA (Form 3)File: FORM 3.pdf23 Nov 2021
Declaration about Commencement CertificateFile: Document 5.pdf1 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf21 Oct 2021
Certificates of CA (Form 3)File: FORM 3.pdf21 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM -2A 19-20.pdf18 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM -2A 20-21.pdf18 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Commensment final cc.pdf15 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 GD SQUARE PROMOTERS LLP PHASE 3 20-21.pdf8 Sep 2021
Certificates of CA (Form 3)File: FORM 3 GD SQUARE PROMOTERS LLP PHASE 3 20-21.pdf8 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 4 GD SQUARE PROMOTERS LLP PHASE 3 20-21.pdf8 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Longitude Phase 3.pdf7 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Longitude Phase 3.pdf7 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Audit Report of Statutory CA (Form 5).pdf6 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Audit Report of Statutory CA (Form 5).pdf6 Aug 2021
Declaration in FORM BFile: Form B Mathews_compressed.pdf11 Nov 2020
Annual Audit Report of Statutory CA (Form 5)File: LONGITUDE.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5)File: LONGITUDE.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5)File: LONGITUDE.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5)File: GD Square Phase III Form 5.pdf25 Sep 2019
Declaration in FORM BFile: Form B GD PH3-compressed.pdf15 Jan 2019
Layout approvalFile: Sanction plan 1.pdf12 Jan 2019
Building plan approvalFile: Sanction plan 2.pdf12 Jan 2019
Building plan approvalFile: Sanction plan 3.pdf12 Jan 2019
Copy of Layout Approval (in case of layout)File: Sanction plan 1.pdf12 Jan 2019
Building Plan Approval (IOD)File: Sanction plan 2.pdf12 Jan 2019
Building Plan Approval (IOD)File: Sanction plan 3.pdf12 Jan 2019
PAN CardFile: Promoters LLP Pan Card.pdf9 Jan 2019
Copy of the legal title reportFile: PH3 Search Report_Mathews-compressed.pdf9 Jan 2019
Details of encumbrancesFile: Scan Self encumbarance.pdf9 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement-mathew-compressed.pdf9 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR LETTER PH3.pdf9 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng certificate phase 3 final.pdf9 Jan 2019
Certificates of CA (Form 3)File: CA Certficate -compressed.pdf9 Jan 2019
Proforma of Allotment letterFile: Alotment_letter-LLP 3.pdf9 Jan 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
18 LATITUDE289 LATITUDE ROAD NEAR BALAJI MANDIR PUNAWALE PUNE 41103378CompletedJun 2018Dec 2017

How this compares with Pune

59%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 18 LONGITUDE PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR BALAJI MANDIR13,700+ in Pune

2 km18 LONGITUDE PHASE 3Completed 67Lapsed / revoked 22Other 76Dot size: filed unitsN

Filed coordinates, straight-line distance. 165 registered projects within 2 km.

Builder: G D SQUARE PROMOTERS LLP

G D SQUARE PROMOTERS LLP has 2 registrations on MahaRERA, including 18 LONGITUDE PHASE 3 and 18 LONGITUDE PHASE 4. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that 18 LONGITUDE PHASE 3 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if 18 LONGITUDE PHASE 3 is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 18 LONGITUDE PHASE 3?

The registered promoter entity is G D SQUARE PROMOTERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 18 LONGITUDE PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 18 LONGITUDE PHASE 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 18 LONGITUDE PHASE 3?

The professionals named in the filing: Engineer: Akshay Sunil Chordiya; Engineer: Kaustubh Dhanaji Pawar; Chartered Accountant: Vinit D Achha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 18 LONGITUDE PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 18 LONGITUDE PHASE 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 18 LONGITUDE PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.