ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / 12TH AVENUE

Registration lapsed No litigation declared Residential / Group Housing project

12TH AVENUE

By SADGURU BABA DEVELOPERS LLP

RG-MH-78792 · RERA P51700008964 · Last updated on MahaRERA portal: 23 Feb 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
3 of 11Construction stages donefurthest along: Stilt Floor, 25%
1Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

12TH AVENUE is a Residential / Group Housing project by SADGURU BABA DEVELOPERS LLP in Thane, Maharashtra, registered with MahaRERA as P51700008964 on 19 Aug 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • Name12TH AVENUE
  • TypeResidential / Group Housing
  • Location
    • beverly park
    • mira road
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401107
  • Pincode401107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700008964
  • ReraGenie IDRG-MH-78792

Builder

  • NameSADGURU BABA DEVELOPERS LLP
  • Entity typePartnership
  • PartnersKUNTHESH PRAVIN CHHEDA, ZAIN NANALAL PALAN, POOJA KUNTHESH CHHEDA

Key dates

46 months past promisethis monthRegisteredAug 2017PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
12TH AVENUENA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 25%.

12TH AVENUE: 32% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor25%
Slabs of Super Structure13%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed7

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots7
Closed/Covered1
Open Space6

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,771 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3771.48
Proposed, not sanctioned2,587 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIRA ROAD BRANCH, SURYA SHOPPING CENTER, MIRA ROAD, THANE 401104

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBAC Planners & Engineers Pvt. Ltd.
EngineerM/s Pro-Tech consultant (Rajesh B Dubey)
PartnerRole in project
SADGURU BABA DEVELOPERS LLP-

Litigation declared1

CaseCourtStatus
7138/2018HIGH COURT OF BOMBAY CIVIL APPELLATE JURISDICTIONPENDING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000161435RAHUL SUDHIR BAISAKHIYAKUNTHESH PRAVIN CHHEDA30/11/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: Order.pdf23 Feb 2021
Certificates of CA (Form 5)File: SADGURU BABA DEV LLP - Form 5.pdf5 Nov 2018
Layout approvalFile: Copy of Layout Page-7.pdf31 Jul 2017
Layout approvalFile: Copy of Layout Page-3.pdf31 Jul 2017
Layout approvalFile: Copy of Layout Page-4.pdf31 Jul 2017
Layout approvalFile: Copy of Layout Page-5.pdf31 Jul 2017
Layout approvalFile: Copy of Layout Page-6.pdf31 Jul 2017
Layout approvalFile: Copy of Layout Page-1.pdf31 Jul 2017
Layout approvalFile: Copy of Layout Page-2.pdf31 Jul 2017
Details of encumbrancesFile: 3 encumbrance certificate-new.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Page-1.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Page-2.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Page-3.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Page-4.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Page-5.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Page-6.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Page-7.pdf31 Jul 2017
Certificates of CA (Form 3)File: 9 Form 3 CA Certificate-Revised.pdf31 Jul 2017
Proforma of Allotment letterFile: DRAFT MODEL AGREEMENT AND ALLOTMENT LETTER IS UNDER PROCESS.pdf31 Jul 2017
Layout approvalFile: 4 Layout Approval-1.pdf30 Jul 2017
Building plan approvalFile: 13 Building Plan Approval.pdf30 Jul 2017
PAN CardFile: 1 PAN CARD- Baba Developers.pdf30 Jul 2017
Copy of the legal title reportFile: 2 Title Certificate.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: 4 Layout Approval-1.pdf30 Jul 2017
Building Plan Approval (IOD)File: 13 Building Plan Approval.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 12 Commencement Certificate-1.pdf30 Jul 2017
Declaration in FORM BFile: 6 Declaration in Form B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 Form 1 Architect's Certificate.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 FORM 2 ENGINEER'S CERTIFICATE.pdf30 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 12TH AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near mira road7,600+ in Thane

2 km12TH AVENUECompleted 106Lapsed / revoked 79Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 294 registered projects within 2 km.

Builder: SADGURU BABA DEVELOPERS LLP

SADGURU BABA DEVELOPERS LLP has 1 registration on MahaRERA, including 12TH AVENUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that 12TH AVENUE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if 12TH AVENUE is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 12TH AVENUE?

The registered promoter entity is SADGURU BABA DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 12TH AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against 12TH AVENUE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for 12TH AVENUE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 12TH AVENUE?

The professionals named in the filing: Architect: BAC Planners & Engineers Pvt. Ltd.; Engineer: M/s Pro-Tech consultant (Rajesh B Dubey). Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 12TH AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 12TH AVENUE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 12TH AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.