Home / Browse projects / Mumbai Suburban, Maharashtra / 10 Square
10 Square
By VIJAY KAMDAR
RG-MH-08890 · RERA P51800004094 · Last updated on MahaRERA portal: 3 Jul 2020
Source: official MahaRERA filing
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 48 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
10 Square is a Residential / Group Housing project by VIJAY KAMDAR in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004094 on 7 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 48 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- Name10 Square
- TypeResidential / Group Housing
- Location
- jiwa mahle road
- east
- Andheri
- Mumbai Suburban
- 400069
- Pincode400069
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800004094
- ReraGenie IDRG-MH-08890
Builder
- NameVIJAY KAMDAR
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on7 Aug 2017
- Promised completion30 Jun 2022
- Revised completionRevised to 30 Jun 2022 (originally 30 Jun 2018)
- Buildings1 building record
- Documents filed19 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 10 Square | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jul 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
10 Square: 83% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 3 Jul 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed35
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SP ASSOCIATES |
| Partner | Role in project |
|---|---|
| VIJAY KAMDAR | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo The Real Estate Regulatory Authority 'A' Wing, SRA Building Anant Kanekar Road Bandra (East), Mumbai 400 051 Sir, Sub : APPLICATION FOR EXTENSION OF REGISTRATION OF PROJECT [Under Rule 7(1)] I hereby apply for renewal of registration certificate of the following project: 10 Square, Plot Bearing / CTS / Survey / Final Plot No.: 1 00/1/2 at Andheri, Andheri, Mumbai Suburban, 400069. Registered with the Authority vide Project Registration Certificate bearing No. P51800004094, which expires on 31/03/2019. The part occupation certificate (O.C) i.e. upto 10th floor has been issued by M.C.G.M. vid
Reason as filed by the promoterWe are eligible for additional FSI based on the width of the road. To consume this additional FSI we need additional height of the building. For this height we have approached Civil Aviation of India Delhi to grant us that additional height based on our eligibility.
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000195163 | SANTOSH YADWAD | VIJAY KAMDAR | 07/12/2020 |
| CC006000000196361 | PRATHAMESH GHARAT AND NEHA GHARAT | Vijay Chhotalal Kamdar | 22/03/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Jun 2020
Documents filed19
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: ArchOC letteropt.pdf | 3 Jul 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2242383_OC_signed.pdf | 27 Jun 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: 2242383_OC_signed.pdf | 27 Jun 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 17 Apr 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation Receipt ANDHERI.pdf | 17 Apr 2018 |
| Details of encumbrancesFile: Affidavit Cum Declaration - Andheri1.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Affidavit Cum Declaration - Andheri1.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG ANDHERI.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CERTIFICATE OF C A - 10 SQUARE.pdf | 31 Jul 2017 |
| Building plan approvalFile: IOD Andheri.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: IOD Andheri.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: DRAFT - AGREEMENT FOR SALE - (ANDHERI).pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: DRAFT ALLOTMENT LETTER ANDHERI FINAL.pdf | 29 Jul 2017 |
| Layout approvalFile: Approval Letter.pdf | 19 Jul 2017 |
| Layout approvalFile: Approved Layout Plan - Andheri.pdf | 19 Jul 2017 |
| Copy of the legal title reportFile: compressed_title.pdf | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Approval Letter.pdf | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Approved Layout Plan - Andheri.pdf | 19 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 19 filed documents as one ZIP, foldered, with a manifest
Keep 10 Square on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near east6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 247 registered projects within 2 km.
Nityanand Nagar Vibhag IV Cooperative Housing
BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED
FORTUNE ELITE
SAFFRON SPACES LIMITED
NICCO RESIDENCY
NEELKAMAL REALTY & CONSTRUCTION LLP
Parleshwar Aangan
Panom Developers LLP
ATHARV AARADHYAM
Atharv Infra LLP
Krishna Milan Heights
Milan Interbuilt Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: VIJAY KAMDAR
VIJAY KAMDAR has 1 registration on MahaRERA, including 10 Square. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if 10 Square is delayed beyond 30 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 10 Square?
The registered promoter entity is VIJAY KAMDAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 10 Square?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against 10 Square?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for 10 Square?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 10 Square?
The professionals named in the filing: Architect: SP ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 10 Square?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback