Vilas Javdekar Eco Homes: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
Vilas Javdekar Eco Homes has 11 registrations in this build, including Yashwin E,F,G and Yashwin A. Its filings disclose 8 earlier MahaRERA projects: 8 of 8 past projects completed on time. Litigation is declared on 6 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Yashwin E,F,G | Pune, Maharashtra | - | - | Completed |
| Yashwin A | Pune, Maharashtra | - | - | Completed |
| YashONE Phase - I | Pune, Maharashtra | - | - | Completed |
| YASH101 | Pune, Maharashtra | - | - | Completed |
| YashONE Pirangut Phase II | Pune, Maharashtra | - | - | Completed |
| Palladio Kharadi Central | Maharashtra | 350 | 86% | Registered |
| 38K Inclusive Housing | Maharashtra | 50 | 86% | Registered |
| VJ Central Avenue | Maharashtra | 778 | 87% | Registered |
| Portia Grande | Pune, Maharashtra | 132 | 98% | Registered |
| Palladio Kharadi Central Phase 2 | Maharashtra | 377 | 88% | Registered |
| VJ IndiWorks Kharadi Central | Pune, Maharashtra | 661 | 89% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Palash Plus | 31 Jan 2013 | 31 Dec 2012 | On time |
| Palash | 30 Jun 2013 | 30 Jun 2013 | On time |
| Shivalaya | 31 Jan 2015 | 31 Jan 2015 | On time |
| Yashwin B, C, D | 31 Dec 2016 | 30 Sep 2016 | On time |
| Yashwin E,F,G P52100000775 | 31 Dec 2018 | 1 Jan 1970 | On time |
| Yashwin A P52100013149 | 30 Sep 2020 | 1 Jan 1970 | On time |
| YashONE Phase - I P52100014585 | 30 Dec 2020 | 1 Jan 1970 | On time |
| YASH101 P52100016807 | 30 Mar 2021 | 1 Jan 1970 | On time |
Frequently asked questions
How do I verify Vilas Javdekar Eco Homes as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Vilas Javdekar Eco Homes?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Vilas Javdekar Eco Homes unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.