Vilas Javdekar Eco Homes: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Vilas Javdekar Eco Homes has 11 registrations in this build, including Yashwin E,F,G and Yashwin A. Its filings disclose 8 earlier MahaRERA projects: 8 of 8 past projects completed on time. Litigation is declared on 6 of its registrations.

11Registrations in this build
8Past projects disclosed
on timeMedian delivery slip
6Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Yashwin E,F,GPune, Maharashtra--Completed
Yashwin APune, Maharashtra--Completed
YashONE Phase - IPune, Maharashtra--Completed
YASH101Pune, Maharashtra--Completed
YashONE Pirangut Phase IIPune, Maharashtra--Completed
Palladio Kharadi CentralMaharashtra35086%Registered
38K Inclusive HousingMaharashtra5086%Registered
VJ Central AvenueMaharashtra77887%Registered
Portia GrandePune, Maharashtra13298%Registered
Palladio Kharadi Central Phase 2Maharashtra37788%Registered
VJ IndiWorks Kharadi CentralPune, Maharashtra66189%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Palash Plus
31 Jan 201331 Dec 2012On time
Palash
30 Jun 201330 Jun 2013On time
Shivalaya
31 Jan 201531 Jan 2015On time
Yashwin B, C, D
31 Dec 201630 Sep 2016On time
Yashwin E,F,G
P52100000775
31 Dec 20181 Jan 1970On time
Yashwin A
P52100013149
30 Sep 20201 Jan 1970On time
YashONE Phase - I
P52100014585
30 Dec 20201 Jan 1970On time
YASH101
P52100016807
30 Mar 20211 Jan 1970On time

Frequently asked questions

How do I verify Vilas Javdekar Eco Homes as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Vilas Javdekar Eco Homes?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Vilas Javdekar Eco Homes unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.