Raymond Realty Limited has 14 registrations on MahaRERA, including TEN X HABITAT Raymond Realty Tower F and TEN X HABITAT Raymond Realty Tower G. Its filings disclose 31 earlier MahaRERA projects: declares 23 of 24 past projects completed on time. Litigation is declared on 11 of its registrations.
Projects by this developer
Showing all 14 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Tenx District 9 Tower BPM1331012502633 | Sector 4, Thane, 400606 | 402 | 24% | 6 Mar 2026 | Registered |
| TEN X HABITAT Raymond Realty Tower FP51700034190 | Thane, Thane, 400606 | 391 | 98% | 25 Mar 2022 | Completed |
| Tenx District 9 Tower CPM1331012502634 | Sector 4, Thane, 400606 | 387 | 4% | 6 Mar 2026 | Registered |
| Tenx District 9 Tower APM1331012502632 | Sector 4, Thane, 400606 | 386 | 15% | 6 Mar 2026 | Registered |
| TEN X ERA Raymond Realty Tower AP51700053528 | J K Gram ( Panchpakhadi), Thane, 400606 | 302 | 91% | 10 Nov 2023 | Registered |
| TEN X HABITAT Raymond Realty Tower GP51700047152 | Thane, Thane, 400606 | 291 | 100% | 10 Oct 2022 | Completed |
| THE ADDRESS BY GS TOWER CP51700052008 | Village Panchpakhadi, Thane, 400606 | 218 | 94% | 19 Jul 2023 | Registered |
| The Address by GS Tower DP51700053947 | JK Gram, Thane, 400606 | 218 | 85% | 11 Dec 2023 | Registered |
| The Address by GS Tower FPR1335052500430 | Thane, Thane, 400606 | 218 | 38% | 30 Jul 2025 | Registered |
| The Address by GS Tower EP51700077861 | Thane, Thane, 400606 | 144 | 73% | 7 Nov 2024 | Registered |
| INVICTUS BY GSP51700052012 | Village Panchpakhadi, Thane, 400606 | 102 | 89% | 19 Jul 2023 | Registered |
| Invictus by GS Tower BPR1335052500426 | Thane, Thane, 400606 | 100 | 20% | 30 Jul 2025 | Registered |
| Raymond RetailPC1330002600856 | Sector 4, Thane, 400606 | 74 | 16% | 18 Jun 2026 | Registered |
| Park AvenueP51700077214 | JK Gram, Thane, 400606 | 65 | 85% | 31 Jul 2024 | Registered |
What this promoter declares as its own experience
Raymond Realty Limited declares experience on 31 earlier projects. 6 of them carry a registration number we could match on MahaRERA, of which 3 are registered under a different promoter name.
6 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
| Declared project | Registered to | Status |
|---|---|---|
| TEN X ERA Raymond Realty Tower B | Raymond Limited | Registered |
| The Address by GS Tower A | Raymond Limited | Registered |
| The Address by GS Bandra Tower A | TEN X REALTY LIMITED | Registered |
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Aashiyana | 6 Feb 2024 | 31 May 2024 | +4 months |
| TEN X HABITAT RAYMOND REALTY TOWER A and B | 31 Mar 2024 | 31 Mar 2024 | On time |
| TEN X HABITAT RAYMOND REALTY TOWER C | 31 Mar 2024 | 31 Mar 2024 | On time |
| TEN X HABITAT RAYMOND REALTY TOWER D | 30 Sep 2024 | 30 Mar 2024 | On time |
| TEN X Habitat Raymond Realty Tower A and B | 30 Mar 2025 | 6 Dec 2022 | On time |
| TEN X Habitat Raymond Realty Tower C | 30 Mar 2025 | 6 Dec 2022 | On time |
| TEN X HABITAT RAYMOND REALTY TOWER J | 30 Jun 2025 | 30 Jun 2025 | On time |
| TEN X Habitat Raymond Realty Tower J | 30 Jun 2025 | 30 Jun 2025 | On time |
| TEN X HABITAT Raymond Realty Tower E | 30 Sep 2025 | 27 Feb 2025 | On time |
| TEN X HABITAT RAYMOND REALTY TOWER D | 30 Sep 2025 | 30 Sep 2025 | On time |
| TEN X HABITAT RAYMOND REALTY TOWER E | 30 Sep 2025 | 30 Sep 2025 | On time |
| TEN X HABITAT RAYMOND REALTY TOWER K | 30 Sep 2025 | 30 Sep 2025 | On time |
Frequently asked questions
How do I verify Raymond Realty Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAJCR9076K1ZL on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Raymond Realty Limited?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Raymond Realty Limited unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.