Home / Browse projects / Pune, Maharashtra / AMITs BLOOMFIELD PHASE III - J AND K BUILDING
AMITs BLOOMFIELD PHASE III - J AND K BUILDING
By AMIT ENTERPRISES HOUSING LIMITED
RG-MH-11347 · RERA P52100005644 · Last updated on MahaRERA portal: 16 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- 8 complaints at MahaRERA
- Completion date moved by 57 months
- 6 extensions taken
- Rs 51.00 crore secured on the land, in favour of ABHIYAN MERCHANTTS PRIVATE LIMITED, SBICAP TRUSTEE COMPANY LTD
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMITs BLOOMFIELD PHASE III - J AND K BUILDING is a Residential / Group Housing project by AMIT ENTERPRISES HOUSING LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100005644 on 11 Aug 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 57 months from the original filing. 172 of the 252 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete. 8 complaints are on record with the regulator.
At a glance
Project
- NameAMITs BLOOMFIELD PHASE III - J AND K BUILDING
- TypeResidential / Group Housing
- Location
- Pune Bangalore Highway
- Ambegaon
- AMBEGAON Bk
- Haveli
- Pune
- 411046
- Pincode411046
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100005644
- ReraGenie IDRG-MH-11347
Builder
- NameAMIT ENTERPRISES HOUSING LIMITED
- Entity typeCompany
- CINU45200PN2008PLC131731
- GSTIN27AAGCA9192A1ZP
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- ChairpersonKISHOR GOVIND PATE
- DirectorsSanjeev Govind Pate, Rohan Kishor Pate
- Other registrations7 more →
- Completed3 of 8
- Past their filed date1
- Declared earlier projects10 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Aug 2017
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2021)
- Buildings2 building records
- Documents filed168 files
Current status
Figures as on 16 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| J Building | NA | 23 | 21 | 168 | 0 | 168 |
| K Building | NA | 23 | 0 | 84 | 0 | 84 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 92%.
J Building90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
K Building100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 75% |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed265
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| J Building | 44 | 132 | 176 |
| K Building | 24 | 65 | 89 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| J Building | NA | Rs 61.07 cr | Rs 58.00 cr |
| - | NA | Rs 34.05 cr | Rs 18.50 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | A&T Consultant |
| Architect | Manoj Tatooskar |
| Engineer | Surendra Sonawane |
| Chartered Accountant | SSAP & Associates LLP |
| Chartered Accountant | Dharini Naswa & Associates |
| Partner | Role in project |
|---|---|
| AMIT ENTERPRISES HOUSING LIMITED | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAcute economic crisis in the real estate market.
Reason as filed by the promoterWe encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector. The economic crises resulting from these factors impeded the progress of sale transactions, creating a substantial impact on the project's cash flow. Just as market conditions were showing signs of improvement, the emergence of the Covid-19 outbreak led to a massive downturn, further disrupting the project's financial stability. Consequently, the construction project experienced a considerable delay, causing moneta
Reason as filed by the promoterWe encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector. The economic crises resulting from these factors impeded the progress of sale transactions, creating a substantial impact on the project's cash flow. Just as market conditions were showing signs of improvement, the emergence of the Covid-19 outbreak led to a massive downturn, further disrupting the project's financial stability. Consequently, the construction project experienced a considerable delay, causing moneta
Reason as filed by the promoter1. Building K is 95 % completed and Building J is 80% Completed, as accordingly the project is 88% Completed. 2. Consent of 78.69 % of Allotees uploaded for Extension till date 30/09/2025. 3. Revised Form B uploaded in Other tab No. 2 and in main Application. 4. PERT Chart for the remaining completion work is uploaded in Other Tab No. 3 and also in Other Technical Tab of Main Application. 5. Explanatory Note for Delay in project Completion Uploaded in Other Tab No. 4 . 6. QPR till dates are updated
Reason as filed by the promoter1. The project consists of two wings - J & K. 2. Wing K is 100% complete and received OC. 3. Wing J is 85% complete. 4. Overall, the project stands at 95% completion with part OC. 5. The consent of 57% of allottees has been uploaded in support of this extension application. 6. Due to unavoidable circumstances, the project has been delayed. 7. The revised date of completion is now 31/03/2026. 8. We hereby assure the Hon’ble Authority that the project shall be fully completed within this stipulated time and the OC will be obtained. 9. We humbly request your kind approval of the extension to enab
Reason as filed by the promoter1. The project stands at 90% completion. 2. The consent of 59.62% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a. Sluggish Market Conditions b. Shortage of Labour and Materials c. Increase in Construction costs d. Financial Constraints 6. The revised date of completion is now 30/09/2026. 7. We hereby assure the Hon’ble Authority that the project shall be fully completed within this stipulated time and the OC will be obtai
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 1595/2008 | Civil Judge Sr Division Pune | Pending |
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000095741 | Mr. Amit Prakash Tembhurnikar | M/S Amit Enterprises Now known as Amit Enterprises Housing Ltd Thr its Director Sanjeev Govind Pate | 06/07/2021 |
| CC005000000279882 | ABHISHEK AND ARTI BHISE | AMIT ENTERPRISES HOUSING LIMITED | 19/12/2023 |
| CC12502346 | Mallikarjun Patil | AMIT ENTERPRISES HOUSING LIMITED | 10/07/2025 |
| CC12502783 | Nivrutti Sopan Patil | AMIT ENTERPRISES HOUSING LIMITED | 07/08/2025 |
| CC12600615 | Sachin Gorkshnath Dimble | AMIT ENTERPRISES HOUSING LIMITED | 02/02/2026 |
| CC12602500 | AMIT ENTERPRISES HOUSING LIMITED | Sonali Sachin Dimble | 29/04/2026 |
| CC12603003 | AMIT ENTERPRISES HOUSING LIMITED | Nivrutti Sopan Patil | 21/05/2026 |
| CC12603005 | AMIT ENTERPRISES HOUSING LIMITED | Abhishek Shirish Bhise | 21/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed168
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 168 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architech Certificate Amit Bloomfiled.pdf | 16 Jul 2026 |
| Withdrawal Update Form 2File: Form2-BLM-JK- Apr 2026 - Jun 2026.pdf | 16 Jul 2026 |
| Withdrawal Update Form 3File: CA Certificate - Amit Bloomfield Phase III - J K Bldg.pdf | 16 Jul 2026 |
| Withdrawal Update Form 1File: AMITS BLOOMFIELD PHASE III FORM 1.pdf | 13 Apr 2026 |
| Withdrawal Update Form 2File: Form2 BLM JK Jan 2026 Mar 2026.pdf | 13 Apr 2026 |
| Withdrawal Update Form 3File: BLOOMFIELD FORM 3 AS ON 31-03-2026.pdf | 13 Apr 2026 |
| Withdrawal Update Form 1File: Bloomfield J and K -form 1.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Bloomfield J and K -form 1.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Form2-BLM-JK-Oct 2025 - Dec 2025.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Form2-BLM-JK-Oct 2025 - Dec 2025.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Bloomfield - Booking J K Building - CA Certificate.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Bloomfield - Booking J K Building - CA Certificate.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Bloomfield J K Bld.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: Bloomfield J K Bld.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form2-BLM-JK-July 2025-Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form2-BLM-JK-July 2025-Sep 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - Bloomfield.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - Bloomfield.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 - Bloomfield.pdf | 17 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Bloomfield JK 2024 2025.pdf | 22 Sep 2025 |
| Form 5 (FY 2023-2024)File: Bloomfield - Form 5 23 - 24.pdf | 22 Sep 2025 |
| Form 1File: Form 1 Architect Certificate Bloomfield J K Building.pdf | 26 Jun 2025 |
| Form 2File: Form 2 - Bloomfield.pdf | 26 Jun 2025 |
| Form 3File: Form 3 - Bloomfield J K.pdf | 26 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Bloomfield- J K Bld.pdf | 26 Jun 2025 |
| Certificates of CA (Form 3)File: Form 3 - Bloomfield J K.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Bloomfield J K Building.pdf | 22 Apr 2025 |
| Certificates of CA (Form 3)File: Bloomfield- J K Bld.pdf | 22 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Bloomfield.pdf | 22 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A - Bloomfield.pdf | 22 Apr 2025 |
| Declaration in FORM BFile: Form B - Declaration Cum Affidavit.pdf | 18 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Bloomfield J K Building.pdf | 18 Mar 2025 |
| Other - TechnicalFile: PERT Chart.pdf | 18 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 - Bloomfield_compressed.pdf | 17 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bloomfield - Form 2.pdf | 16 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Bloomfield J K - Form 2A.pdf | 16 Jan 2025 |
| Certificates of CA (Form 3)File: Bloomfield J and K_compressed.pdf | 14 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Bloomfield J K.pdf | 10 Jan 2025 |
| Certificates of CA (Form 3)File: AEHL - Bloomfield J K - FORM 3 - 30-9-24 revised.pdf | 13 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 - Bloomfield_compressed.pdf | 23 Nov 2024 |
| Certificates of CA (Form 3)File: From3 Bloomfield.pdf | 23 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Bloomfield J K Building.pdf | 22 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-Bloomfield-JK-Jul24-Sep24.pdf | 22 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Bloomfield J K.pdf | 22 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-Bloomfield-JK-Jul24-Sep24.pdf | 22 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Bloomfield.pdf | 22 Oct 2024 |
| Layout approvalFile: Bloomfield Layout.pdf | 26 Jul 2024 |
| Building plan approvalFile: 3.pdf | 26 Jul 2024 |
| Building plan approvalFile: 10.pdf | 26 Jul 2024 |
| Building plan approvalFile: 11.pdf | 26 Jul 2024 |
| Building plan approvalFile: 12.pdf | 26 Jul 2024 |
| Building plan approvalFile: 13.pdf | 26 Jul 2024 |
| Building plan approvalFile: 14.pdf | 26 Jul 2024 |
| Building plan approvalFile: 15.pdf | 26 Jul 2024 |
| Building plan approvalFile: 16.pdf | 26 Jul 2024 |
| Building plan approvalFile: 17.pdf | 26 Jul 2024 |
| Building plan approvalFile: 18.pdf | 26 Jul 2024 |
| Building plan approvalFile: 19.pdf | 26 Jul 2024 |
| Building plan approvalFile: 20.pdf | 26 Jul 2024 |
| Building plan approvalFile: 21.pdf | 26 Jul 2024 |
| Layout approvalFile: Bloomfield Layout.pdf | 26 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: Bloomfield Layout.pdf | 26 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: Bloomfield Layout.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 3.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 10.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 11.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 12.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 13.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 14.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 15.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 16.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 17.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 18.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 19.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 20.pdf | 26 Jul 2024 |
| Building Plan Approval (IOD)File: 21.pdf | 26 Jul 2024 |
| Declaration about Commencement CertificateFile: Declaration about C C Bloomfield J K Building.pdf | 26 Jul 2024 |
| Declaration in FORM BFile: Affidavait cum Declaration.pdf | 26 Jul 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account For Real Estate Project.pdf | 26 Jul 2024 |
| Details of encumbrancesFile: No encumbrance.pdf | 19 Jul 2024 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Astonia Classic A1 to A4 Building | Village Undri Taluka Haveli Dist. Pune | 384 | Completed | Dec 2015 | Late, Nov 2016 |
| Amits Colori A to F Building | Village Undri Taluka Haveli District Pune | 288 | Completed | Dec 2012 | Mar 2012 |
| Astonia Royale A to J, Q and R Building | Village Ambegaon Budruk Taluka Haveli Dist Pune | 576 | Completed | Aug 2012 | Late, Nov 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 168 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AMITs BLOOMFIELD PHASE III - J AND K BUILDIN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ambegaon13,700+ in Pune
Filed coordinates, straight-line distance. 182 registered projects within 2 km.
Sai Nagari Phase I
Saikedareshwar Developers LLP
SAI NAGARI Phase V
Saikedareshwar Developers LLP
Sai Nagari Phase II
Saikedareshwar Developers LLP
Sai Nagari Phase IV
Saikedareshwar Developers LLP
Sai Nagari Phase III
Saikedareshwar Developers LLP
Bella Casa - Phase 1
Kakkad Infra LLP
Builder: AMIT ENTERPRISES HOUSING LIMITED
AMIT ENTERPRISES HOUSING LIMITED has 8 registrations on MahaRERA, including AMITs COLORI Phase-II H and I Building and AMITs COLORI Phase-III G Building. Its filings disclose 10 earlier MahaRERA projects: declares 1 of 6 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if AMITs BLOOMFIELD PHASE III - J AND K BUILDING is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMITs BLOOMFIELD PHASE III - J AND K BUILDING?
The registered promoter entity is AMIT ENTERPRISES HOUSING LIMITED, a company as per the filing. Its CIN U45200PN2008PLC131731 and GSTIN 27AAGCA9192A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMITs BLOOMFIELD PHASE III - J AND K BUILDING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AMITs BLOOMFIELD PHASE III - J AND K BUILDING?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AMITs BLOOMFIELD PHASE III - J AND K BUILDING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMITs BLOOMFIELD PHASE III - J AND K BUILDING?
The professionals named in the filing: Architect: A&T Consultant; Architect: Manoj Tatooskar; Engineer: Surendra Sonawane; Chartered Accountant: SSAP & Associates LLP; Chartered Accountant: Dharini Naswa & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMITs BLOOMFIELD PHASE III - J AND K BUILDING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback