Home / Browse projects / Pune, Maharashtra / AMITs BLOOMFIELD PHASE III - J AND K BUILDING

Registered No litigation declared Residential / Group Housing project

AMITs BLOOMFIELD PHASE III - J AND K BUILDING

By AMIT ENTERPRISES HOUSING LIMITED

RG-MH-11347 · RERA P52100005644 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 8 complaints at MahaRERA
  • Completion date moved by 57 months
  • 6 extensions taken
  • Rs 51.00 crore secured on the land, in favour of ABHIYAN MERCHANTTS PRIVATE LIMITED, SBICAP TRUSTEE COMPANY LTD

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 92%
80 of 252Units unsoldnot recorded sold or booked
8Complaints at MahaRERAon this registration
Jump to the 168 documents Report an error

AMITs BLOOMFIELD PHASE III - J AND K BUILDING is a Residential / Group Housing project by AMIT ENTERPRISES HOUSING LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100005644 on 11 Aug 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 57 months from the original filing. 172 of the 252 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete. 8 complaints are on record with the regulator.

At a glance

Project

  • NameAMITs BLOOMFIELD PHASE III - J AND K BUILDING
  • TypeResidential / Group Housing
  • Location
    • Pune Bangalore Highway
    • Ambegaon
    • AMBEGAON Bk
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100005644
  • ReraGenie IDRG-MH-11347

Builder

  • NameAMIT ENTERPRISES HOUSING LIMITED
  • Entity typeCompany
  • CINU45200PN2008PLC131731
  • GSTIN27AAGCA9192A1ZP
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • ChairpersonKISHOR GOVIND PATE
  • DirectorsSanjeev Govind Pate, Rohan Kishor Pate
  • Other registrations7 more →
  • Completed3 of 8
  • Past their filed date1
  • Declared earlier projects10 →

Key dates

1 months past promisethis monthRegisteredAug 2017First promiseDec 2021Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Aug 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2021)
  • Buildings2 building records
  • Documents filed168 files

Current status

68%172 of 252 units booked
80.4%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
J BuildingNA23211680168
K BuildingNA23084084

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 92%.

J Building90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
K Building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed265

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots265
Closed/Covered68
Open Space197
BuildingClosed/CoveredOpen SpaceTotal
J Building44132176
K Building246589

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area6,706 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofABHIYAN MERCHANTTS PRIVATE LIMITED, SBICAP TRUSTEE COMPANY LTD
Secured amountRs 51.00 crore
CERSAI search filedYes
Declared on18 Dec 2025

Approvals and building plan

Sanctioning authorityPMC
Permissible FSI26465.71
Proposed, not sanctioned26,466 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSenapati Bapat Road Pune
Estimated costRs 95.12 cr
Cost incurredRs 76.50 cr
Work done80.42%
BuildingWingEstimatedIncurred
J BuildingNARs 61.07 crRs 58.00 cr
-NARs 34.05 crRs 18.50 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA&T Consultant
ArchitectManoj Tatooskar
EngineerSurendra Sonawane
Chartered AccountantSSAP & Associates LLP
Chartered AccountantDharini Naswa & Associates
PartnerRole in project
AMIT ENTERPRISES HOUSING LIMITED-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005537Dec 2021 → Dec 2022

Reason as filed by the promoterAcute economic crisis in the real estate market.

EXT52100018914Dec 2021 → Jun 2024

Reason as filed by the promoterWe encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector. The economic crises resulting from these factors impeded the progress of sale transactions, creating a substantial impact on the project's cash flow. Just as market conditions were showing signs of improvement, the emergence of the Covid-19 outbreak led to a massive downturn, further disrupting the project's financial stability. Consequently, the construction project experienced a considerable delay, causing moneta

EXT52100024376Dec 2021 → Mar 2025

Reason as filed by the promoterWe encountered significant challenges in completing the project within the stipulated timeline, primarily due to sluggish market conditions and a downturn in the real estate sector. The economic crises resulting from these factors impeded the progress of sale transactions, creating a substantial impact on the project's cash flow. Just as market conditions were showing signs of improvement, the emergence of the Covid-19 outbreak led to a massive downturn, further disrupting the project's financial stability. Consequently, the construction project experienced a considerable delay, causing moneta

EXT52100027486Dec 2021 → Sep 2025

Reason as filed by the promoter1. Building K is 95 % completed and Building J is 80% Completed, as accordingly the project is 88% Completed. 2. Consent of 78.69 % of Allotees uploaded for Extension till date 30/09/2025. 3. Revised Form B uploaded in Other tab No. 2 and in main Application. 4. PERT Chart for the remaining completion work is uploaded in Other Tab No. 3 and also in Other Technical Tab of Main Application. 5. Explanatory Note for Delay in project Completion Uploaded in Other Tab No. 4 . 6. QPR till dates are updated

EA11092502556Dec 2021 → Mar 2026

Reason as filed by the promoter1. The project consists of two wings - J & K. 2. Wing K is 100% complete and received OC. 3. Wing J is 85% complete. 4. Overall, the project stands at 95% completion with part OC. 5. The consent of 57% of allottees has been uploaded in support of this extension application. 6. Due to unavoidable circumstances, the project has been delayed. 7. The revised date of completion is now 31/03/2026. 8. We hereby assure the Hon’ble Authority that the project shall be fully completed within this stipulated time and the OC will be obtained. 9. We humbly request your kind approval of the extension to enab

EA21032620322Dec 2021 → Sep 2026

Reason as filed by the promoter1. The project stands at 90% completion. 2. The consent of 59.62% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a. Sluggish Market Conditions b. Shortage of Labour and Materials c. Increase in Construction costs d. Financial Constraints 6. The revised date of completion is now 30/09/2026. 7. We hereby assure the Hon’ble Authority that the project shall be fully completed within this stipulated time and the OC will be obtai

Litigation declared1

CaseCourtStatus
1595/2008Civil Judge Sr Division PunePending

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC005000000095741Mr. Amit Prakash TembhurnikarM/S Amit Enterprises Now known as Amit Enterprises Housing Ltd Thr its Director Sanjeev Govind Pate06/07/2021
CC005000000279882ABHISHEK AND ARTI BHISEAMIT ENTERPRISES HOUSING LIMITED19/12/2023
CC12502346Mallikarjun PatilAMIT ENTERPRISES HOUSING LIMITED10/07/2025
CC12502783Nivrutti Sopan PatilAMIT ENTERPRISES HOUSING LIMITED07/08/2025
CC12600615Sachin Gorkshnath DimbleAMIT ENTERPRISES HOUSING LIMITED02/02/2026
CC12602500AMIT ENTERPRISES HOUSING LIMITEDSonali Sachin Dimble29/04/2026
CC12603003AMIT ENTERPRISES HOUSING LIMITEDNivrutti Sopan Patil21/05/2026
CC12603005AMIT ENTERPRISES HOUSING LIMITEDAbhishek Shirish Bhise21/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed168

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 168 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architech Certificate Amit Bloomfiled.pdf16 Jul 2026
Withdrawal Update Form 2File: Form2-BLM-JK- Apr 2026 - Jun 2026.pdf16 Jul 2026
Withdrawal Update Form 3File: CA Certificate - Amit Bloomfield Phase III - J K Bldg.pdf16 Jul 2026
Withdrawal Update Form 1File: AMITS BLOOMFIELD PHASE III FORM 1.pdf13 Apr 2026
Withdrawal Update Form 2File: Form2 BLM JK Jan 2026 Mar 2026.pdf13 Apr 2026
Withdrawal Update Form 3File: BLOOMFIELD FORM 3 AS ON 31-03-2026.pdf13 Apr 2026
Withdrawal Update Form 1File: Bloomfield J and K -form 1.pdf14 Jan 2026
Withdrawal Update Form 1File: Bloomfield J and K -form 1.pdf14 Jan 2026
Withdrawal Update Form 2File: Form2-BLM-JK-Oct 2025 - Dec 2025.pdf14 Jan 2026
Withdrawal Update Form 2File: Form2-BLM-JK-Oct 2025 - Dec 2025.pdf14 Jan 2026
Withdrawal Update Form 3File: Bloomfield - Booking J K Building - CA Certificate.pdf14 Jan 2026
Withdrawal Update Form 3File: Bloomfield - Booking J K Building - CA Certificate.pdf14 Jan 2026
Withdrawal Update Form 1File: Bloomfield J K Bld.pdf17 Oct 2025
Withdrawal Update Form 1File: Bloomfield J K Bld.pdf17 Oct 2025
Withdrawal Update Form 2File: Form2-BLM-JK-July 2025-Sep 2025.pdf17 Oct 2025
Withdrawal Update Form 2File: Form2-BLM-JK-July 2025-Sep 2025.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 - Bloomfield.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 - Bloomfield.pdf17 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 - Bloomfield.pdf17 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A - Bloomfield JK 2024 2025.pdf22 Sep 2025
Form 5 (FY 2023-2024)File: Bloomfield - Form 5 23 - 24.pdf22 Sep 2025
Form 1File: Form 1 Architect Certificate Bloomfield J K Building.pdf26 Jun 2025
Form 2File: Form 2 - Bloomfield.pdf26 Jun 2025
Form 3File: Form 3 - Bloomfield J K.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Bloomfield- J K Bld.pdf26 Jun 2025
Certificates of CA (Form 3)File: Form 3 - Bloomfield J K.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Bloomfield J K Building.pdf22 Apr 2025
Certificates of CA (Form 3)File: Bloomfield- J K Bld.pdf22 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Bloomfield.pdf22 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A - Bloomfield.pdf22 Apr 2025
Declaration in FORM BFile: Form B - Declaration Cum Affidavit.pdf18 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Bloomfield J K Building.pdf18 Mar 2025
Other - TechnicalFile: PERT Chart.pdf18 Mar 2025
Certificates of CA (Form 3)File: Form 3 - Bloomfield_compressed.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Bloomfield - Form 2.pdf16 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Bloomfield J K - Form 2A.pdf16 Jan 2025
Certificates of CA (Form 3)File: Bloomfield J and K_compressed.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: Bloomfield J K.pdf10 Jan 2025
Certificates of CA (Form 3)File: AEHL - Bloomfield J K - FORM 3 - 30-9-24 revised.pdf13 Dec 2024
Certificates of CA (Form 3)File: Form 3 - Bloomfield_compressed.pdf23 Nov 2024
Certificates of CA (Form 3)File: From3 Bloomfield.pdf23 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Bloomfield J K Building.pdf22 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2-Bloomfield-JK-Jul24-Sep24.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Bloomfield J K.pdf22 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A-Bloomfield-JK-Jul24-Sep24.pdf22 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Bloomfield.pdf22 Oct 2024
Layout approvalFile: Bloomfield Layout.pdf26 Jul 2024
Building plan approvalFile: 3.pdf26 Jul 2024
Building plan approvalFile: 10.pdf26 Jul 2024
Building plan approvalFile: 11.pdf26 Jul 2024
Building plan approvalFile: 12.pdf26 Jul 2024
Building plan approvalFile: 13.pdf26 Jul 2024
Building plan approvalFile: 14.pdf26 Jul 2024
Building plan approvalFile: 15.pdf26 Jul 2024
Building plan approvalFile: 16.pdf26 Jul 2024
Building plan approvalFile: 17.pdf26 Jul 2024
Building plan approvalFile: 18.pdf26 Jul 2024
Building plan approvalFile: 19.pdf26 Jul 2024
Building plan approvalFile: 20.pdf26 Jul 2024
Building plan approvalFile: 21.pdf26 Jul 2024
Layout approvalFile: Bloomfield Layout.pdf26 Jul 2024
Copy of Layout Approval (in case of layout)File: Bloomfield Layout.pdf26 Jul 2024
Copy of Layout Approval (in case of layout)File: Bloomfield Layout.pdf26 Jul 2024
Building Plan Approval (IOD)File: 3.pdf26 Jul 2024
Building Plan Approval (IOD)File: 10.pdf26 Jul 2024
Building Plan Approval (IOD)File: 11.pdf26 Jul 2024
Building Plan Approval (IOD)File: 12.pdf26 Jul 2024
Building Plan Approval (IOD)File: 13.pdf26 Jul 2024
Building Plan Approval (IOD)File: 14.pdf26 Jul 2024
Building Plan Approval (IOD)File: 15.pdf26 Jul 2024
Building Plan Approval (IOD)File: 16.pdf26 Jul 2024
Building Plan Approval (IOD)File: 17.pdf26 Jul 2024
Building Plan Approval (IOD)File: 18.pdf26 Jul 2024
Building Plan Approval (IOD)File: 19.pdf26 Jul 2024
Building Plan Approval (IOD)File: 20.pdf26 Jul 2024
Building Plan Approval (IOD)File: 21.pdf26 Jul 2024
Declaration about Commencement CertificateFile: Declaration about C C Bloomfield J K Building.pdf26 Jul 2024
Declaration in FORM BFile: Affidavait cum Declaration.pdf26 Jul 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account For Real Estate Project.pdf26 Jul 2024
Details of encumbrancesFile: No encumbrance.pdf19 Jul 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Astonia Classic A1 to A4 BuildingVillage Undri Taluka Haveli Dist. Pune384CompletedDec 2015Late, Nov 2016
Amits Colori A to F BuildingVillage Undri Taluka Haveli District Pune288CompletedDec 2012Mar 2012
Astonia Royale A to J, Q and R BuildingVillage Ambegaon Budruk Taluka Haveli Dist Pune576CompletedAug 2012Late, Nov 2013

How this compares with Pune

68%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 57 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AMITs BLOOMFIELD PHASE III - J AND K BUILDIN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ambegaon13,700+ in Pune

2 kmAMITs BLOOMFIELD PHASE ICompleted 82Lapsed / revoked 35Other 65Dot size: filed unitsN

Filed coordinates, straight-line distance. 182 registered projects within 2 km.

Builder: AMIT ENTERPRISES HOUSING LIMITED

AMIT ENTERPRISES HOUSING LIMITED has 8 registrations on MahaRERA, including AMITs COLORI Phase-II H and I Building and AMITs COLORI Phase-III G Building. Its filings disclose 10 earlier MahaRERA projects: declares 1 of 6 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AMITs BLOOMFIELD PHASE III - J AND K BUILDING is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AMITs BLOOMFIELD PHASE III - J AND K BUILDING?

The registered promoter entity is AMIT ENTERPRISES HOUSING LIMITED, a company as per the filing. Its CIN U45200PN2008PLC131731 and GSTIN 27AAGCA9192A1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AMITs BLOOMFIELD PHASE III - J AND K BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AMITs BLOOMFIELD PHASE III - J AND K BUILDING?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AMITs BLOOMFIELD PHASE III - J AND K BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AMITs BLOOMFIELD PHASE III - J AND K BUILDING?

The professionals named in the filing: Architect: A&T Consultant; Architect: Manoj Tatooskar; Engineer: Surendra Sonawane; Chartered Accountant: SSAP & Associates LLP; Chartered Accountant: Dharini Naswa & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AMITs BLOOMFIELD PHASE III - J AND K BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AMITs BLOOMFIELD PHASE III - J AND K BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AMITs BLOOMFIELD PHASE III - J AND K BUILDIN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.