New projects and RERA data in Vijayanagara district, Karnataka
117 projects are registered in Vijayanagara district: 473 units across the 8 that file a count, 14 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 117 covered registrations, 9 have revised their promised completion date and 0 declare litigation. Of the 2 that file a booking figure, the median is 28% booked as of the current data. Every figure comes from the projects' own RERA Karnataka filings.
How far Vijayanagara possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 9 of 117 projects (8%) have moved at least once; the median move is 9 months and the longest is 12 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Where in Vijayanagara: projects by taluka
117 of the 117 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Hospet | 107 | 91% |
| Harapanahalli | 6 | 5% |
| 3 other talukas | 4 | 3% |
Projects in Vijayanagara
Showing 1 to 60 of 117 projects.
Largest first, by the unit count in the filing.
Developers active in Vijayanagara
KARNATAKA SLUM DEVELOPMENT BOARD (6), M/S Suraksha Enterprises (3), G MALLINATH (3), S B INFRA PROJECTS (2), Karnataka housing board (2), SAMRUDDHI GREENS (2). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Vijayanagara projects listed above?
Compare each project against its neighbours, not against the brochure. Of the 2 projects on this page that file a booking figure, the median is 28% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Vijayanagara project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What if a Vijayanagara project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own RERA Karnataka filings, and we read every report.
Report an errorShare feedbackData from official RERA Karnataka filings.