ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Zinnia Row Houses

Completed No litigation declared Residential / Group Housing project

Zinnia Row Houses

By Magarpatta Township Development & Construction Co. Ltd.

RG-MH-48952 · RERA P52100018373 · Last updated on MahaRERA portal: 1 Oct 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2021Possession promisedregistration recorded completed
12 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 98%
0Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

Zinnia Row Houses is a Residential / Group Housing project by Magarpatta Township Development & Construction Co. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100018373 on 26 Oct 2018. The registration is recorded completed; possession was promised by 30 Oct 2021.

At a glance

Project

  • NameZinnia Row Houses
  • TypeResidential / Group Housing
  • Location
    • Magarpatta Police Station Road
    • Adjacent to Magarpatta City
    • Hadapsar
    • Haveli
    • Pune
    • 411013
  • Pincode411013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018373
  • ReraGenie IDRG-MH-48952

Builder

  • NameMagarpatta Township Development & Construction Co. Ltd.
  • Entity typeCompany
  • CINU45201MH1994PLC082257
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorSatish Dattatray Magar
  • DirectorUmesh Dattatray Magar
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2018PromisedOct 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on26 Oct 2018
  • Promised completion30 Oct 2021
  • Revised completionNone
  • Buildings2 building records
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
R1 to R5NA40000
R6 to R11NA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 98%.

R1 to R588%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.91%
R6 to R1186%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 1 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes91%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
R1 to R511
R6 to R1111

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,925 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2009.82
Proposed, not sanctioned2,010 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSolapur Bazar Road Off East Street Pune 411001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArch Prakash Deshmukh
EngineerMr Achyut Watve
Chartered AccountantD R Barve & Co
Chartered AccountantSDB & Company
PartnerRole in project
Magarpatta Township Development & Construction Co. Ltd.-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Sep 2021

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf1 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final OC.pdf7 Sep 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf31 May 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Row House 4-7-9.pdf8 Apr 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Row House 2-3-5-6.pdf22 Feb 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Row House 8-10-11.pdf22 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Annual Report of Statement of Accounts.pdf2 Jan 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 -Annual Report Statement of Accounts - March 2020.pdf2 Jan 2021
Annual Audit Report of Statutory CA (Form 5)File: Form 5 - Annual Report of Statement of Accounts.pdf7 Oct 2019
Proforma of Allotment letterFile: Agreement.pdf12 Jun 2019
Certificates of CA (Form 3)File: CA Certificate.pdf19 Oct 2018
Layout approvalFile: Layout with Parking.pdf17 Oct 2018
Building plan approvalFile: RH 1 to 5.pdf17 Oct 2018
Building plan approvalFile: RH 6 to 11.pdf17 Oct 2018
PAN CardFile: PAN Card.pdf17 Oct 2018
Copy of the legal title reportFile: Search Report.pdf17 Oct 2018
Details of encumbrancesFile: Encumbrance Certificate.pdf17 Oct 2018
Copy of Layout Approval (in case of layout)File: Layout with Parking.pdf17 Oct 2018
Building Plan Approval (IOD)File: RH 1 to 5.pdf17 Oct 2018
Building Plan Approval (IOD)File: RH 6 to 11.pdf17 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf17 Oct 2018
Declaration in FORM BFile: Affidavit.pdf17 Oct 2018
Proforma of Allotment letterFile: Allotment Letter - Agreement.pdf17 Oct 2018

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Summer Court138 139 Magarpatta City Hadapsar Pune 411 0138CompletedApr 2017Apr 2017
Magarpatta City Annexe134 Magarpatta City Hadapsar Pune 411 013444CompletedMar 2014Mar 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Zinnia Row Houses on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Adjacent to Magarpatta City13,700+ in Pune

2 kmZinnia Row HousesCompleted 48Lapsed / revoked 23Other 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 164 registered projects within 2 km.

Builder: Magarpatta Township Development & Construction Co. Ltd.

Magarpatta Township Development & Construction Co. Ltd. has 2 registrations on MahaRERA, including Zinnia Row Houses and Nova Elegance. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Zinnia Row Houses is delayed beyond 30 Oct 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Zinnia Row Houses?

The registered promoter entity is Magarpatta Township Development & Construction Co. Ltd., a company as per the filing. Its CIN U45201MH1994PLC082257 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Zinnia Row Houses?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Zinnia Row Houses?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Zinnia Row Houses?

The professionals named in the filing: Architect: Arch Prakash Deshmukh; Engineer: Mr Achyut Watve; Chartered Accountant: D R Barve & Co; Chartered Accountant: SDB & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Zinnia Row Houses?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Zinnia Row Houses. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Zinnia Row Houses to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.