Home / Browse projects / Pune, Maharashtra / Dosti Greenscapes - Phase 2
Dosti Greenscapes - Phase 2
RG-MH-40983 · RERA P52100051041 · Last updated on MahaRERA portal: 22 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Rs 85.00 crore secured on the land, in favour of ICICI BANK LIMITED
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Dosti Greenscapes - Phase 2 is a Residential / Group Housing project by DOSTI REALTY LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100051041 on 22 May 2023. Possession is promised by 30 Apr 2028. 151 of the 258 units on this registration are recorded sold or booked, and 17 of 33 construction stages are filed complete.
At a glance
Project
- NameDosti Greenscapes - Phase 2
- TypeResidential / Group Housing
- Location
- Haveli
- Hadapsar
- Hadapsar
- Haveli
- Pune
- 411013
- Pincode411013
- RERA no.P52100051041
- ReraGenie IDRG-MH-40983
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 May 2023
- Promised completion30 Apr 2028
- Revised completionNone
- Buildings3 building records
- Documents filed96 files
Current status
Figures as on 22 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Dosti Greenscapes - Phase 2 - Wing E / C2 Wing | NA | 23 | 21 | 86 | 0 | 86 |
| Dosti Greenscapes - Phase 2 - Wing F / C1B Wing | NA | 23 | 21 | 86 | 0 | 86 |
| Dosti Greenscapes - Phase 2 - Wing G / C2A Wing | NA | 23 | 21 | 86 | 0 | 86 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.
Dosti Greenscapes - Phase 2 - Wing E / C2 Wing73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 2% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Dosti Greenscapes - Phase 2 - Wing F / C1B Wing74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Dosti Greenscapes - Phase 2 - Wing G / C2A Wing46%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 10% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed342
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Dosti Greenscapes - Phase 2 - Wing E / C2 Wing | 128 | 128 |
| Dosti Greenscapes - Phase 2 - Wing F / C1B Wing | 86 | 86 |
| Dosti Greenscapes - Phase 2 - Wing G / C2A Wing | 128 | 128 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| THE INDIAN HUME PIPE COMPANY LIMITED | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Dosti Greenscapes - Phase 2 - Wing E / C2 Wing | NA | Rs 42.01 cr | Rs 19.13 cr |
| Dosti Greenscapes - Phase 2 - Wing F / C1B Wing | NA | Rs 42.01 cr | Rs 19.13 cr |
| Dosti Greenscapes - Phase 2 - Wing G / C2A Wing | NA | Rs 42.01 cr | Rs 19.13 cr |
| - | NA | Rs 12.00 cr | Rs 38.40 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Architect Jay R Vora |
| Engineer | Paras R Vishwakarma |
| Engineer | SWAPNIL LONDHE |
| Engineer | Vaibhav Raghunath Kalambate |
| Chartered Accountant | Manish Bardia And Co |
| Chartered Accountant | BAGADE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| DOSTI REALTY LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Apr 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 May 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Apr 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2028
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A - DRL Dosti Greenscapes Ph 2.pdf | 22 Jun 2026 |
| Withdrawal Update Form 1File: DRL Greenscapes Ph 2 Form 1 Mar26.pdf | 6 May 2026 |
| Withdrawal Update Form 2File: DRL Greenscapes Ph 2 Form 2 Mar26.pdf | 6 May 2026 |
| Withdrawal Update Form 3File: DRL Greenscapes Ph 2 Form 3 Mar26.pdf | 6 May 2026 |
| Withdrawal Update Form 1File: DRL Greenscapes Ph 2 Form 1 Dec25.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: DRL Greenscapes Ph 2 Form 2 Dec25.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: DRL Greenscapes Ph 2 Form 3 Dec25.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: DRL Greenscapes Ph 2 Form 1 Sept25.pdf | 24 Nov 2025 |
| Withdrawal Update Form 2File: DRL Greenscapes Ph 2 Form 2 Sept25.pdf | 24 Nov 2025 |
| Withdrawal Update Form 3File: DRL Greenscapes Ph 2 Form 3 Sept25.pdf | 24 Nov 2025 |
| Form 5 (FY 2024-2025)File: DRL Pune PH2.pdf | 12 Nov 2025 |
| Form 1File: Dosti Greenscape PH2 Arch certificate June2025.pdf | 25 Jul 2025 |
| Form 2File: Dosti Greenscape PH2 Engineer certificate June2025.pdf | 25 Jul 2025 |
| Form 3File: Dosti Greenscape PH2 CA certificate June2025.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DRL Greenscape PH2 Sold Unsold June2025.pdf | 25 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: DOsti Greenscape PH2 Sold Unsold.pdf | 14 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dosti Greenscape PH2 Achitect's certificate March2025.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dosti Greenscape PH2 CA Certificate April2025.pdf | 11 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dosti Greenscape PH2 Engineer certificate March2025.pdf | 11 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Dosti Greenscape PH2 Quality certificate March2025.pdf | 11 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dosti Greenscape Phase-2 Architect certificate.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dosti Greenscape Phase-2 CA certificate.pdf | 16 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dosti Greenscape Phase-2 Engineer certificate.pdf | 16 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Dosti Greenscape Phase-2 Sold Unsold.pdf | 16 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Dosti Greenscape PH2.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dosti Greenscape PH2 Form1 Sep24.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dosti Greenscape PH2 Form3 Sep24.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dosti Greenscape PH2 Form2 Sep24.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Dosti Greenscape Phase-2.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 2-2 Dosti GreenScape PH2.pdf | 9 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dosti Greenscape PH2- Form1 Arch June 24.pdf | 22 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dosti Greenscape PH2- Form2 Engg June 24.pdf | 22 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dosti Greenscape PH2- Form3 CA June 24.pdf | 22 Jul 2024 |
| Proforma of Agreement for saleFile: Revised - Greenscapes Phase 2 - AFS.pdf | 31 May 2024 |
| Deviation Report with respect to model copy of AgreementFile: Revised - Greenscapes Phase 2 - Deviation.pdf | 31 May 2024 |
| Disclosure of sold/ booked inventoryFile: Dosti Greenscape Phase-2.pdf | 10 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate Dosti Greenscape Phase 2 March 2024.pdf | 25 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Dosti Greenscape Phase 2 March 2024.pdf | 25 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate DG Phase 2.pdf | 23 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Dosti Greenscape Phase-2.pdf | 23 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate DGP Phase 2.pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Wing D E F DG Phase 2.pdf | 17 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate DGP Phase 2.pdf | 16 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg-Form-2-DGP-PH-II.pdf | 18 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA- Form-3-DGP-PH-II.pdf | 13 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: DG Phase 2 Wing C1B Wing C2A.pdf | 25 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Dosti Greenscapes Phase 2.pdf | 23 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Dosti Greenscapes Phase 2.pdf | 12 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Dosti Greenscapes Phase 2.pdf | 18 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Greenscape Ph 2.pdf | 10 Jul 2023 |
| Other - TechnicalFile: Clarification on CC - Greenscapes Phase 2.pdf | 16 May 2023 |
| Layout approvalFile: Pune RERA Annexure - R2-Model 456.pdf | 9 May 2023 |
| Copy of Layout Approval (in case of layout)File: Pune RERA Annexure - R2-Model 456.pdf | 9 May 2023 |
| Building plan approvalFile: Wing C2A - Sanctioned_compressed.pdf | 26 Apr 2023 |
| Layout approvalFile: 2 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Layout approvalFile: 3 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Layout approvalFile: 4 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Layout approvalFile: 5 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Layout approvalFile: 6 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Layout approvalFile: 7 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Layout approvalFile: 8 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Building plan approvalFile: Wing C1B - Sanctioned_compressed.pdf | 26 Apr 2023 |
| Building plan approvalFile: Wing C2 - Sanctioned_compressed.pdf | 26 Apr 2023 |
| PAN CardFile: 1 PAN Card.pdf | 26 Apr 2023 |
| Copy of the legal title reportFile: 1 Copy of the legal title report.pdf | 26 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: Financial And Legal Encumberances Certificate.pdf | 26 Apr 2023 |
| Details of encumbrances concerned to LegalFile: Financial And Legal Encumberances Certificate.pdf | 26 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 2 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 3 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 4 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 5 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 6 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 7 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: 8 Copy of Layout Approval (in case of layout).pdf | 26 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Wing C1B - Sanctioned_compressed.pdf | 26 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Wing C2 - Sanctioned_compressed.pdf | 26 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Wing C2A - Sanctioned_compressed.pdf | 26 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Dosti Greenscapes - Phase 2 - CC_compressed.pdf | 26 Apr 2023 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf | 26 Apr 2023 |
| Declaration in FORM BFile: Affidavit Cum Declaration - Form B- DKG.pdf | 26 Apr 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Dosti Imperia - Dosti Majesta | Chitalsar Manpada Ghodbunder Road Majivade Taluka and District Thane | 56 | Completed | Dec 2018 | Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Dosti Greenscapes - Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hadapsar13,700+ in Pune
Dosti Greenscapes - Phase 1
DOSTI REALTY LIMITED
Dosti Greenscapes - Phase 3
DOSTI REALTY LIMITED
Dosti Greenscapes - Phase 5
DOSTI REALTY LIMITED
Dosti Greenscapes - Phase 4
DOSTI REALTY LIMITED
Songs From The Wood - Phase 1
Total Environment Building Systems Private
Songs From The Wood -Phase 2
Total Environment Building Systems Private
Builder: DOSTI REALTY LIMITED
DOSTI REALTY LIMITED has 5 registrations on MahaRERA, including Dosti Greenscapes - Phase 1 and Dosti Greenscapes - Phase 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Dosti Greenscapes - Phase 2 is delayed beyond 30 Apr 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Dosti Greenscapes - Phase 2?
The registered promoter entity is DOSTI REALTY LIMITED, a company as per the filing. Its CIN U70102MH2008PLC178101 and GSTIN 27AACCD7714K1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Dosti Greenscapes - Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Dosti Greenscapes - Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Dosti Greenscapes - Phase 2?
The professionals named in the filing: Architect: Architect Jay R Vora; Engineer: Paras R Vishwakarma; Engineer: SWAPNIL LONDHE; Engineer: Vaibhav Raghunath Kalambate; Chartered Accountant: Manish Bardia And Co; Chartered Accountant: BAGADE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Dosti Greenscapes - Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback