Home / Browse projects / Raigarh, Maharashtra / Yogakshema Residency Phase-I

Registered No litigation declared Residential / Group Housing project

Yogakshema Residency Phase-I

By Superb Maa Infra and Housing LLP

RG-MH-65284 · RERA P52000034419 · Last updated on MahaRERA portal: 1 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 7 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 7 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 83%
94 of 434Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

Yogakshema Residency Phase-I is a Residential / Group Housing project by Superb Maa Infra and Housing LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000034419 on 5 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 7 months from the original filing. 340 of the 434 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameYogakshema Residency Phase-I
  • TypeResidential / Group Housing
  • Location
    • Giravale Village Road
    • Giravale
    • Panvel
    • Raigarh
    • 410221
  • Pincode410221
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000034419
  • ReraGenie IDRG-MH-65284

Builder

  • NameSuperb Maa Infra and Housing LLP
  • Entity typePartnership
  • PartnersSugat Gyaneshwar Waghmare, Milind Pralhad Kamble, Vishal Maheshkumar Dave, Vaibhav Dilip Wankhade
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2022First promiseMay 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 May 2026)
  • Buildings2 building records
  • Documents filed103 files

Current status

78%340 of 434 units booked
64.4%Work done, per cost certificate

Figures as on 1 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block ANA29272120212
Block BNA292820715222

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 83%.

Block A57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises62%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Block B42%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure83%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises33%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes57%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed854

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots854
Closed/Covered207
Open Space647
BuildingClosed/CoveredOpen SpaceTotal
Block A104339443
Block B103308411

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area31,830 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Narayan Mahad BhomkarGiravaleRaigarh

Approvals and building plan

Sanctioning authorityMaharashtra State Road Development Corporation
Permissible FSI40337.98
Proposed, not sanctioned40,338 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGalleria Shopping Mall, Hiranandani Gardens, Powai, Mumbai 400076
Estimated costRs 179.00 cr
Cost incurredRs 115.23 cr
Work done64.38%
BuildingWingEstimatedIncurred
Block BNARs 89.84 crRs 50.82 cr
Block ANARs 74.77 crRs 55.45 cr
-NARs 14.40 crRs 8.97 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVAO Architects Research And Design Studio
EngineerRudraksh G Pathak
EngineerFidesto Projects Private Limited
Chartered AccountantH S B and Co
Chartered AccountantK Parekh Associates
Chartered AccountantShrada Shankar Bagwale
PartnerRole in project
Superb Maa Infra and Housing LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA31052621176May 2026 → Dec 2026

Reason as filed by the promoterWe, hereby apply for extension u/s 7(3), of the registered project Yogakshema Residency Phase-I bearing vide no P52000034419, until date 31/12/2026. As prescribed under circular no 07/2019 dated 8 Feb 2019, the consent of 54.01% of the allottees is enclosed herewith. The construction of the buildings in the project is at advanced stage, and Promoter is striving to complete the balance work at the earliest. The proposed construction schedule, as given in enclosed CPM chart, has been planned to aggressively finish the balance construction work and hand over the apartments to respective allottees

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jun 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: Amended Approval Plans_Part 2 of 3 updated.pdf1 Jul 2026
Layout approvalFile: Amended Approval Plans_Part 1 of 3.pdf20 Jun 2026
Building plan approvalFile: Amended Approval Plans_Part 2 of 3.pdf20 Jun 2026
Building plan approvalFile: Amended Approval Plans_Part 3 of 3.pdf20 Jun 2026
Withdrawal Update Form 1File: YR_Phase-I_Form-1 Dec 2025.pdf31 May 2026
Withdrawal Update Form 1File: YR_Phase-I_Form-1 March 2026.pdf31 May 2026
Withdrawal Update Form 2File: YR_Phase-I_Form-2 Dec 2025.pdf31 May 2026
Withdrawal Update Form 2File: YR_Phase-I_Form-2 March 2026.pdf31 May 2026
Withdrawal Update Form 3File: YR_Phase-I_Form-3 Dec 2025.pdf31 May 2026
Withdrawal Update Form 3File: YR_Phase-I_Form-3 March 2026.pdf31 May 2026
Form 2A (FY 2025-2026)File: YR_Phase-I_Form-2A FY 2025-26.pdf31 May 2026
Form 2A (FY 2024-2025)File: YR_Phase-I_Form-2A FY 2024-25.pdf31 May 2026
Form 5 (FY 2024-2025)File: YR_Phase-I_Form-5 FY 2024-25.pdf31 May 2026
Withdrawal Update Form 1File: YR_Phase-I_Form-1 Sep 2025.pdf30 May 2026
Withdrawal Update Form 2File: YR_Phase-I_Form-2 June 2025.pdf30 May 2026
Withdrawal Update Form 3File: YR_Phase-I_Form-3 Sep 2025.pdf30 May 2026
Withdrawal Update Form 1File: YR_Phase-I_Form-1 June 2025.pdf29 May 2026
Withdrawal Update Form 2File: YR_Phase-I_Form-2 June 2025.pdf29 May 2026
Withdrawal Update Form 3File: YR_Phase-I_Form-3 June 2025.pdf29 May 2026
Form 1File: YP I Form 1 202209.pdf10 Dec 2025
Form 2File: YP I Form 2 202209.pdf10 Dec 2025
Form 3File: YP I Form 3 202209.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: YP I Sold 202209.pdf10 Dec 2025
Form 1File: YP I Form 1 202212.pdf10 Dec 2025
Form 2File: YP I Form 2 202212.pdf10 Dec 2025
Form 3File: YP I Form 3 202212.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: YP I Sold 202212.pdf10 Dec 2025
Form 1File: YP I Form 1 202406.pdf10 Dec 2025
Form 2File: YP I Form 2 202406.pdf10 Dec 2025
Form 3File: YP I Form 3 202406.pdf10 Dec 2025
Disclosure of Sold and Booked InventoryFile: YP I Sold 202406.pdf10 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 DOC-20250128-WA0051 3.pdf9 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: YR_P-I_202409_Form-1.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: YR_P-I_202409_Form-3.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: YR_P-I_202409_Form-2.PDF13 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: YR_P-I_2022-23_Form-2A.pdf12 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: YR_P-I_2023-24_Form-2A.pdf12 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: YR_P-I_2023-24_Form-5.pdf12 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: 6_Commencement Certificate.pdf13 Aug 2024
Declaration about Commencement CertificateFile: 7_CC Declaration_10082023.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202406_Ar.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202406_Er.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: 202406_Sold.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202406_CA.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23_Form 5.pdf13 Aug 2024
Details of encumbrancesFile: YR_P1-Encumbrance_032024.PDF5 Aug 2024
Disclosure of sold/ booked inventoryFile: 202206_Sold.pdf28 Jul 2024
Disclosure of sold/ booked inventoryFile: 202209_Sold.pdf28 Jul 2024
Disclosure of sold/ booked inventoryFile: 202212_Sold.pdf28 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202403_Ar.pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202403_Er.pdf23 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202309_Ar.pdf4 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202312_Ar.pdf4 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202309_Er.pdf4 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202309_CA.pdf4 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202312_CA.pdf4 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure by partners.pdf4 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202306_Ar.pdf19 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202306_Er.pdf19 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202306_CA.pdf19 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202304_Ar.pdf11 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202304_Er.pdf11 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202303_CA.pdf11 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202212_Ar.pdf18 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202212_Er.pdf18 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 JUNE 2022.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 SEP 2022-.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3 UDIN DEC 2022.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202206_Ar.pdf3 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202209_Ar.pdf3 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202209_Er.pdf3 Nov 2022
Proforma of Agreement for saleFile: 14_AfS.pdf3 Nov 2022
Copy of the legal title reportFile: 2_Title.pdf31 Mar 2022
Copy of the legal title reportFile: 2A_Search Report.pdf31 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11_CA.pdf31 Mar 2022
Building plan approvalFile: 4_2.pdf29 Mar 2022
Building plan approvalFile: 4_3.pdf29 Mar 2022
Building plan approvalFile: 4_4.pdf29 Mar 2022
Building plan approvalFile: 4_5.pdf29 Mar 2022
Building plan approvalFile: 4_6.pdf29 Mar 2022

How this compares with Raigarh

78%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 7 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Yogakshema Residency Phase-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Giravale5,900+ in Raigarh

2 kmYogakshema Residency PhaCompleted 9Lapsed / revoked 4Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 36 registered projects within 2 km.

Builder: Superb Maa Infra and Housing LLP

Superb Maa Infra and Housing LLP has 2 registrations on MahaRERA, including Yogakshema Residency Phase-I and Yogakshema Residency Phase-II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Yogakshema Residency Phase-I is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Yogakshema Residency Phase-I?

The registered promoter entity is Superb Maa Infra and Housing LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Yogakshema Residency Phase-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Yogakshema Residency Phase-I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Yogakshema Residency Phase-I?

The professionals named in the filing: Architect: VAO Architects Research And Design Studio; Engineer: Rudraksh G Pathak; Engineer: Fidesto Projects Private Limited; Chartered Accountant: H S B and Co; Chartered Accountant: K Parekh Associates; Chartered Accountant: Shrada Shankar Bagwale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Yogakshema Residency Phase-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Yogakshema Residency Phase-I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Yogakshema Residency Phase-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.