YASHWANT SANKALP- Jasmin Phase 2
RG-MH-04340 · RERA P99000021693 · Last updated on MahaRERA portal: 16 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 15 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
YASHWANT SANKALP- Jasmin Phase 2 is a Residential / Group Housing project by MAHALAXMI INFRA in Palghar, Maharashtra, registered with MahaRERA as P99000021693 on 19 Jul 2019. Possession was promised by 31 Jul 2025 and is now 15 months past that date. 42 of the 50 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameYASHWANT SANKALP- Jasmin Phase 2
- TypeResidential / Group Housing
- Location
- SARAVALI
- Palghar
- 401501
- Pincode401501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000021693
- ReraGenie IDRG-MH-04340
Builder
- NameMAHALAXMI INFRA
- Entity typePartnership
- PartnersPANNALAL RAMACHARYA MISHRA, PARAG RAJANIKANT LADHANI, AMIT TAKHATSINH SOLANKI, DHARMESH ARVIND GANDHI, NILESH DEVRAM MANGELA, VINIT PANNALAL MISHRA, RAMSURAT RAMACHARYA MISHRA, MILIND MADHUKAR MASDEKAR, DEEPAK VINAYAK UTEKAR, HEMANT BHASKAR CHAMPANERKAR
- Other registrations12 more →
- Completed7 of 13
- No longer live4 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Jul 2019
- Promised completion31 Jul 2025
- Revised completionNone
- Buildings1 building record
- Documents filed117 files
Current status
Figures as on 16 Sep 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JASMIN Phase 2 | NA | 5 | 5 | 50 | 0 | 50 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 30%.
JASMIN Phase 2: 41% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 2% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NISHANT PATIL VASTU SHILP SSOCIATES |
| Engineer | RUPESH RAMESH PAWADE |
| Chartered Accountant | PALLAVI BARAPATRE |
| Partner | Role in project |
|---|---|
| MAHALAXMI INFRA | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Jul 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Jul 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jul 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed117
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM 1 JULY TO SEPT'24.pdf | 16 Sep 2025 |
| Form 2File: JASMINE FORM 2 100% SEP 24.pdf | 16 Sep 2025 |
| Form 3File: FORM 3_DATE -- 30-09-2024.pdf | 16 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD LIST 300924.pdf | 16 Sep 2025 |
| Form 1File: FORM 1 JULY TO SEPT'24.pdf | 16 Sep 2025 |
| Form 2File: JASMINE FORM 2 100% SEP 24.pdf | 16 Sep 2025 |
| Form 3File: FORM 3_DATE -- 30-09-2024.pdf | 16 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD LIST 300924.pdf | 16 Sep 2025 |
| Form 1File: FORM 1 _22-05-2025 (1).pdf | 16 Sep 2025 |
| Form 2File: JASMINE FORM 2 100% MAR 25.pdf | 16 Sep 2025 |
| Form 3File: FORM 3_DATE -- 31-03-2025.pdf | 16 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD LIST 310325.pdf | 16 Sep 2025 |
| Form 1File: FORM 1 OCT TO DEC'23.pdf | 4 Aug 2025 |
| Form 2File: FORM 2_DATE -- 25-12-2023.pdf | 4 Aug 2025 |
| Form 3File: FORM 3_DATE -- 31-12-2023.pdf | 4 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD N UNSOLD LIST.pdf | 4 Aug 2025 |
| Form 1File: FORM 1 APRIL TO JUNE'24.pdf | 4 Aug 2025 |
| Form 2File: FORM 2_DATE -- 25-06-2024.pdf | 4 Aug 2025 |
| Form 3File: FORM 3_DATE -- 30-06-2024.pdf | 4 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD LIST 010424 TO 300624.pdf | 4 Aug 2025 |
| Form 1File: FORM 1 JULY TO SEPT'19.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 25-09-2019.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 30-09-2019.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 30-09-2019.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 OCT TO DEC'19.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 27-12-2019.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 31-12-2019.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 31-12-2019.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 JAN TO MARCH'20.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 20-03-2020.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 31-03-2020.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 31-03-2020.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 APRIL TO JUNE 2020.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 20-06-2020.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 30-06-2020.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 30-06-2020.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 JULY TO SEPT 2020.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 20-09-2020.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 30-09-2020.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 30-09-2020.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 31122020.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 20-12-2020.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 31-12-2020.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 31-12-2020.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 JAN TO MAR'21.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 25-03-2021.pdf | 29 Jul 2025 |
| Form 3File: FORM 3 31032021.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 31-03-2021.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 APRIL TO JUNE'21.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 28-06-2021.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 30-06-2021.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 30-06-2021.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 JULY TO SEPT'21.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 28-09-2021.pdf | 29 Jul 2025 |
| Form 3File: FORM 3_DATE -- 30-09_2021.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 30-09-2021.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 OCT TO DEC 2021.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 28-12-2021.pdf | 29 Jul 2025 |
| Form 3File: FORM 3 _DATE -- 31-12-2021.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 31-12-2021.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 JAN TO MAR'21.pdf | 29 Jul 2025 |
| Form 2File: FORM 2_DATE -- 25-03-2021.pdf | 29 Jul 2025 |
| Form 3File: FORM 3 31032021.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold n unsold list 31-03-2021.pdf | 29 Jul 2025 |
| Form 1File: FORM 1 APRIL TO JUNE'23.pdf | 26 Jul 2025 |
| Form 2File: FORM 2_DATE -- 25-06-2023.pdf | 26 Jul 2025 |
| Form 3File: FORM 3_DATE -- 30-06-2023.pdf | 26 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD N UNSOLD INVENTORY.pdf | 26 Jul 2025 |
| Form 1File: FORM 1 JULY TO SEPT'22.pdf | 26 Jul 2025 |
| Form 2File: FORM 2_DATE -- 28-09-2022.pdf | 26 Jul 2025 |
| Form 3File: FORM 3 _DATE -- 30-09-2022.pdf | 26 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD N UNSOLD INVENTORY.pdf | 26 Jul 2025 |
| Form 1File: FORM 1 JULY TO SEPT'23.pdf | 26 Jul 2025 |
| Form 2File: FORM 2_DATE -- 25-09-2023.pdf | 26 Jul 2025 |
| Form 3File: FORM 3_DATE -- 30-09-2023.pdf | 26 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD N UNSOLD INVENTORY.pdf | 26 Jul 2025 |
| Form 1File: FORM 1 OCT TO DEC'22.pdf | 26 Jul 2025 |
| Form 2File: FORM 2_DATE -- 29-12-2022.pdf | 26 Jul 2025 |
| Form 3File: FORM 3_DATE -- 31-12-2022.pdf | 26 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD N UNSOLD INVENTORY.pdf | 26 Jul 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 12 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 117 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep YASHWANT SANKALP- Jasmin Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SARAVALI3,200+ in Palghar
Filed coordinates, straight-line distance. 88 registered projects within 2 km.
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: MAHALAXMI INFRA
MAHALAXMI INFRA has 13 registrations on MahaRERA, including MAHALAXMI NAGAR 1 and SHIVTHIRTH NAGAR 2. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that YASHWANT SANKALP- Jasmin Phase 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if YASHWANT SANKALP- Jasmin Phase 2 is delayed beyond 31 Jul 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of YASHWANT SANKALP- Jasmin Phase 2?
The registered promoter entity is MAHALAXMI INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in YASHWANT SANKALP- Jasmin Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for YASHWANT SANKALP- Jasmin Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at YASHWANT SANKALP- Jasmin Phase 2?
The professionals named in the filing: Architect: NISHANT PATIL VASTU SHILP SSOCIATES; Engineer: RUPESH RAMESH PAWADE; Chartered Accountant: PALLAVI BARAPATRE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in YASHWANT SANKALP- Jasmin Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.