Red flags

  • Rs 14.50 crore secured on the land, in favour of ICICI HOME FINANCE COMPANY LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
96 of 102Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

YASHOMANGAL C.H.S. is a Others project by Kedar Buildcon in Raigarh, Maharashtra, registered with MahaRERA as P52000078290 on 4 Dec 2024. Possession is promised by 30 Sep 2028. 6 of the 102 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameYASHOMANGAL C.H.S.
  • TypeOthers
  • Location
    • DR. RD PATWARDHAN MARG
    • PANVEL
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000078290
  • ReraGenie IDRG-MH-19218

Builder

  • NameKedar Buildcon
  • Entity typePartnership
  • PartnersMitesh Piyush Doshi, Vishal Piyush Doshi
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredDec 2024PromisedSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Dec 2024
  • Promised completion30 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed63 files

Current status

6%6 of 102 units booked
41.2%Work done, per cost certificate

Figures as on 12 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
YASHOMANGAL CHSNA15137428102

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

YASHOMANGAL CHS: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed98

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots98
Closed/Covered53
Open Space45

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,747 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofICICI HOME FINANCE COMPANY LIMITED
Secured amountRs 14.50 crore
CERSAI search filedYes
Declared on25 Nov 2025
LandownerVillageDistrict
YASHOMANGAL CO-OP HSG SOCIETY LTDNavi Mumbai Panvel Rigardh (CT)Raigarh

Approvals and building plan

Sanctioning authorityPANVEL MUNICIPAL CORPORATION
Permissible FSI6945.88
Proposed, not sanctioned6,946 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR SHOP NO 2 SHREE BALAJI BANQUETS PLOT NO 231 BEHIND MTNL OLD PANVEL NAVI MUMBAI 410206
Estimated costRs 21.62 cr
Cost incurredRs 8.90 cr
Work done41.17%
BuildingWingEstimatedIncurred
YASHOMANGAL CHSNARs 18.80 crRs 8.90 cr
-NARs 2.82 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectROOM N ROOF ARCHITECT AND INTERIORS
ArchitectDEVISE DESIGN
EngineerDESTECH STRUCTURAL CONSULTANT
Chartered AccountantKMR and Associates LLP
PartnerRole in project
Kedar Buildcon-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2028

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 March 2026.pdf12 Jun 2026
Withdrawal Update Form 2File: Form-2 March 2026.pdf12 Jun 2026
Withdrawal Update Form 3File: Form-3 March 2026.pdf12 Jun 2026
Withdrawal Update Form 1File: Form 1 Yashomangal.pdf23 Mar 2026
Withdrawal Update Form 2File: Q3 Form -2 Engineers Certificate - Yashomangal.pdf23 Mar 2026
Withdrawal Update Form 3File: F-3 Q3 CA Certificate - Yashomangal_compressed.pdf23 Mar 2026
Withdrawal Update Form 1File: Form 1 Yashomangal.pdf26 Oct 2025
Withdrawal Update Form 2File: Form 2 Yashomangal.pdf26 Oct 2025
Withdrawal Update Form 3File: Form 3 Yashomangal.pdf26 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F-1 Yashomangal Q4 24-25.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F-3 Yashomangal Q4 24-25_compressed.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F-2 Yashomangal Q4 24-25.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: Yashomangal Q4 soldunsold sign copy.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: yashomangal sold unsold Q3.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: yashomangal sold unsold Q3.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Yashomangal Form 1 Q-3 (24-25)UPDATED.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Yashomangal Form 1 Q-3 (24-25)UPDATED.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Yashomangal CHS.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Yashomangal_compressed.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Yashomangal CHS.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Yashomangal CHS.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Yashomangal_compressed.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Yashomangal CHS.pdf28 Jan 2025
Building plan approvalFile: YASHO PALN.pdf28 Dec 2024
Building plan approvalFile: YASHO PALN.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: YASHOMANGAL REVISED CC.pdf28 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: YASHO PALN.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: YASHOMANGAL REVISED CC.pdf28 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: YASHO PALN.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: cc clarification.pdf25 Nov 2024
Other - TechnicalFile: cc clarification.pdf25 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate.pdf12 Nov 2024
Declaration about Commencement CertificateFile: Declaration About Commencemennt Certificate.pdf12 Nov 2024
Other - FinanceFile: Clarification For Query.pdf12 Nov 2024
Other - TechnicalFile: Clarification For Query.pdf12 Nov 2024
Building plan approvalFile: Yashomangal Layout Plan-2-5.pdf22 Oct 2024
Layout approvalFile: Yashomangal Layout Plan-1.pdf22 Oct 2024
Copy of Layout Approval (in case of layout)File: Yashomangal Layout Plan-1.pdf22 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Yashomangal Layout Plan-2-5.pdf22 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Yashomangal Bank Declaration Format A.pdf19 Oct 2024
Other - TechnicalFile: Annexure A.pdf19 Oct 2024
Proforma of Agreement for saleFile: AFS_RERA-Yashomangal.pdf19 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Yashomangal CHS Bank Format B.pdf19 Oct 2024
Proforma of Allotment letterFile: New Model from Allotment Letter.pdf15 Oct 2024
Copy of the legal title reportFile: yashomangal title with 30 yrs search.pdf14 Oct 2024
Details of encumbrances concerned to FinanceFile: Declaration Finance encumbrances (3).pdf14 Oct 2024
Details of encumbrances concerned to FinanceFile: DECLARTAION LEGAL ENCUMBRANCES Scan - Copy.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 Scan.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 Scan.pdf14 Oct 2024
Other - LegalFile: DEED OF RETIREMENT_organized_compressed.pdf14 Oct 2024
CERSAI detailsFile: DECLARATION CERSAI Scan.pdf14 Oct 2024
Details of encumbrances concerned to LegalFile: Declaration Finance encumbrances (3).pdf14 Oct 2024
Details of encumbrances concerned to LegalFile: DECLARTAION LEGAL ENCUMBRANCES Scan - Copy.pdf14 Oct 2024
Other - TechnicalFile: cc VERIFICATION MAIL.pdf14 Oct 2024
PAN CardFile: Pan Card-Kedar Buildcon.pdf12 Oct 2024
Declaration in FORM BFile: AFFIDAVIT PROMOTER.pdf12 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Yashomangal CC.pdf12 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: cc VERIFICATION MAIL.pdf12 Oct 2024
Deviation Report with respect to Allotment letterFile: Draft Allotment Deviation Report Scan.pdf12 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Draft Sale Agreement Deviation Report Scan.pdf12 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A MrMitesh sir Scan.pdf12 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A MrVishar sir Scan.pdf12 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Discloser for Secured unsecured finance Funds Scan.pdf12 Oct 2024

How this compares with Raigarh

6%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep YASHOMANGAL C.H.S. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PANVEL5,900+ in Raigarh

2 kmYASHOMANGAL C.H.S.Completed 212Lapsed / revoked 57Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 402 registered projects within 2 km.

Builder: Kedar Buildcon

Kedar Buildcon has 2 registrations on MahaRERA, including Sunflower and YASHOMANGAL C.H.S.. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if YASHOMANGAL C.H.S. is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of YASHOMANGAL C.H.S.?

The registered promoter entity is Kedar Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in YASHOMANGAL C.H.S.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for YASHOMANGAL C.H.S.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at YASHOMANGAL C.H.S.?

The professionals named in the filing: Architect: ROOM N ROOF ARCHITECT AND INTERIORS; Architect: DEVISE DESIGN; Engineer: DESTECH STRUCTURAL CONSULTANT; Chartered Accountant: KMR and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in YASHOMANGAL C.H.S.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About YASHOMANGAL C.H.S.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save YASHOMANGAL C.H.S. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.