Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 13 other registrations.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2030Possession promisedno revision filed
72 of 1991Construction stages doneacross 181 buildings; furthest along: Basement (if any), 75%
73 of 181Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 107 documents Report an error

World Villas Phase 1 is a Residential / Group Housing project by ARIHANT SUPERSTRUCTURES LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000076635 on 18 Jun 2024. Possession is promised by 31 Mar 2030. 108 of the 181 units on this registration are recorded sold or booked, and 72 of 1991 construction stages are filed complete.

At a glance

Project

  • NameWorld Villas Phase 1
  • TypeResidential / Group Housing
  • Location
    • Bhilavale
    • Bhilvale
    • Khalapur
    • Raigarh
    • 410202
  • Pincode410202
  • RERA no.P52000076635
  • ReraGenie IDRG-MH-18351

Builder

  • NameARIHANT SUPERSTRUCTURES LIMITED
  • Entity typeCompany
  • CINL51900MH1983PLC029643
  • GSTIN27AABCS1848L1Z2
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsASHOKKUMAR BHANWARLAL CHHAJER, PARTH ASHOKKUMAR CHHAJER
  • Other registrations13 more →
  • Completed5 of 14

Key dates

this monthRegisteredJun 2024PromisedMar 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Jun 2024
  • Promised completion31 Mar 2030
  • Revised completionNone
  • Buildings181 building records
  • Documents filed107 files

Current status

60%108 of 181 units booked
0.0%Work done, per cost certificate

Figures as on 22 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bungalow Type ELA 94NA22101
Bungalow Type ELA 95NA22101
Bungalow Type ELA 96NA22101
Bungalow Type ELA 97NA22101
Bungalow Type ELA 98NA22101
Bungalow Type ELA 99NA22101
Bungalow Type ELA 100NA22101
Bungalow Type ELA 101NA22101
Bungalow Type ELA 102NA22101
Bungalow Type ELA 103NA22101
Bungalow Type ELA 104NA22101
Bungalow Type ELA 105NA22101
Bungalow Type ELA 106NA22101
Bungalow Type ELA 107NA22101
Bungalow Type ELA 108NA22101
Bungalow Type ELA 109NA22101
Bungalow Type ELA 110NA22101
Bungalow Type ELA 161NA22101
Bungalow Type ELA 162NA22101
Bungalow Type ELA 163NA22101
Bungalow Type ELA 164NA22101
Bungalow Type ELA 165NA22101
Bungalow Type ELA 166NA22101
Bungalow Type ELA 167NA22101
Bungalow Type ELA 168NA22101
Bungalow Type ELA 169NA22101
Bungalow Type ELA 170NA22101
Bungalow Type ELA 171NA22101
Bungalow Type ELA 172NA22101
Bungalow Type ELA 173NA22101
Bungalow Type ELA 183NA22101
Bungalow Type ELA 184NA22101
Bungalow Type ELA 185NA22101
Bungalow Type ELA 186NA22101
Bungalow Type ELA 187NA22101
Bungalow Type ELA 188NA22101
Bungalow Type ELA 189NA22101
Bungalow Type ELA 190NA22101
Bungalow Type ELA 191NA22101
Bungalow Type ELA 192NA22101
Bungalow Type ELA 193NA22101
Bungalow Type ELA 194NA22101
Bungalow Type ELA 195NA22101
Bungalow Type ELA 196NA22101
Bungalow Type ELA 197NA22101
Bungalow Type ELA 198NA22101
Bungalow Type ELA 199NA22101
Bungalow Type ELA 200NA22101
Bungalow Type ELA 228NA22101
Bungalow Type ELA 229NA22101
Bungalow Type ELA 230NA22101
Bungalow Type ELA 231NA22101
Bungalow Type ELA 232NA22101
Bungalow Type ELA 300NA22101
Bungalow Type ELA 301NA22101
Bungalow Type ELA 302NA22101
Bungalow Type ELA 303NA22101
Bungalow Type ELA 304NA22101
Bungalow Type ELA 305NA22101
Bungalow Type ELA 306NA22101
Bungalow Type ELA 307NA22101
Bungalow Type ELA 308NA22101
Bungalow Type ELA 309NA22101
Bungalow Type ELA 310NA22101
Bungalow Type ELA 311NA22101
Bungalow Type ELA 312NA22101
Bungalow Type ELA 313NA22101
Bungalow Type ELA 314NA22101
Bungalow Type ELA 315NA22101
Bungalow Type ELA 316NA22101
Bungalow Type ELA 317NA22101
Bungalow Type SLB 282NA22101
Bungalow Type ELA 318NA22101
Bungalow Type ELA 319NA22101
Bungalow Type SLA 226NA22101
Bungalow Type SLA 227NA22101
Bungalow Type ELB 213NA22101
Bungalow Type ELB 214NA22101
Bungalow Type ELB 215NA22101
Bungalow Type ELB 216NA22101
Bungalow Type SP 284NA22101
Bungalow Type LAMHENA22101
Bungalow Type SLB 237NA22101
Bungalow Type SLB 238NA22101
Bungalow Type SLB 239NA22101
Bungalow Type SLB 240NA22101
Bungalow Type SLB 241NA22101
Bungalow Type SLB 242NA22101
Bungalow Type SLB 243NA22101
Bungalow Type SLB 244NA22101
Bungalow Type SLB 245NA22101
Bungalow Type SLB 260NA22101
Bungalow Type SLB 261NA22101
Bungalow Type SLB 262NA22101
Bungalow Type SLB 263NA22101
Bungalow Type ELA 174NA22101
Bungalow Type ELA 175NA22101
Bungalow Type ELA 201NA22101
Bungalow Type ELA 202NA22101
Bungalow Type ELA 203NA22101
Bungalow Type ELA 204NA22101
Bungalow Type ELA 205NA22101
Bungalow Type ELA 206NA22101
Bungalow Type ELA 207NA22101
Bungalow Type ELA 208NA22101
Bungalow Type ELA 209NA22101
Bungalow Type ELA 210NA22101
Bungalow Type ELA 211NA22101
Bungalow Type ELA 212NA22101
Bungalow Type ELA 217NA22101
Bungalow Type ELA 176NA22101
Bungalow Type ELA 177NA22101
Bungalow Type ELA 178NA22101
Bungalow Type ELA 179NA22101
Bungalow Type ELA 180NA22101
Bungalow Type ELA 181NA22101
Bungalow Type ELA 182NA22101
Bungalow Type ELA 233NA22101
Bungalow Type ELA 234NA22101
Bungalow Type ELA 235NA22101
Bungalow Type ELA 236NA22101
Bungalow Type SLB 281NA22101
Bungalow Type ELA 256NA22101
Bungalow Type ELA 257NA22101
Bungalow Type ELA 258NA22101
Bungalow Type ELA 259NA22101
Bungalow Type ELA 286NA22101
Bungalow Type ELA 287NA22101
Bungalow Type ELA 288NA22101
Bungalow Type ELA 289NA22101
Bungalow Type ELA 290NA22101
Bungalow Type ELA 291NA22101
Bungalow Type ELA 292NA22101
Bungalow Type ELA 293NA22101
Bungalow Type ELA 294NA22101
Bungalow Type ELA 295NA22101
Bungalow Type ELA 296NA22101
Bungalow Type ELA 297NA22101
Bungalow Type ELA 298NA22101
Bungalow Type ELA 299NA22101
Bungalow Type ELA 320NA22101
Bungalow Type ELA 321NA22101
Bungalow Type ELA 322NA22101
Bungalow Type ELA 323NA22101
Bungalow Type LB 159NA22101
Bungalow Type LB 160NA22101
Bungalow Type LB 246NA22101
Bungalow Type LB 247NA22101
Bungalow Type LB 248NA22101
Bungalow Type LB 249NA22101
Bungalow Type LB 250NA22101
Bungalow Type LB 251NA22101
Bungalow Type LB 252NA22101
Bungalow Type LB 253NA22101
Bungalow Type LB 254NA22101
Bungalow Type LB 255NA22101
Bungalow Type SLA 218NA22101
Bungalow Type SLA 219NA22101
Bungalow Type SLA 220NA22101
Bungalow Type SLA 221NA22101
Bungalow Type SLA 222NA22101
Bungalow Type SLA 223NA22101
Bungalow Type SLA 224NA22101
Bungalow Type SLA 225NA22101
Bungalow Type SLB 264NA22101
Bungalow Type SLB 265NA22101
Bungalow Type SLB 266NA22101
Bungalow Type SLB 267NA22101
Bungalow Type SLB 268NA22101
Bungalow Type SLB 269NA22101
Bungalow Type SLB 270NA22101
Bungalow Type SLB 271NA22101
Bungalow Type SLB 272NA22101
Bungalow Type SLB 273NA22101
Bungalow Type SLB 274NA22101
Bungalow Type SLB 275NA22101
Bungalow Type SLB 276NA22101
Bungalow Type SLB 277NA22101
Bungalow Type SLB 278NA22101
Bungalow Type SLB 279NA22101
Bungalow Type SLB 280NA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 181 buildings; the table lists the first 20.

72 of 1991 construction stages are filed complete across 181 buildings. The stage furthest along is Basement (if any), at 75%.

Bungalow Type ELA 940%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 950%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 960%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 970%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 980%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 990%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1000%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1010%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1020%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1039%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1040%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 10516%
ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 10619%
ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1075%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1085%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 10914%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 11019%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth75%
Stilt Floor0%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1619%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1620%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow Type ELA 1630%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed197

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots197
Open Space197
BuildingOpen SpaceTotal
Bungalow Type ELA 9411
Bungalow Type ELA 9511
Bungalow Type ELA 9611
Bungalow Type ELA 9711
Bungalow Type ELA 9811
Bungalow Type ELA 9911
Bungalow Type ELA 10011
Bungalow Type ELA 10111
Bungalow Type ELA 10211
Bungalow Type ELA 10311
Bungalow Type ELA 10411
Bungalow Type ELA 10511
Bungalow Type ELA 10611
Bungalow Type ELA 10711
Bungalow Type ELA 10811
Bungalow Type ELA 10911
Bungalow Type ELA 11011
Bungalow Type ELA 16111
Bungalow Type ELA 16211
Bungalow Type ELA 16311
Bungalow Type ELA 16411
Bungalow Type ELA 16511
Bungalow Type ELA 16611
Bungalow Type ELA 16711
Bungalow Type ELA 16811
Bungalow Type ELA 16911
Bungalow Type ELA 17011
Bungalow Type ELA 17111
Bungalow Type ELA 17211
Bungalow Type ELA 17311
Bungalow Type ELA 18311
Bungalow Type ELA 18411
Bungalow Type ELA 18511
Bungalow Type ELA 18611
Bungalow Type ELA 18711
Bungalow Type ELA 18811
Bungalow Type ELA 18911
Bungalow Type ELA 19011
Bungalow Type ELA 19111
Bungalow Type ELA 19211
Bungalow Type ELA 19311
Bungalow Type ELA 19411
Bungalow Type ELA 19511
Bungalow Type ELA 19611
Bungalow Type ELA 19711
Bungalow Type ELA 19811
Bungalow Type ELA 19911
Bungalow Type ELA 20011
Bungalow Type ELA 22811
Bungalow Type ELA 22911
Bungalow Type ELA 23011
Bungalow Type ELA 23111
Bungalow Type ELA 23211
Bungalow Type ELA 30011
Bungalow Type ELA 30111
Bungalow Type ELA 30211
Bungalow Type ELA 30311
Bungalow Type ELA 30411
Bungalow Type ELA 30511
Bungalow Type ELA 30611
Bungalow Type ELA 30711
Bungalow Type ELA 30811
Bungalow Type ELA 30911
Bungalow Type ELA 31011
Bungalow Type ELA 31111
Bungalow Type ELA 31211
Bungalow Type ELA 31311
Bungalow Type ELA 31411
Bungalow Type ELA 31511
Bungalow Type ELA 31611
Bungalow Type ELA 31711
Bungalow Type SLB 28211
Bungalow Type ELA 31811
Bungalow Type ELA 31911
Bungalow Type SLA 22622
Bungalow Type SLA 22722
Bungalow Type ELB 21322
Bungalow Type ELB 21422
Bungalow Type ELB 21522
Bungalow Type ELB 21622
Bungalow Type SP 28411
Bungalow Type LAMHE33
Bungalow Type SLB 23711
Bungalow Type SLB 23811
Bungalow Type SLB 23911
Bungalow Type SLB 24011
Bungalow Type SLB 24111
Bungalow Type SLB 24211
Bungalow Type SLB 24311
Bungalow Type SLB 24411
Bungalow Type SLB 24511
Bungalow Type SLB 26011
Bungalow Type SLB 26111
Bungalow Type SLB 26211
Bungalow Type SLB 26311
Bungalow Type ELA 17411
Bungalow Type ELA 17511
Bungalow Type ELA 20111
Bungalow Type ELA 20211
Bungalow Type ELA 20311
Bungalow Type ELA 20411
Bungalow Type ELA 20511
Bungalow Type ELA 20611
Bungalow Type ELA 20711
Bungalow Type ELA 20811
Bungalow Type ELA 20911
Bungalow Type ELA 21011
Bungalow Type ELA 21111
Bungalow Type ELA 21211
Bungalow Type ELA 21711
Bungalow Type ELA 17611
Bungalow Type ELA 17711
Bungalow Type ELA 17811
Bungalow Type ELA 17911
Bungalow Type ELA 18011
Bungalow Type ELA 18111
Bungalow Type ELA 18211
Bungalow Type ELA 23311
Bungalow Type ELA 23411
Bungalow Type ELA 23511
Bungalow Type ELA 23611
Bungalow Type SLB 28111
Bungalow Type ELA 25611
Bungalow Type ELA 25711
Bungalow Type ELA 25811
Bungalow Type ELA 25911
Bungalow Type ELA 28611
Bungalow Type ELA 28711
Bungalow Type ELA 28811
Bungalow Type ELA 28911
Bungalow Type ELA 29011
Bungalow Type ELA 29111
Bungalow Type ELA 29211
Bungalow Type ELA 29311
Bungalow Type ELA 29411
Bungalow Type ELA 29511
Bungalow Type ELA 29611
Bungalow Type ELA 29711
Bungalow Type ELA 29811
Bungalow Type ELA 29911
Bungalow Type ELA 32011
Bungalow Type ELA 32111
Bungalow Type ELA 32211
Bungalow Type ELA 32311
Bungalow Type LB 15911
Bungalow Type LB 16011
Bungalow Type LB 24611
Bungalow Type LB 24711
Bungalow Type LB 24811
Bungalow Type LB 24911
Bungalow Type LB 25011
Bungalow Type LB 25111
Bungalow Type LB 25211
Bungalow Type LB 25311
Bungalow Type LB 25411
Bungalow Type LB 25511
Bungalow Type SLA 21822
Bungalow Type SLA 21922
Bungalow Type SLA 22022
Bungalow Type SLA 22122
Bungalow Type SLA 22222
Bungalow Type SLA 22322
Bungalow Type SLA 22422
Bungalow Type SLA 22522
Bungalow Type SLB 26411
Bungalow Type SLB 26511
Bungalow Type SLB 26611
Bungalow Type SLB 26711
Bungalow Type SLB 26811
Bungalow Type SLB 26911
Bungalow Type SLB 27011
Bungalow Type SLB 27111
Bungalow Type SLB 27211
Bungalow Type SLB 27311
Bungalow Type SLB 27411
Bungalow Type SLB 27511
Bungalow Type SLB 27611
Bungalow Type SLB 27711
Bungalow Type SLB 27811
Bungalow Type SLB 27911
Bungalow Type SLB 28011

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area82,188 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMaharashtra State Road Development Corporation Limited
Permissible FSI84640.27
Proposed, not sanctioned42,684 sq m
Buildings approved181
Buildings sanctioned181

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhoomi Heights, Plot No 596, Sector- 8, Kharghar, Navi Mumbai- 410210
Estimated costRs 38.45 cr
Work done0.0%
BuildingWingEstimatedIncurred
-NARs 38.45 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAN Arch
ArchitectYOGITA BHANDARKAR
EngineerJW Consultants LLP
EngineerKALEEM SAYYAD
EngineerHrushikesh Pathak
Chartered AccountantAnjani Goyal & Co.
Chartered AccountantUmmed Jain & Co.
PartnerRole in project
ARIHANT SUPERSTRUCTURES LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2030

Documents filed107

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_World Villas_03042026.pdf22 Apr 2026
Withdrawal Update Form 1File: Form 1 World Villas 300925.pdf22 Apr 2026
Withdrawal Update Form 1File: Form 1_World Villas Ph I_31122025.pdf22 Apr 2026
Withdrawal Update Form 2File: 7 Form 2_World Villas Ph I_250326.pdf22 Apr 2026
Withdrawal Update Form 2File: Form 2_World Villas Ph I_30092025.pdf22 Apr 2026
Withdrawal Update Form 2File: Form 2_World Villas Ph I_31122025.pdf22 Apr 2026
Withdrawal Update Form 3File: 7 Form 3_World Villas Ph I_250326.pdf22 Apr 2026
Withdrawal Update Form 3File: Form 3_World Villas Ph I_30092025.pdf22 Apr 2026
Withdrawal Update Form 3File: Form 3_World Villas Ph I_31122025.pdf22 Apr 2026
Form 5 (FY 2024-2025)File: World Villas Phase I.pdf17 Oct 2025
Form 2A (FY 2024-2025)File: World villas.pdf4 Oct 2025
Form 1File: Form 1_World Villas Ph I_30062025.pdf18 Jul 2025
Form 2File: Form 2_World Villas Ph I_30062025.pdf18 Jul 2025
Form 3File: Form 3_World Villas Ph I_30062025.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure_Signed.pdf18 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-1-40.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-41-80.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-81-120.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-121-160.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-161-183.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-World Villas Ph I_310325.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-World Villas Ph-I_310325.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-World Villas_31032025_SIGNED_compressed.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-1-40.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-41-80.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-81-120.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-121-160.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - WORLD VILLAS PHASE I-161-183.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - World Villas - SIGNED.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - WORLD VILLAS PH 1.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - WORLD VILLA PHASE I_SEP 24-1-37.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - WORLD VILLA PHASE I_SEP 24-38-75.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - WORLD VILLA PHASE I_SEP 24-76-113.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - WORLD VILLA PHASE I_SEP 24-114-151.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - WORLD VILLA PHASE I_SEP 24-152-183_SIGNED.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: World Villas Ph-1_SIGNED.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - World Villas Ph I.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 World Villas Phase I-1-61 30062024.pdf5 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 World Villas Phase I-62-123 30062024.pdf5 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 World Villas Phase I-124-183 30062024.pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 World Villas I.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure SIGNED.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30062024 World Villas I SIGNED.pdf20 Jul 2024
Building plan approvalFile: Approved Plan Merged-pages-17.pdf5 Jun 2024
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (44)_11zon (2).pdf5 Jun 2024
Building plan approvalFile: 1 Copy of Layout Approval (in case of layout) (44)_11zon (2).pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-2_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-3_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-4_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-5_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-6_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-8_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-9_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-10_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-11_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-12_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-14_11zon.pdf5 Jun 2024
Building plan approvalFile: Approved Plan Merged-pages-15_11zon.pdf5 Jun 2024
Copy of the legal title reportFile: World Villas Title Reports (1)-compressed.pdf5 Jun 2024
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (44)_11zon (2).pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: 1 Copy of Layout Approval (in case of layout) (44)_11zon (2).pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-2_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-3_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-4_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-5_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-6_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-8_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-9_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-10_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-11_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-12_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-14_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-15_11zon.pdf5 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Plan Merged-pages-17.pdf5 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 World Villas Phase 1 (1).pdf5 Jun 2024
Proforma of Agreement for saleFile: Final AFS draft-World Villas Phase 1.pdf5 Jun 2024
Proforma of Allotment letterFile: Allotment Letter_World Villas Phase I_Arihant Superstructures Limited_22052024.pdf5 Jun 2024

How this compares with Raigarh

60%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep World Villas Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhilavale5,900+ in Raigarh

Builder: ARIHANT SUPERSTRUCTURES LIMITED

ARIHANT SUPERSTRUCTURES LIMITED has 14 registrations on MahaRERA, including ARIHANT ARSHIYA PHASE II and ARIHANT ARSHIYA PHASE III. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if World Villas Phase 1 is delayed beyond 31 Mar 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of World Villas Phase 1?

The registered promoter entity is ARIHANT SUPERSTRUCTURES LIMITED, a company as per the filing. Its CIN L51900MH1983PLC029643 and GSTIN 27AABCS1848L1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in World Villas Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for World Villas Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at World Villas Phase 1?

The professionals named in the filing: Architect: AN Arch; Architect: YOGITA BHANDARKAR; Engineer: JW Consultants LLP; Engineer: KALEEM SAYYAD; Engineer: Hrushikesh Pathak; Chartered Accountant: Anjani Goyal & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in World Villas Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About World Villas Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save World Villas Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.