Indiabulls Savroli - 3
By Sylvanus Properties Limited
RG-MH-11607 · RERA P52000002846 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 6 complaints at MahaRERA
- Completion date moved by 45 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Indiabulls Savroli - 3 is a Residential / Group Housing project by Sylvanus Properties Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000002846 on 4 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 45 months from the original filing. 135 of the 558 units on this registration are recorded sold or booked, and 166 of 220 construction stages are filed complete. 6 complaints are on record with the regulator.
At a glance
Project
- NameIndiabulls Savroli - 3
- TypeResidential / Group Housing
- Location
- Pen Khopoli Road
- Near Khalapur Toll Naka
- Savroli
- Khalapur
- Raigarh
- 410202
- Pincode410202
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000002846
- ReraGenie IDRG-MH-11607
Builder
- NameSylvanus Properties Limited
- Entity typeCompany
- Whole Time DirectorRikesh Lakhani
- DirectorsSsatyajit Parrihaar, Milind Khedekar
- Other registrations2 more →
- Completed2 of 3
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2023)
- Buildings20 building records
- Documents filed194 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D7 | NA | 8 | 8 | 30 | 0 | 30 |
| D8 | NA | 8 | 8 | 30 | 0 | 30 |
| D9 | NA | 8 | 8 | 30 | 0 | 30 |
| D10 | NA | 8 | 8 | 30 | 0 | 30 |
| E5 | NA | 8 | 8 | 32 | 0 | 32 |
| E6 | NA | 8 | 8 | 32 | 0 | 32 |
| E7 | NA | 8 | 8 | 32 | 0 | 32 |
| E8 | NA | 8 | 8 | 32 | 0 | 32 |
| F5 | NA | 8 | 8 | 32 | 0 | 32 |
| F6 | NA | 8 | 8 | 32 | 0 | 32 |
| F7 | NA | 8 | 8 | 32 | 0 | 32 |
| F8 | NA | 8 | 8 | 32 | 0 | 32 |
| G1 | NA | 8 | 8 | 30 | 0 | 30 |
| G2 | NA | 8 | 8 | 32 | 0 | 32 |
| G3 | NA | 8 | 8 | 30 | 0 | 30 |
| G4 | NA | 6 | 6 | 26 | 0 | 26 |
| G5 | NA | 8 | 8 | 32 | 0 | 32 |
| G6 | NA | 8 | 8 | 30 | 0 | 30 |
| Villa 5 | NA | 2 | 1 | 2 | 0 | 2 |
| Villa 6 | NA | 2 | 1 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
166 of 220 construction stages are filed complete across 20 buildings. The stage furthest along is Internal walls, at 95%.
D775%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D875%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D974%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D1074%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G175%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G375%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G475%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G575%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G675%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Villa 582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Villa 682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 85% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 47% |
| Street Lighting | Yes | 90% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 15% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 10% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 82% |
| Aggregate area of recreational Open Space | Yes | 55% |
| Open Parking | Yes | 55% |
Parking filed152
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| D7 | 15 | 15 |
| D8 | 15 | 15 |
| D9 | 15 | 15 |
| D10 | 15 | 15 |
| G1 | 15 | 15 |
| G2 | 16 | 16 |
| G3 | 15 | 15 |
| G4 | 15 | 15 |
| G5 | 16 | 16 |
| G6 | 15 | 15 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D10 | NA | Rs 24.25 cr | Rs 24.25 cr |
| G6 | NA | Rs 23.01 cr | Rs 23.01 cr |
| D7 | NA | Rs 22.10 cr | Rs 24.31 cr |
| D8 | NA | Rs 21.62 cr | Rs 23.78 cr |
| D9 | NA | Rs 21.59 cr | Rs 21.59 cr |
| G1 | NA | Rs 20.04 cr | Rs 21.04 cr |
| G2 | NA | Rs 19.12 cr | Rs 19.12 cr |
| G5 | NA | Rs 18.84 cr | Rs 20.72 cr |
| G3 | NA | Rs 18.51 cr | Rs 18.51 cr |
| G4 | NA | Rs 18.23 cr | Rs 20.06 cr |
| F6 | NA | Rs 10.66 cr | Rs 11.73 cr |
| F5 | NA | Rs 10.51 cr | Rs 11.56 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAKHI UBHARE |
| Engineer | Ramesh Rampure |
| Engineer | Vitthal Shinde |
| Chartered Accountant | R G V A & ASSOCIATES |
| Chartered Accountant | A K O R D & CO |
| Partner | Role in project |
|---|---|
| Sylvanus Properties Limited | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Self Declaration of Reason for Delay is uploaded below in "OTHER" Tab.
Reason as filed by the promoter(i) Increase in costs of raw materials required for construction of the Project: In the month of February 2022, war broke out between Russia & Ukraine. The Applicant states that, one of the effects of the war was that the cost of raw materials shot up. This increase was by a staggering 40% in case of certain materials. We are attaching herewith the quotation for costs obtained by the applicant in the month of June 2021 as well as a comparable quote for similar materials procured/to be procured during the month of August 2022, after the war had commenced which was obtained by two different cont
Reason as filed by the promoterWe hereby apply for extension of registration of the following project: INDIABULLS SAVROLI 3 registered with the regulatory authority vide project registration certificate bearing No. P52000002846. which is about to be expired as on 31/03/2025. Reason for delay in completion of project MAHARERA project vide bearing Registration no. P52000002846 1. Pandemic-Induced Disruptions: The COVID-19 pandemic severely disrupted the real estate sector, causing widespread supply chain interruptions, labour shortages, and liquidity issues. These factors significantly affected our construction timelines, p
Reason as filed by the promoterThe Self-Declaration for Reason for Delay has been uploaded in the file titled “Annexure 2 - Self Declaration Reasons for Delay Explanatory Note.”
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000023552 | M/s. B. T. Conclave Private Limited | M/s. Sylvanus Properties Limited | 01/03/2018 |
| CC006000000198280 | Amit Agarwal | Sylvanus Properties Limited | 08/09/2021 |
| CC006000000231135 | PRAPTI AMIT KHATURIA | Sylvanus Properties Limited | 17/05/2022 |
| CC006000000231137 | AMIT LEKHRAJ KHATURIA | Sylvanus Properties Limited | 17/05/2022 |
| CC12400457 | Pranav Shah | Sylvanus Properties Limited | 19/10/2024 |
| CC12603458 | MILAN GANDHI | Sylvanus Properties Limited | 05/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed194
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 194 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate Q1 202627.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form_2 Savroli 3.PDF | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Q1 2627.pdf | 20 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form_2 A Savroli-3 (1).PDF | 1 Jul 2026 |
| Withdrawal Update Form 1File: Form_1 Indiabulls Savroli-3_Signed.PDF | 16 Jun 2026 |
| Withdrawal Update Form 2File: Signed_Form_2 Savroli 3.pdf | 16 Jun 2026 |
| Withdrawal Update Form 3File: Final_Indiabulls Savroli 3.pdf | 16 Jun 2026 |
| Withdrawal Update Form 1File: Form_1 Indiabulls Savroli-3_Final.PDF | 2 Mar 2026 |
| Withdrawal Update Form 2File: Form_2 Indiabulls Savroli-3.pdf | 2 Mar 2026 |
| Withdrawal Update Form 3File: Form 3_Q3 of FY 25-26_Compressed.pdf | 2 Mar 2026 |
| Withdrawal Update Form 1File: Form_1 IB Savroli-3.PDF | 12 Dec 2025 |
| Withdrawal Update Form 2File: Form_2 Indiabulls Savroli-3.PDF | 12 Dec 2025 |
| Withdrawal Update Form 3File: Form 3_Savroli 3_Q2_compressed.pdf | 12 Dec 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 Indiabulls Savroli 3.pdf | 1 Oct 2025 |
| Withdrawal Update Form 1File: Form_1 Indiabulls Savroli-3.PDF | 18 Sep 2025 |
| Withdrawal Update Form 2File: Form_2 Indiabulls Savroli-3 Q1.pdf | 18 Sep 2025 |
| Withdrawal Update Form 3File: Signed FORM 3 Indiabulls Savroli-Q1.pdf | 18 Sep 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Latest .pdf | 16 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Latest.pdf | 16 May 2025 |
| Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf | 24 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From_1Indiabulls Savroli-3.PDF | 24 Apr 2025 |
| Certificates of CA (Form 3)File: Final Signed_Form 3_Q4_Fy 24-25_V2.pdf | 24 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of sold Unsold Inventory_compressed.pdf | 24 Apr 2025 |
| CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf | 24 Apr 2025 |
| CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf | 24 Apr 2025 |
| Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf | 24 Apr 2025 |
| Declaration in FORM BFile: From_B Affidavit Cum Declaration.pdf | 16 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Savroli Golf City Phase -3.PDF | 1 Mar 2025 |
| Certificates of CA (Form 3)File: SAVROLI 3_Final_Form 3_compressed.pdf | 1 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From_2 Indiabulls Savroli-3.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of Sold Unsold.PDF | 1 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final_Form 5_FY 23-24_Indiabulls Savroli 3.PDF | 3 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf | 15 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1_Q2_Revised.PDF | 15 Nov 2024 |
| Certificates of CA (Form 3)File: Signed_Form 3_Indiabulls Savrolli 3.pdf | 15 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Q2_Revised.PDF | 15 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of sold Unsold Inventory.pdf | 15 Nov 2024 |
| CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf | 15 Nov 2024 |
| CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf | 15 Nov 2024 |
| Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf | 15 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf | 22 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf | 22 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Savroli-3.PDF | 22 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Savroli -3.PDF | 22 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure B- Disclosure of sold Unsold Inventory.pdf | 22 Jul 2024 |
| CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf | 22 Jul 2024 |
| CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf | 22 Jul 2024 |
| Certificates of CA (Form 3)File: Signed Form 3.PDF | 22 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Indiabulls Golf City.PDF | 7 May 2024 |
| Details of encumbrances concerned to FinanceFile: Annexure-K-Non-Enumberance Concerned to Finance.pdf | 19 Apr 2024 |
| Details of encumbrances concerned to LegalFile: Annexure-K-Non-Enumberance Concerned to Finance.pdf | 19 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Savroli Golf City Phase-3.PDF | 19 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Indiabulls Savroli Golf City-3.PDF | 19 Apr 2024 |
| CERSAI detailsFile: Annexure-G-Asset Based Declaration.pdf | 19 Apr 2024 |
| CERSAI detailsFile: Annexure-L-Debtor Based Declaration.pdf | 19 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure-B-Disclosure of sold unsold inventory reduced.pdf | 19 Apr 2024 |
| Certificates of CA (Form 3)File: Signed Form 3_Q4.PDF | 19 Apr 2024 |
| Declaration in FORM BFile: FORM_B-Affidavit Savroli Phase-3.PDF | 10 Apr 2024 |
| Certificates of CA (Form 3)File: Signed Form 3 - Savroli -3_compressed.pdf | 30 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Savroli Golf City.pdf | 29 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Indiabulls Savroli Phase -3.PDF | 29 Jan 2024 |
| Details of encumbrances concerned to FinanceFile: Annexure-K- Non Encumbrance Concerned of finance.pdf | 19 Jan 2024 |
| Details of encumbrances concerned to LegalFile: Annexure-K- Non Encumbrance Concerned of finance.pdf | 19 Jan 2024 |
| CERSAI detailsFile: Annexure-G- Asset Based Declaration.pdf | 19 Jan 2024 |
| CERSAI detailsFile: Annexure-L- Debtor Based Declartion.pdf | 19 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure-B- Disclosure of Sold _ Booked Inventory.pdf | 19 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Golf City Phase-3_Revised.pdf | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Golf City Phase3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Golf City-3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Golf City-3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Golf City-3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Golf City 3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Savroli Golf City 3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: INDIABULLS GOLF CITY D7 3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Savroli Golf City 3- D7.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Golf City-3.pdf | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Savroli Golf City 3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Savroli Golf City 3.PDF | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Savroli 3.pdf | 9 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Indiabulls Golf City 3.PDF | 9 Nov 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 194 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Indiabulls Savroli - 3 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Khalapur Toll Naka5,900+ in Raigarh
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
Godrej Woodside Estate Phase 1
Godrej Projects Development Limited
VRINDAVAN FLORA
Thalia Vastu Infra Projects
World Villas Phase 1
ARIHANT SUPERSTRUCTURES LIMITED
Basalt Hills
VIYONAA WORLD LLP
Magic Hill Enclave
Garnet Construction Ltd.
Advika Hill City-1
Shirish Khivraj Gadiya
See every Raigarh project, with the district possession charts
Builder: Sylvanus Properties Limited
Sylvanus Properties Limited has 3 registrations on MahaRERA, including Indiabulls Savroli - 3 and Indiabulls Savroli - 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Indiabulls Savroli - 3 is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Indiabulls Savroli - 3?
The registered promoter entity is Sylvanus Properties Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Indiabulls Savroli - 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Indiabulls Savroli - 3?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Indiabulls Savroli - 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Indiabulls Savroli - 3?
The professionals named in the filing: Architect: RAKHI UBHARE; Engineer: Ramesh Rampure; Engineer: Vitthal Shinde; Chartered Accountant: R G V A & ASSOCIATES; Chartered Accountant: A K O R D & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Indiabulls Savroli - 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback