Home / Browse projects / Raigarh, Maharashtra / Magic Hill Enclave
Magic Hill Enclave
RG-MH-20775 · RERA P52000004503 · Last updated on MahaRERA portal: 8 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 12 complaints at MahaRERA
- Completion date moved by 60 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Magic Hill Enclave is a Mixed project by Garnet Construction Ltd. in Raigarh, Maharashtra, registered with MahaRERA as P52000004503 on 9 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 113 of the 132 units on this registration are recorded sold or booked, and 681 of 1441 construction stages are filed complete. 12 complaints are on record with the regulator.
At a glance
Project
- NameMagic Hill Enclave
- TypeMixed
- Location
- Khalapur Road
- Khalapur
- Ambivali T. Wankhal (CT)
- Raigarh
- 410202
- Pincode410202
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000004503
- ReraGenie IDRG-MH-20775
Builder
- NameGarnet Construction Ltd.
- Entity typeCompany
- Managing DirectorKishankumar Jugalkishor Kedia
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Aug 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
- Buildings131 building records
- Documents filed268 files
Current status
Figures as on 8 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Bungalow 1 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 2 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 3 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 4 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 5 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 6 | NA | 3 | 3 | 1 | 0 | 1 |
| Bungalow 7 | NA | 3 | 3 | 1 | 0 | 1 |
| Bungalow 8 | NA | 3 | 3 | 1 | 0 | 1 |
| Bungalow 9 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 10 | NA | 3 | 3 | 1 | 0 | 1 |
| Bungalow 11 | NA | 3 | 3 | 1 | 0 | 1 |
| Bungalow 12 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 13 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 14 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 15 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 16 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 17 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 18 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 19 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 20 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 21 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 22 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 23 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 24 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 25 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 26 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 27 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 28 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 29 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 30 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 31 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 32 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 33 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 34 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 35 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 36 | NA | 2 | 2 | 1 | 0 | 1 |
| Bangalow 37 | NA | 3 | 3 | 1 | 0 | 1 |
| Bungalow 38 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 39 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 40 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 41 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 42 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 43 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 44 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 45 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 46 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 47 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 48 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 49 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 50 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 51 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 52 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 53 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 54 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 55 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 56 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 57 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 58 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 59 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 60 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 61 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 62 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 63 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 64 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 65 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 66 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 67 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 68 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 69 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 70 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 71 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 72 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 73 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 74 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 75 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 76 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 77 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 78 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 79 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 80 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 81 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 82 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 83 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 84 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 85 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 86 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 87 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 88 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 89 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 90 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 91 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 92 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 93 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 94 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 95 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 96 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 97 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 98 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 99 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 100 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 101 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 102 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 103 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 104 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 105 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 106 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 107 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 108 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 109 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 110 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 111 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 112 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 113 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 114 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 115 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 116 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 117 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 118 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 119 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 120 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 121 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 122 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 123 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 124 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 125 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 126 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 127 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 128 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 129 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 130 | NA | 2 | 2 | 1 | 0 | 1 |
| Bungalow 131 | NA | 2 | 2 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 8 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 132 buildings; the table lists the first 20.
681 of 1441 construction stages are filed complete across 132 buildings. The stage furthest along is Installation of Lifts, at 90%.
Bungalow 152%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 265%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 352%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 452%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 552%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 652%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 752%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 852%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 952%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1052%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1152%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1252%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1352%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1452%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1552%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1665%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1752%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1861%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 1965%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Bungalow 2061%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 8 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 20% |
| Solid Waste Management And Disposal | Yes | 60% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 10% |
| Fire protection and fire safety requirements | Yes | 10% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 90% |
| Open Parking | Yes | 100% |
Parking filed130
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Bungalow 1 | 1 | 1 |
| Bungalow 2 | 1 | 1 |
| Bungalow 3 | 1 | 1 |
| Bungalow 4 | 1 | 1 |
| Bungalow 5 | 1 | 1 |
| Bungalow 6 | 1 | 1 |
| Bungalow 7 | 1 | 1 |
| Bungalow 8 | 1 | 1 |
| Bungalow 9 | 1 | 1 |
| Bungalow 10 | 1 | 1 |
| Bungalow 11 | 1 | 1 |
| Bungalow 12 | 1 | 1 |
| Bungalow 13 | 1 | 1 |
| Bungalow 14 | 1 | 1 |
| Bungalow 15 | 1 | 1 |
| Bungalow 16 | 1 | 1 |
| Bungalow 17 | 1 | 1 |
| Bungalow 18 | 1 | 1 |
| Bungalow 19 | 1 | 1 |
| Bungalow 20 | 1 | 1 |
| Bungalow 21 | 1 | 1 |
| Bungalow 22 | 1 | 1 |
| Bungalow 23 | 1 | 1 |
| Bungalow 24 | 1 | 1 |
| Bungalow 25 | 1 | 1 |
| Bungalow 26 | 1 | 1 |
| Bungalow 27 | 1 | 1 |
| Bungalow 28 | 1 | 1 |
| Bungalow 29 | 1 | 1 |
| Bungalow 30 | 1 | 1 |
| Bungalow 31 | 1 | 1 |
| Bungalow 32 | 1 | 1 |
| Bungalow 33 | 1 | 1 |
| Bungalow 34 | 1 | 1 |
| Bungalow 35 | 1 | 1 |
| Bungalow 36 | 1 | 1 |
| Bungalow 38 | 1 | 1 |
| Bungalow 39 | 1 | 1 |
| Bungalow 40 | 1 | 1 |
| Bungalow 41 | 1 | 1 |
| Bungalow 42 | 1 | 1 |
| Bungalow 43 | 1 | 1 |
| Bungalow 44 | 1 | 1 |
| Bungalow 45 | 1 | 1 |
| Bungalow 46 | 1 | 1 |
| Bungalow 47 | 1 | 1 |
| Bungalow 48 | 1 | 1 |
| Bungalow 49 | 1 | 1 |
| Bungalow 50 | 1 | 1 |
| Bungalow 51 | 1 | 1 |
| Bungalow 52 | 1 | 1 |
| Bungalow 53 | 1 | 1 |
| Bungalow 54 | 1 | 1 |
| Bungalow 55 | 1 | 1 |
| Bungalow 56 | 1 | 1 |
| Bungalow 57 | 1 | 1 |
| Bungalow 58 | 1 | 1 |
| Bungalow 59 | 1 | 1 |
| Bungalow 60 | 1 | 1 |
| Bungalow 61 | 1 | 1 |
| Bungalow 62 | 1 | 1 |
| Bungalow 63 | 1 | 1 |
| Bungalow 64 | 1 | 1 |
| Bungalow 65 | 1 | 1 |
| Bungalow 66 | 1 | 1 |
| Bungalow 67 | 1 | 1 |
| Bungalow 68 | 1 | 1 |
| Bungalow 69 | 1 | 1 |
| Bungalow 70 | 1 | 1 |
| Bungalow 71 | 1 | 1 |
| Bungalow 72 | 1 | 1 |
| Bungalow 73 | 1 | 1 |
| Bungalow 74 | 1 | 1 |
| Bungalow 75 | 1 | 1 |
| Bungalow 76 | 1 | 1 |
| Bungalow 77 | 1 | 1 |
| Bungalow 78 | 1 | 1 |
| Bungalow 79 | 1 | 1 |
| Bungalow 80 | 1 | 1 |
| Bungalow 81 | 1 | 1 |
| Bungalow 82 | 1 | 1 |
| Bungalow 83 | 1 | 1 |
| Bungalow 84 | 1 | 1 |
| Bungalow 85 | 1 | 1 |
| Bungalow 86 | 1 | 1 |
| Bungalow 87 | 1 | 1 |
| Bungalow 88 | 1 | 1 |
| Bungalow 89 | 1 | 1 |
| Bungalow 90 | 1 | 1 |
| Bungalow 91 | 1 | 1 |
| Bungalow 92 | 1 | 1 |
| Bungalow 93 | 1 | 1 |
| Bungalow 94 | 1 | 1 |
| Bungalow 95 | 1 | 1 |
| Bungalow 96 | 1 | 1 |
| Bungalow 97 | 1 | 1 |
| Bungalow 98 | 1 | 1 |
| Bungalow 99 | 1 | 1 |
| Bungalow 100 | 1 | 1 |
| Bungalow 101 | 1 | 1 |
| Bungalow 102 | 1 | 1 |
| Bungalow 103 | 1 | 1 |
| Bungalow 104 | 1 | 1 |
| Bungalow 105 | 1 | 1 |
| Bungalow 106 | 1 | 1 |
| Bungalow 107 | 1 | 1 |
| Bungalow 108 | 1 | 1 |
| Bungalow 109 | 1 | 1 |
| Bungalow 110 | 1 | 1 |
| Bungalow 111 | 1 | 1 |
| Bungalow 112 | 1 | 1 |
| Bungalow 113 | 1 | 1 |
| Bungalow 114 | 1 | 1 |
| Bungalow 115 | 1 | 1 |
| Bungalow 116 | 1 | 1 |
| Bungalow 117 | 1 | 1 |
| Bungalow 118 | 1 | 1 |
| Bungalow 119 | 1 | 1 |
| Bungalow 120 | 1 | 1 |
| Bungalow 121 | 1 | 1 |
| Bungalow 122 | 1 | 1 |
| Bungalow 123 | 1 | 1 |
| Bungalow 124 | 1 | 1 |
| Bungalow 125 | 1 | 1 |
| Bungalow 126 | 1 | 1 |
| Bungalow 127 | 1 | 1 |
| Bungalow 128 | 1 | 1 |
| Bungalow 129 | 1 | 1 |
| Bungalow 130 | 1 | 1 |
| Bungalow 131 | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 23.10 cr | Rs 22.32 cr |
| Bungalow 1 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 2 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 3 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 4 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 5 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 6 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 7 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 8 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 9 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 10 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
| Bungalow 11 | NA | Rs 41.15 lakh | Rs 39.76 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Adinath Patkar |
| Engineer | Mahadeo Rahate |
| Chartered Accountant | ASIMKUMAR SANTARA |
| Chartered Accountant | ASHISH MAHESHWARI & ASSOCIATES |
| Chartered Accountant | PODDAR A. & ASSOCIATES |
| Chartered Accountant | Shankarlal Jain & Associates LLP |
| Partner | Role in project |
|---|---|
| Garnet Construction Ltd. | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIt is submitted on behalf of the Applicant above named that the said Project comprises of 131 (one hundred and thirty bungalows to be constructed on all that piece and parcel of land admeasuring 64,274 sq. mtr. It is further submitted that the aforesaid project is a case of plotted development whereby the entire land is divided into fragmented plots and bungalows are developed on the said plots. It is stated on behalf of the Applicants that the civil work of the said Project is complete in all aspects. Furthermore, most of the allottees in the said Project are non - resident Indians who are in
Reason as filed by the promoter.In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 55.46% allottees for purpose of extension of RERA registration period of the said project
Complaints filed with MahaRERA12
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000409 | Milind Paltanwale | Garnet Constructions | 09/09/2017 |
| CC006000000171597 | Vijay Jadhav | GARNET CONSTRUCTION | 19/11/2019 |
| CC006000000194508 | SATISH PATEL | GARNET CONSTRUCTIONS LTD | 17/10/2020 |
| CC006000000195004 | Vithal G. Gajria & Seema V. Gajria | Garnet Construction Ltd | 24/11/2020 |
| CC006000000196098 | Subhash Tekale | Garnet Construction Ltd | 01/06/2021 |
| CC006000000196539 | Jayendra Kanabar | Garnet Construction Ltd. | 29/03/2021 |
| CC006000000210350 | SITAL SACHANANDANI | M/S. GARNET CONSTRUCTION LTD | 17/03/2022 |
| CC006000000354500 | Kishor Gosalia | Garnet Construction Limited | 27/02/2023 |
| CC006000000397918 | AMIT SURESH GANATRA | M/S. GARNET CONSTRUCTION LTD., | 23/10/2023 |
| CC12502437 | RAMESH IYER | Garnet Construction Ltd. | 17/07/2025 |
| CC12502646 | Arzina Aminmohamed Bhanjee | Garnet Construction Ltd. | 30/07/2025 |
| CC12601002 | RAJANDRA LAXMAN KULKARNI | Garnet Construction Ltd. | 24/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 May 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed268
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 268 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Magic Enclave_compressed.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: Signed Form 2 Magic Enclave.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: Signed Form 3 Magic Enclave.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 Q 3_compressed.pdf | 20 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Q3 magic enclave signed.pdf | 20 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Q3 magic enclave signed.pdf | 20 Feb 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 10 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 Sept 25 Magic Enclave.pdf | 10 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 Sept 25 Magic Enclave.pdf | 10 Dec 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 7 Oct 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 7 Oct 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 7 Oct 2025 |
| Withdrawal Update Form 2File: Engineer Certificate_Dec'23.pdf | 7 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 magic enclave june 25.pdf | 7 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 magic enclave june 25.pdf | 7 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Decu002723.pdf | 7 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Decu002723.pdf | 7 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Magic Enclave June 25.pdf | 7 Oct 2025 |
| Form 1File: FORM 1 September 2017.pdf | 31 May 2025 |
| Form 2File: Form 2 September 2017.pdf | 31 May 2025 |
| Form 3File: Form 3 September 2017.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 September 2017.pdf | 31 May 2025 |
| Form 1File: FORM 1 December 2017.pdf | 31 May 2025 |
| Form 2File: Form 2 December 2017.pdf | 31 May 2025 |
| Form 3File: Form 3 December 2017.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 December 2017.pdf | 31 May 2025 |
| Form 1File: FORM 1 March 2018.pdf | 31 May 2025 |
| Form 2File: Form 2 March 2018.pdf | 31 May 2025 |
| Form 3File: Form 3 March 2018.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 March 2018.pdf | 31 May 2025 |
| Form 1File: FORM 1 June 2018.pdf | 31 May 2025 |
| Form 2File: Form 2 June 2018.pdf | 31 May 2025 |
| Form 3File: Form 3 June 2018.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 June 2018.pdf | 31 May 2025 |
| Form 1File: FORM 1 September 2018.pdf | 31 May 2025 |
| Form 2File: Form 2 September 2018.pdf | 31 May 2025 |
| Form 3File: Form 3 September 2018.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 September 2018.pdf | 31 May 2025 |
| Form 1File: FORM 1 December 2018.pdf | 31 May 2025 |
| Form 2File: Form 2 December 2018.pdf | 31 May 2025 |
| Form 3File: Form 3 December 2018.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 December 2018.pdf | 31 May 2025 |
| Form 1File: FORM 1 March 2019.pdf | 31 May 2025 |
| Form 2File: Form 2 March 2019.pdf | 31 May 2025 |
| Form 3File: Form 3 March 2019.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 March 2019.pdf | 31 May 2025 |
| Form 1File: FORM 1 June 2019.pdf | 31 May 2025 |
| Form 2File: Form 2 June 2019.pdf | 31 May 2025 |
| Form 3File: Form 3 June 2019.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 June 2019.pdf | 31 May 2025 |
| Form 1File: FORM 1 September 2019.pdf | 31 May 2025 |
| Form 2File: Form 2 September 2019.pdf | 31 May 2025 |
| Form 3File: Form 3 September 2019.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 September 2019.pdf | 31 May 2025 |
| Form 1File: FORM 1 December 2019.pdf | 31 May 2025 |
| Form 2File: Form 2 December 2019.pdf | 31 May 2025 |
| Form 3File: Form 3 December 2019.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 December 2019.pdf | 31 May 2025 |
| Form 1File: FORM 1 December 2020.pdf | 31 May 2025 |
| Form 2File: Form 2 December 2020.pdf | 31 May 2025 |
| Form 3File: Form 3 December 2020.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 December 2020.pdf | 31 May 2025 |
| Form 1File: FORM 1 June 2020.pdf | 31 May 2025 |
| Form 2File: Form 2 June 2020.pdf | 31 May 2025 |
| Form 3File: Form 3 June 2020.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 June 2020.pdf | 31 May 2025 |
| Form 1File: FORM 1 September 2020.pdf | 31 May 2025 |
| Form 2File: Form 2 September 2020.pdf | 31 May 2025 |
| Form 3File: Form 3 September 2020.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 September 2020.pdf | 31 May 2025 |
| Form 1File: FORM 1 December 2020.pdf | 31 May 2025 |
| Form 2File: Form 2 December 2020.pdf | 31 May 2025 |
| Form 3File: Form 3 December 2020.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 December 2020.pdf | 31 May 2025 |
| Form 1File: FORM 1 March 2021.pdf | 31 May 2025 |
| Form 2File: Form 2 March 2021.pdf | 31 May 2025 |
| Form 3File: Form 3 March 2021.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 March 2021.pdf | 31 May 2025 |
| Form 1File: FORM 1 June 2021.pdf | 31 May 2025 |
| Form 2File: Form 2 June 2021.pdf | 31 May 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Magic Hill | Village Ambivali Taluka Khalapur District Raigad | 283 | Completed | Apr 2017 | Apr 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 268 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Magic Hill Enclave on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Khalapur5,900+ in Raigarh
Filed coordinates, straight-line distance. 68 registered projects within 2 km.
Godrej Woodside Estate Phase 1
Godrej Projects Development Limited
Indiabulls Savroli - 3
Sylvanus Properties Limited
VRINDAVAN FLORA
Thalia Vastu Infra Projects
World Villas Phase 1
ARIHANT SUPERSTRUCTURES LIMITED
Basalt Hills
VIYONAA WORLD LLP
Advika Hill City-1
Shirish Khivraj Gadiya
See every Raigarh project, with the district possession charts
Builder: Garnet Construction Ltd.
Garnet Construction Ltd. has 1 registration on MahaRERA, including Magic Hill Enclave. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Magic Hill Enclave is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Magic Hill Enclave?
The registered promoter entity is Garnet Construction Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Magic Hill Enclave?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Magic Hill Enclave?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Magic Hill Enclave?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Magic Hill Enclave?
The professionals named in the filing: Architect: Adinath Patkar; Engineer: Mahadeo Rahate; Chartered Accountant: ASIMKUMAR SANTARA; Chartered Accountant: ASHISH MAHESHWARI & ASSOCIATES; Chartered Accountant: PODDAR A. & ASSOCIATES; Chartered Accountant: Shankarlal Jain & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Magic Hill Enclave?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback