ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Magic Hill Enclave

Registered No litigation declared Mixed project

Magic Hill Enclave

By Garnet Construction Ltd.

RG-MH-20775 · RERA P52000004503 · Last updated on MahaRERA portal: 8 Jun 2026

Source: official MahaRERA filing

Red flags

  • 12 complaints at MahaRERA
  • Completion date moved by 60 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 60 months from the original
681 of 1441Construction stages doneacross 132 buildings; furthest along: Installation of Lifts, 90%
19 of 132Units unsoldnot recorded sold or booked
12Complaints at MahaRERAon this registration
Jump to the 268 documents Report an error

Magic Hill Enclave is a Mixed project by Garnet Construction Ltd. in Raigarh, Maharashtra, registered with MahaRERA as P52000004503 on 9 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 113 of the 132 units on this registration are recorded sold or booked, and 681 of 1441 construction stages are filed complete. 12 complaints are on record with the regulator.

At a glance

Project

  • NameMagic Hill Enclave
  • TypeMixed
  • Location
    • Khalapur Road
    • Khalapur
    • Ambivali T. Wankhal (CT)
    • Raigarh
    • 410202
  • Pincode410202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000004503
  • ReraGenie IDRG-MH-20775

Builder

  • NameGarnet Construction Ltd.
  • Entity typeCompany
  • Managing DirectorKishankumar Jugalkishor Kedia
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
  • Buildings131 building records
  • Documents filed268 files

Current status

86%113 of 132 units booked
96.6%Work done, per cost certificate

Figures as on 8 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bungalow 1NA22101
Bungalow 2NA22101
Bungalow 3NA22101
Bungalow 4NA22101
Bungalow 5NA22101
Bungalow 6NA33101
Bungalow 7NA33101
Bungalow 8NA33101
Bungalow 9NA22101
Bungalow 10NA33101
Bungalow 11NA33101
Bungalow 12NA22101
Bungalow 13NA22101
Bungalow 14NA22101
Bungalow 15NA22101
Bungalow 16NA22101
Bungalow 17NA22101
Bungalow 18NA22101
Bungalow 19NA22101
Bungalow 20NA22101
Bungalow 21NA22101
Bungalow 22NA22101
Bungalow 23NA22101
Bungalow 24NA22101
Bungalow 25NA22101
Bungalow 26NA22101
Bungalow 27NA22101
Bungalow 28NA22101
Bungalow 29NA22101
Bungalow 30NA22101
Bungalow 31NA22101
Bungalow 32NA22101
Bungalow 33NA22101
Bungalow 34NA22101
Bungalow 35NA22101
Bungalow 36NA22101
Bangalow 37NA33101
Bungalow 38NA22101
Bungalow 39NA22101
Bungalow 40NA22101
Bungalow 41NA22101
Bungalow 42NA22101
Bungalow 43NA22101
Bungalow 44NA22101
Bungalow 45NA22101
Bungalow 46NA22101
Bungalow 47NA22101
Bungalow 48NA22101
Bungalow 49NA22101
Bungalow 50NA22101
Bungalow 51NA22101
Bungalow 52NA22101
Bungalow 53NA22101
Bungalow 54NA22101
Bungalow 55NA22101
Bungalow 56NA22101
Bungalow 57NA22101
Bungalow 58NA22101
Bungalow 59NA22101
Bungalow 60NA22101
Bungalow 61NA22101
Bungalow 62NA22101
Bungalow 63NA22101
Bungalow 64NA22101
Bungalow 65NA22101
Bungalow 66NA22101
Bungalow 67NA22101
Bungalow 68NA22101
Bungalow 69NA22101
Bungalow 70NA22101
Bungalow 71NA22101
Bungalow 72NA22101
Bungalow 73NA22101
Bungalow 74NA22101
Bungalow 75NA22101
Bungalow 76NA22101
Bungalow 77NA22101
Bungalow 78NA22101
Bungalow 79NA22101
Bungalow 80NA22101
Bungalow 81NA22101
Bungalow 82NA22101
Bungalow 83NA22101
Bungalow 84NA22101
Bungalow 85NA22101
Bungalow 86NA22101
Bungalow 87NA22101
Bungalow 88NA22101
Bungalow 89NA22101
Bungalow 90NA22101
Bungalow 91NA22101
Bungalow 92NA22101
Bungalow 93NA22101
Bungalow 94NA22101
Bungalow 95NA22101
Bungalow 96NA22101
Bungalow 97NA22101
Bungalow 98NA22101
Bungalow 99NA22101
Bungalow 100NA22101
Bungalow 101NA22101
Bungalow 102NA22101
Bungalow 103NA22101
Bungalow 104NA22101
Bungalow 105NA22101
Bungalow 106NA22101
Bungalow 107NA22101
Bungalow 108NA22101
Bungalow 109NA22101
Bungalow 110NA22101
Bungalow 111NA22101
Bungalow 112NA22101
Bungalow 113NA22101
Bungalow 114NA22101
Bungalow 115NA22101
Bungalow 116NA22101
Bungalow 117NA22101
Bungalow 118NA22101
Bungalow 119NA22101
Bungalow 120NA22101
Bungalow 121NA22101
Bungalow 122NA22101
Bungalow 123NA22101
Bungalow 124NA22101
Bungalow 125NA22101
Bungalow 126NA22101
Bungalow 127NA22101
Bungalow 128NA22101
Bungalow 129NA22101
Bungalow 130NA22101
Bungalow 131NA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 8 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 132 buildings; the table lists the first 20.

681 of 1441 construction stages are filed complete across 132 buildings. The stage furthest along is Installation of Lifts, at 90%.

Bungalow 152%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 265%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 352%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 452%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 552%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 652%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 752%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 852%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 952%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1052%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1152%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1252%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1352%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1452%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1552%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1665%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1752%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1861%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 1965%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Bungalow 2061%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 8 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes10%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes60%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes10%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes90%
Open ParkingYes100%

Parking filed130

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots130
Open Space130
BuildingOpen SpaceTotal
Bungalow 111
Bungalow 211
Bungalow 311
Bungalow 411
Bungalow 511
Bungalow 611
Bungalow 711
Bungalow 811
Bungalow 911
Bungalow 1011
Bungalow 1111
Bungalow 1211
Bungalow 1311
Bungalow 1411
Bungalow 1511
Bungalow 1611
Bungalow 1711
Bungalow 1811
Bungalow 1911
Bungalow 2011
Bungalow 2111
Bungalow 2211
Bungalow 2311
Bungalow 2411
Bungalow 2511
Bungalow 2611
Bungalow 2711
Bungalow 2811
Bungalow 2911
Bungalow 3011
Bungalow 3111
Bungalow 3211
Bungalow 3311
Bungalow 3411
Bungalow 3511
Bungalow 3611
Bungalow 3811
Bungalow 3911
Bungalow 4011
Bungalow 4111
Bungalow 4211
Bungalow 4311
Bungalow 4411
Bungalow 4511
Bungalow 4611
Bungalow 4711
Bungalow 4811
Bungalow 4911
Bungalow 5011
Bungalow 5111
Bungalow 5211
Bungalow 5311
Bungalow 5411
Bungalow 5511
Bungalow 5611
Bungalow 5711
Bungalow 5811
Bungalow 5911
Bungalow 6011
Bungalow 6111
Bungalow 6211
Bungalow 6311
Bungalow 6411
Bungalow 6511
Bungalow 6611
Bungalow 6711
Bungalow 6811
Bungalow 6911
Bungalow 7011
Bungalow 7111
Bungalow 7211
Bungalow 7311
Bungalow 7411
Bungalow 7511
Bungalow 7611
Bungalow 7711
Bungalow 7811
Bungalow 7911
Bungalow 8011
Bungalow 8111
Bungalow 8211
Bungalow 8311
Bungalow 8411
Bungalow 8511
Bungalow 8611
Bungalow 8711
Bungalow 8811
Bungalow 8911
Bungalow 9011
Bungalow 9111
Bungalow 9211
Bungalow 9311
Bungalow 9411
Bungalow 9511
Bungalow 9611
Bungalow 9711
Bungalow 9811
Bungalow 9911
Bungalow 10011
Bungalow 10111
Bungalow 10211
Bungalow 10311
Bungalow 10411
Bungalow 10511
Bungalow 10611
Bungalow 10711
Bungalow 10811
Bungalow 10911
Bungalow 11011
Bungalow 11111
Bungalow 11211
Bungalow 11311
Bungalow 11411
Bungalow 11511
Bungalow 11611
Bungalow 11711
Bungalow 11811
Bungalow 11911
Bungalow 12011
Bungalow 12111
Bungalow 12211
Bungalow 12311
Bungalow 12411
Bungalow 12511
Bungalow 12611
Bungalow 12711
Bungalow 12811
Bungalow 12911
Bungalow 13011
Bungalow 13111

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area64,274 sq m
Land owned byThe promoter
Named landownersNone
Declared on2 Jun 2025

Approvals and building plan

Sanctioning authorityCollector of Raigad
Permissible FSI18557.73
Proposed, not sanctioned18,558 sq m
Buildings approved131
Buildings sanctioned131

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMumbai
Estimated costRs 77.00 cr
Cost incurredRs 74.41 cr
Work done96.64%
BuildingWingEstimatedIncurred
-NARs 23.10 crRs 22.32 cr
Bungalow 1NARs 41.15 lakhRs 39.76 lakh
Bungalow 2NARs 41.15 lakhRs 39.76 lakh
Bungalow 3NARs 41.15 lakhRs 39.76 lakh
Bungalow 4NARs 41.15 lakhRs 39.76 lakh
Bungalow 5NARs 41.15 lakhRs 39.76 lakh
Bungalow 6NARs 41.15 lakhRs 39.76 lakh
Bungalow 7NARs 41.15 lakhRs 39.76 lakh
Bungalow 8NARs 41.15 lakhRs 39.76 lakh
Bungalow 9NARs 41.15 lakhRs 39.76 lakh
Bungalow 10NARs 41.15 lakhRs 39.76 lakh
Bungalow 11NARs 41.15 lakhRs 39.76 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAdinath Patkar
EngineerMahadeo Rahate
Chartered AccountantASIMKUMAR SANTARA
Chartered AccountantASHISH MAHESHWARI & ASSOCIATES
Chartered AccountantPODDAR A. & ASSOCIATES
Chartered AccountantShankarlal Jain & Associates LLP
PartnerRole in project
Garnet Construction Ltd.-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000013842Dec 2022 → Dec 2023

Reason as filed by the promoterIt is submitted on behalf of the Applicant above named that the said Project comprises of 131 (one hundred and thirty bungalows to be constructed on all that piece and parcel of land admeasuring 64,274 sq. mtr. It is further submitted that the aforesaid project is a case of plotted development whereby the entire land is divided into fragmented plots and bungalows are developed on the said plots. It is stated on behalf of the Applicants that the civil work of the said Project is complete in all aspects. Furthermore, most of the allottees in the said Project are non - resident Indians who are in

EXT52000019480Dec 2022 → Dec 2027

Reason as filed by the promoter.In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 55.46% allottees for purpose of extension of RERA registration period of the said project

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000000409Milind PaltanwaleGarnet Constructions09/09/2017
CC006000000171597Vijay JadhavGARNET CONSTRUCTION19/11/2019
CC006000000194508SATISH PATELGARNET CONSTRUCTIONS LTD17/10/2020
CC006000000195004Vithal G. Gajria & Seema V. GajriaGarnet Construction Ltd24/11/2020
CC006000000196098Subhash TekaleGarnet Construction Ltd01/06/2021
CC006000000196539Jayendra KanabarGarnet Construction Ltd.29/03/2021
CC006000000210350SITAL SACHANANDANIM/S. GARNET CONSTRUCTION LTD17/03/2022
CC006000000354500Kishor GosaliaGarnet Construction Limited27/02/2023
CC006000000397918AMIT SURESH GANATRAM/S. GARNET CONSTRUCTION LTD.,23/10/2023
CC12502437RAMESH IYERGarnet Construction Ltd.17/07/2025
CC12502646Arzina Aminmohamed BhanjeeGarnet Construction Ltd.30/07/2025
CC12601002RAJANDRA LAXMAN KULKARNIGarnet Construction Ltd.24/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 May 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed268

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 268 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Magic Enclave_compressed.pdf8 Jun 2026
Withdrawal Update Form 2File: Signed Form 2 Magic Enclave.pdf8 Jun 2026
Withdrawal Update Form 3File: Signed Form 3 Magic Enclave.pdf8 Jun 2026
Withdrawal Update Form 1File: Withdrawal Application Form1 Q 3_compressed.pdf20 Feb 2026
Withdrawal Update Form 2File: Form 2 Q3 magic enclave signed.pdf20 Feb 2026
Withdrawal Update Form 3File: Form 3 Q3 magic enclave signed.pdf20 Feb 2026
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf10 Dec 2025
Withdrawal Update Form 2File: Form 2 Sept 25 Magic Enclave.pdf10 Dec 2025
Withdrawal Update Form 3File: Form 3 Sept 25 Magic Enclave.pdf10 Dec 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf7 Oct 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf7 Oct 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf7 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate_Dec'23.pdf7 Oct 2025
Withdrawal Update Form 2File: Form 2 magic enclave june 25.pdf7 Oct 2025
Withdrawal Update Form 2File: Form 2 magic enclave june 25.pdf7 Oct 2025
Withdrawal Update Form 3File: Form 3 Decu002723.pdf7 Oct 2025
Withdrawal Update Form 3File: Form 3 Decu002723.pdf7 Oct 2025
Withdrawal Update Form 3File: Form 3 Magic Enclave June 25.pdf7 Oct 2025
Form 1File: FORM 1 September 2017.pdf31 May 2025
Form 2File: Form 2 September 2017.pdf31 May 2025
Form 3File: Form 3 September 2017.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2017.pdf31 May 2025
Form 1File: FORM 1 December 2017.pdf31 May 2025
Form 2File: Form 2 December 2017.pdf31 May 2025
Form 3File: Form 3 December 2017.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2017.pdf31 May 2025
Form 1File: FORM 1 March 2018.pdf31 May 2025
Form 2File: Form 2 March 2018.pdf31 May 2025
Form 3File: Form 3 March 2018.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2018.pdf31 May 2025
Form 1File: FORM 1 June 2018.pdf31 May 2025
Form 2File: Form 2 June 2018.pdf31 May 2025
Form 3File: Form 3 June 2018.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2018.pdf31 May 2025
Form 1File: FORM 1 September 2018.pdf31 May 2025
Form 2File: Form 2 September 2018.pdf31 May 2025
Form 3File: Form 3 September 2018.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2018.pdf31 May 2025
Form 1File: FORM 1 December 2018.pdf31 May 2025
Form 2File: Form 2 December 2018.pdf31 May 2025
Form 3File: Form 3 December 2018.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2018.pdf31 May 2025
Form 1File: FORM 1 March 2019.pdf31 May 2025
Form 2File: Form 2 March 2019.pdf31 May 2025
Form 3File: Form 3 March 2019.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2019.pdf31 May 2025
Form 1File: FORM 1 June 2019.pdf31 May 2025
Form 2File: Form 2 June 2019.pdf31 May 2025
Form 3File: Form 3 June 2019.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2019.pdf31 May 2025
Form 1File: FORM 1 September 2019.pdf31 May 2025
Form 2File: Form 2 September 2019.pdf31 May 2025
Form 3File: Form 3 September 2019.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2019.pdf31 May 2025
Form 1File: FORM 1 December 2019.pdf31 May 2025
Form 2File: Form 2 December 2019.pdf31 May 2025
Form 3File: Form 3 December 2019.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2019.pdf31 May 2025
Form 1File: FORM 1 December 2020.pdf31 May 2025
Form 2File: Form 2 December 2020.pdf31 May 2025
Form 3File: Form 3 December 2020.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2020.pdf31 May 2025
Form 1File: FORM 1 June 2020.pdf31 May 2025
Form 2File: Form 2 June 2020.pdf31 May 2025
Form 3File: Form 3 June 2020.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2020.pdf31 May 2025
Form 1File: FORM 1 September 2020.pdf31 May 2025
Form 2File: Form 2 September 2020.pdf31 May 2025
Form 3File: Form 3 September 2020.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 September 2020.pdf31 May 2025
Form 1File: FORM 1 December 2020.pdf31 May 2025
Form 2File: Form 2 December 2020.pdf31 May 2025
Form 3File: Form 3 December 2020.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 December 2020.pdf31 May 2025
Form 1File: FORM 1 March 2021.pdf31 May 2025
Form 2File: Form 2 March 2021.pdf31 May 2025
Form 3File: Form 3 March 2021.pdf31 May 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2021.pdf31 May 2025
Form 1File: FORM 1 June 2021.pdf31 May 2025
Form 2File: Form 2 June 2021.pdf31 May 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Magic HillVillage Ambivali Taluka Khalapur District Raigad283CompletedApr 2017Apr 2017

How this compares with Raigarh

86%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 60 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Magic Hill Enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khalapur5,900+ in Raigarh

2 kmMagic Hill EnclaveCompleted 37Lapsed / revoked 28Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: Garnet Construction Ltd.

Garnet Construction Ltd. has 1 registration on MahaRERA, including Magic Hill Enclave. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Magic Hill Enclave is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Magic Hill Enclave?

The registered promoter entity is Garnet Construction Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Magic Hill Enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Magic Hill Enclave?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Magic Hill Enclave?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Magic Hill Enclave?

The professionals named in the filing: Architect: Adinath Patkar; Engineer: Mahadeo Rahate; Chartered Accountant: ASIMKUMAR SANTARA; Chartered Accountant: ASHISH MAHESHWARI & ASSOCIATES; Chartered Accountant: PODDAR A. & ASSOCIATES; Chartered Accountant: Shankarlal Jain & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Magic Hill Enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Magic Hill Enclave. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Magic Hill Enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.