Red flags

  • Litigation declared, 4 cases
  • Allotment letter deviates from the model form

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • All 1 earlier projects delivered on promise
Jump to the 5 documents Report an error

Wind Chimes is a Residential / Group Housing project by PR Enterprises in Nashik, Maharashtra, registered with MahaRERA as PR1221012601683 on 27 Aug 2026. Possession is promised by 31 Dec 2032.

At a glance

Project

  • NameWind Chimes
  • TypeResidential / Group Housing
  • Location
    • Gangapur Road
    • Near Wonderzone Trampoline Park
    • Govardhan
    • Nashik
    • 422222
  • Pincode422222
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1221012601683
  • ReraGenie IDRG-MH-83118

Builder

  • NamePR Enterprises
  • Entity typePartnership
  • GSTIN27ABFFP3493A1ZB
  • Track record1 past project →

Key dates

todayRegisteredAug 2026PromisedDec 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Aug 2026
  • Promised completion31 Dec 2032
  • Revised completionNone
  • Buildings77 building records
  • Documents filed5 files

Current status

0%0 of 77 units booked

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building/Unit No. 1NA33101
Building/Unit No. 2NA33101
Building/Unit No. 3NA33101
Building/Unit No. 4NA33101
Building/Unit No. 5NA33101
Building/Unit No. 6NA33101
Building/Unit No. 7NA33101
Building/Unit No. 8 NA33101
Building/Unit No. 9 NA33101
Building/Unit No. 10 NA33101
Building/Unit No. 11 NA33101
Building/Unit No. 12 NA33101
Building/Unit No. 12A NA33101
Building/Unit No. 14 NA33101
Building/Unit No. 15 NA33101
Building/Unit No. 16NA33101
Building/Unit No. 17NA33101
Building/Unit No. 18NA33101
Building/Unit No. 19NA33101
Building/Unit No. 20NA33101
Building/Unit No. 21NA33101
Building/Unit No. 22NA33101
Building/Unit No. 23NA33101
Building/Unit No. 24NA33101
Building/Unit No. 25NA33101
Building/Unit No. 26NA33101
Building/Unit No. 27NA33101
Building/Unit No. 28NA33101
Building/Unit No. 29NA33101
Building/Unit No. 30NA33101
Building/Unit No. 31NA33101
Building/Unit No. 32NA33101
Building/Unit No. 33NA33101
Building/Unit No. 34NA33101
Building/Unit No. 35NA33101
Building/Unit No. 36NA33101
Building/Unit No. 37NA33101
Building/Unit No. 38NA33101
Building/Unit No. 39NA33101
Building/Unit No. 40NA33101
Building/Unit No. 41NA33101
Building/Unit No. 42NA33101
Building/Unit No. 43NA33101
Building/Unit No. 44NA33101
Building/Unit No. 45NA33101
Building/Unit No. 46NA33101
Building/Unit No. 47NA33101
Building/Unit No. 48NA33101
Building/Unit No. 49NA33101
Building/Unit No. 50NA32101
Building/Unit No. 51NA32101
Building/Unit No. 52NA33101
Building/Unit No. 53NA33101
Building/Unit No. 54NA33101
Building/Unit No. 55NA33101
Building/Unit No. 56NA33101
Building/Unit No. 57NA33101
Building/Unit No. 58NA33101
Building/Unit No. 59NA33101
Building/Unit No. 60NA33101
Building/Unit No. 61NA33101
Building/Unit No. 62NA33101
Building/Unit No. 63NA33101
Building/Unit No. 64NA33101
Building/Unit No. 65NA33101
Building/Unit No. 66NA33101
Building/Unit No. 67NA33101
Building/Unit No. 68NA33101
Building/Unit No. 69NA33101
Building/Unit No. 70NA33101
Building/Unit No. 71NA33101
Building/Unit No. 72NA33101
Building/Unit No. 73NA33101
Building/Unit No. 74NA33101
Building/Unit No. 75NA33101
Building/Unit No. 76NA33101
Building/Unit No. 77NA33101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.

Building/Unit No. 10%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 20%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 30%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 40%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 50%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 60%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 70%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 80%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 90%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 100%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 1151%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure83%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks62%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 1251%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure83%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks62%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 12A0%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 140%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 150%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 160%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 170%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 180%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 190%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building/Unit No. 200%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNo0%
Open ParkingNo0%

Parking filed170

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots170
Stilt / Ground170
BuildingStilt / GroundTotal
Building/Unit No. 122
Building/Unit No. 211
Building/Unit No. 322
Building/Unit No. 411
Building/Unit No. 522
Building/Unit No. 611
Building/Unit No. 722
Building/Unit No. 811
Building/Unit No. 922
Building/Unit No. 1011
Building/Unit No. 1122
Building/Unit No. 1211
Building/Unit No. 12A22
Building/Unit No. 1411
Building/Unit No. 1522
Building/Unit No. 1611
Building/Unit No. 1711
Building/Unit No. 1822
Building/Unit No. 1911
Building/Unit No. 2022
Building/Unit No. 2122
Building/Unit No. 2211
Building/Unit No. 2322
Building/Unit No. 2411
Building/Unit No. 2533
Building/Unit No. 2644
Building/Unit No. 2722
Building/Unit No. 2822
Building/Unit No. 2922
Building/Unit No. 3011
Building/Unit No. 3122
Building/Unit No. 3211
Building/Unit No. 3322
Building/Unit No. 3411
Building/Unit No. 3522
Building/Unit No. 3611
Building/Unit No. 3722
Building/Unit No. 3833
Building/Unit No. 3944
Building/Unit No. 4022
Building/Unit No. 4111
Building/Unit No. 4222
Building/Unit No. 4311
Building/Unit No. 4422
Building/Unit No. 4511
Building/Unit No. 4622
Building/Unit No. 4711
Building/Unit No. 4822
Building/Unit No. 4933
Building/Unit No. 5022
Building/Unit No. 5133
Building/Unit No. 5233
Building/Unit No. 5333
Building/Unit No. 5433
Building/Unit No. 5533
Building/Unit No. 5633
Building/Unit No. 5733
Building/Unit No. 5833
Building/Unit No. 5944
Building/Unit No. 6044
Building/Unit No. 6133
Building/Unit No. 6233
Building/Unit No. 6333
Building/Unit No. 6433
Building/Unit No. 6533
Building/Unit No. 6633
Building/Unit No. 6733
Building/Unit No. 6833
Building/Unit No. 6933
Building/Unit No. 7033
Building/Unit No. 7133
Building/Unit No. 7233
Building/Unit No. 7333
Building/Unit No. 7433
Building/Unit No. 7533
Building/Unit No. 7633
Building/Unit No. 7733

Land and ownership3

MahaRERA does not publish landowner contact details.

Land area23,100 sq m
Promoter owns the landNo
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Jul 2026
LandownerVillageDistrict
Amar Mahesh KadakiaNashikNashik
Vaishali Amar KadakiaNashikNashik
Mahesh Chimanlal KadakiaNashikNashik

Approvals and building plan

Permissible FSI22092.52
Proposed, not sanctioned17,741 sq m
Buildings approved77
Buildings sanctioned77

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.

Separate project accountDeclared
Bank branchVASTUSHRI NO.3THATTE NAGAR GANGAPUR COLLEGE, LINKROADNASHIKMAHARASHTRA422 005

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVivek Jaykhedkar
EngineerSagar Shah
Chartered AccountantNirav Shailesh Shah & Co
PartnerRole in project
PR Enterprises-

Litigation declared4

CaseCourtStatus
370/202516th Extra Jt. Civil JudgeOngoing
413/20259-10th Jt. Civil Judge Senior Division and Addl. CJM Nashik Mr. J. V. PaliwalOngoing
834/20245th Jt. Civil JudgeOngoing
17/20257-II Jt. Civil JudgeOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

Documents filed5

As listed on the registration. The files themselves are on the MahaRERA portal.

DocumentUploaded
SP 120 Jul 2026
Annexure A Order 503 Jul 2026
SP 129 May 2026
SP 229 May 2026
SP 329 May 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing.

1 delivered on promise
ProjectStatusPromisedDeliveredLitigation
Trinity SquareCompletedNov 2025Nov 2025No

How this compares with Nashik

0%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,144 Nashik projects on ReraGenie, from their own filings.

Keep Wind Chimes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Wonderzone Trampoline Park4,144 in Nashik

Builder: PR Enterprises

PR Enterprises has 1 registration on MahaRERA, including Wind Chimes. Its filings disclose 1 earlier MahaRERA project: 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if Wind Chimes is delayed beyond 31 Dec 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Wind Chimes?

The registered promoter entity is PR Enterprises, a partnership as per the filing. Its GSTIN 27ABFFP3493A1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Wind Chimes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Wind Chimes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Wind Chimes?

The professionals named in the filing: Architect: Vivek Jaykhedkar; Engineer: Sagar Shah; Chartered Accountant: Nirav Shailesh Shah & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Wind Chimes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Planning to buy here? The Rs 499 buyer report adds red flags, the progress-versus-promise read, this promoter's other registrations and what the filed documents say, plus a ZIP of every document on the filing. It includes the Rs 299 project watch free for 90 days: an email in plain words every time this project's filing changes. See a real sample report before you buy. Get the buyer report · Rs 499
Studying this micro-market? The developer project analysis maps every registration within 5 km of this project from filed coordinates, reads what the market absorbs and what competes, prices the parcel, and takes the promoter's whole book apart, facts with their N, never a verdict. See a complete sample first. Get the developer analysis · Rs 2,999

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Wind Chimes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TULJAI TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.