Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2021Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 40 documents Report an error

WESTLINE FAIRMONT is a Residential/Group Housing project by WESTLINE BUILDERS PVT LTD in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180507/001655 on 7 May 2018. Possession is promised by 30 Sep 2021. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameWESTLINE FAIRMONT
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/180507/001655
  • ReraGenie IDRG-KA-86008

Builder

  • NameWESTLINE BUILDERS PVT LTD
  • Entity typeCompany
  • CINU45205KA2014PTC075160
  • Authorized SignatoryNASIR MOHIDEEN
  • OthersMAHAMMED SUHAIL
  • Other registrations2 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredMay 2018First promiseDec 2020Revised toSep 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 May 2018
  • Promised completion30 Sep 2021
  • Revised completionRevised to 30 Sep 2021 (originally 31 Dec 2020)
  • Buildings1 building record
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WESTLINE FAIRMONT---15015

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area549 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.30 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2020 → Sep 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180507/001655 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: CERTIFICATE OF INCORPORATION.pdf-
Comencment-
SITE PLAN-
LAYOUT PLAN-
PROFORMA OF SALE DEED FAIRMONT-
AGREEMENT FOR SALE FAIRMONT - FORMAT-
SALE DEED AND RTC-
SECTION-
Single Site-
FAIRMONT ALLOTMENT LETTER-
Brochure-
Specification-
EC-FAIRMONT-
KHATA-
JDA-
FIRE NOC FAIRMONT-
APPROVED LAYOUT PLAN-
MYSCAN_20160406_0015-
CONVERSION (2)-
Balance Sheet 2016 - 2017File: BALANCE SHEET 2017.pdf-
Balance Sheet 2015 - 2016File: BALANCE SHEET 2016.pdf-
Balance Sheet 2014 - 2015File: BALANCE SHEET.pdf-
Audited Profit and Loss Statement 2016 - 2017File: PROFIT AND LOSS STATEMENT 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P & L AC 2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P & L 2015.pdf-
Director's Report 2016 - 2017File: DIRECTORS REPORT 2017.pdf-
Director's Report 2015 - 2016File: DIRECTORS REPORT 2016.pdf-
Director's Report 2014 - 2015File: DIRECTORS REPORT 2015.pdf-
Cash Flow Statement 2016 - 2017File: CASH FLOW 2017.pdf-
Cash Flow Statement 2015 - 2016File: CASH FLOW 2016.pdf-
Auditor's Report 2016 - 2017File: AUDITORS REPORT 2017.pdf-
Auditor's Report 2015 - 2016File: AUDITORS REPORT 2016.pdf-
Auditor's Report 2014 - 2015File: AUDITORS REPORT 2015.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR ACKNOWLEGMENT 2017.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR ACHNOWLEGMENT 2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR ACHNOWLEGMENT2015.pdf-
FORM B-
Prospectus/BrochureFile: Fairmont RERA Brochure.pdf-
Advertisement Copy 1File: RERA ADVERTISEMENT.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_180507_001655.xlsx-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
WESTLINE SIGNATURE-OngoingJun 2022Not delivered
WESTLINE SKYDALE-OngoingDec 2019Not delivered

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 9 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep WESTLINE FAIRMONT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmWESTLINE FAIRMONTOther 79Dot size: filed unitsN

Filed coordinates, straight-line distance. 79 registered projects within 2 km.

Builder: WESTLINE BUILDERS PVT LTD

Westline Builders Pvt Ltd has 3 registrations on RERA Karnataka, including Westline Signature and WESTLINE FAIRMONT. Its filings declare 3 earlier projects, none of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if WESTLINE FAIRMONT is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of WESTLINE FAIRMONT?

The registered promoter entity is WESTLINE BUILDERS PVT LTD, a company as per the filing. Its CIN U45205KA2014PTC075160 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in WESTLINE FAIRMONT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in WESTLINE FAIRMONT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WESTLINE FAIRMONT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WESTLINE FAIRMONT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.