ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Wellwisher Town

Completed No litigation declared Residential / Group Housing project

Wellwisher Town

By Wellwisher Properties

RG-MH-01685 · RERA P52000000721 · Last updated on MahaRERA portal: 6 Jul 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
109 of 143Construction stages doneacross 13 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

Wellwisher Town is a Residential / Group Housing project by Wellwisher Properties in Raigarh, Maharashtra, registered with MahaRERA as P52000000721 on 23 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2025.

At a glance

Project

  • NameWellwisher Town
  • TypeResidential / Group Housing
  • Location
    • khopoli
    • khopoli muncipal council
    • Khalapur
    • Raigarh
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000000721
  • ReraGenie IDRG-MH-01685

Builder

  • NameWellwisher Properties
  • Entity typePartnership
  • PartnerHimgiri Dealcom LLP Himgiri Dealcom LLP

Key dates

this monthRegisteredJul 2017PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings13 building records
  • Documents filed122 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
building no 1NA100000
Building no 2NA100000
Building No 3NA100000
Building No 4NA100000
building no 5NA100000
Building no 6NA100000
Building no 7NA100000
Building no 8NA100000
Building no 9NA160000
building no 10NA160000
building no 11NA00000
club houseNA30000
Municipal officeNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building13

As on 6 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

109 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is Podiums (if any), at 0%.

building no 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building no 291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
building no 591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building no 691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building no 791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building no 891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building no 991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
building no 1045%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
building no 110%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
club house36%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Municipal office91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes48%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes30%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed774

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots774
Closed/Covered423
Open Space351
BuildingClosed/CoveredOpen SpaceTotal
building no 1504595
Building no 202020
Building No 38627113
Building No 4306898
building no 502020
Building no 6355994
Building no 79266158
Building no 89246138
Municipal office38038

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI61145.04
Proposed, not sanctioned44,958 sq m
Buildings approved13
Buildings sanctioned12

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVardhaman Market Sector 17, Vashi Navi Mumbai

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s. DESTINATION ARCHITECTURE INTERIOR DESIGNS
EngineerAdarshila Consultants
PartnerRole in project
Wellwisher Properties-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Jul 2024

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Building no-10 OC Verified.pdf6 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 F Y 2022-23-WP.pdf1 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Building No 9 occupancy.pdf13 Jan 2024
Proforma of Agreement for saleFile: rera DEED -.pdf22 Sep 2023
Certificates of CA (Form 3)File: Form 3-WP_Signed.pdf15 May 2023
Certificates of CA (Form 3)File: CA-Certifcate -WP-Dec 2022_Signed.pdf22 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5-WP-F Y 2021-22.pdf19 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC BUILDING NO 3 5 6 7 8.pdf18 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate BUILDING NO 4.pdf18 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Building No 9 occupancy (2).pdf18 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5-WP-F Y 2020-21.pdf10 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 53-FORM 2.pdf14 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 TILL NOV 31 R2.pdf29 Dec 2022
Certificates of CA (Form 3)File: FORM 3-JUNE 2022 WP.pdf16 Dec 2022
Certificates of CA (Form 3)File: FORM 3-SEPT 2022 WP.pdf16 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: New doc Jul 15, 2022-Dec 2021_compressed-compressed.pdf18 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: New doc Jul 15, 2022 -March 2022 (1).pdf18 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: New doc Jul 15, 2022 -June 2022 (1).pdf18 Jul 2022
Certificates of CA (Form 3)File: ilovepdf_merged.pdf21 Apr 2022
Certificates of CA (Form 3)File: ilovepdf_merged.pdf21 Apr 2022
Certificates of CA (Form 3)File: Form 3 WP 30092021.pdf21 Apr 2022
Certificates of CA (Form 3)File: Form 3 WP 31122021.pdf21 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC 1st -1,2,4.pdf13 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 38_fORM 1.pdf22 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 52-FORM 2.pdf22 Mar 2021
Certificates of CA (Form 3)File: Form 3-Dec 2020.pdf20 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Annual F Y 2019-20-WP.pdf19 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 37 Sept 2020.pdf7 Dec 2020
Certificates of CA (Form 3)File: Form 3 Sept 2020.pdf7 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RCC.pdf4 Dec 2020
Certificates of CA (Form 3)File: Form 3- Dec2019.pdf30 Sep 2020
Certificates of CA (Form 3)File: Form 3-March 2020.pdf30 Sep 2020
Certificates of CA (Form 3)File: Form 3- June 2020.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Annual Report-F Y 2018-19-WP.pdf9 Mar 2020
OtherFile: RERA LETTER_compressed (1).pdf3 Mar 2020
Certificates of CA (Form 5)File: RERA Annual Report-F Y 2018-19-WP.pdf28 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate_compressed.pdf9 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf9 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate_compressed.pdf9 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate_compressed.pdf9 Nov 2019
Certificates of CA (Form 3)File: CA Certificate_compressed.pdf9 Nov 2019
Certificates of CA (Form 3)File: CA Certificate.pdf9 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate 1-4.pdf28 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate 5-8.pdf28 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate 1-5.pdf28 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate 6-9.pdf28 May 2019
Certificates of CA (Form 3)File: CA Certificate.pdf28 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate-1-4.pdf29 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate-5-8.pdf29 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-1-5.pdf29 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-6-9.pdf29 Jan 2019
Certificates of CA (Form 3)File: CA Certificate final.pdf29 Jan 2019
Certificates of CA (Form 5)File: form 5.pdf29 Dec 2018
Certificates of CA (Form 3)File: CA certificate final.pdf27 Nov 2018
Certificates of CA (Form 3)File: CA certificate final.pdf27 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-1-4.pdf20 Nov 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-5-8.pdf20 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate-1-5.pdf20 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate-6-9.pdf20 Nov 2018
Certificates of CA (Form 3)File: CA certificate.pdf11 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate 1-4.pdf5 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate 5-8.pdf5 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate 1-5.pdf5 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate 6-9.pdf5 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-1-3.pdf27 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-4-6.pdf27 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-7-8.pdf27 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate-1-5.pdf27 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate--6-9.pdf27 Mar 2018
Certificates of CA (Form 3)File: CA certificate.pdf27 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-1-4.pdf18 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-5-7.pdf18 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate-1-5.pdf18 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate-6-9.pdf18 Nov 2017
Certificates of CA (Form 3)File: Ca certificate -1-7.pdf18 Nov 2017
Certificates of CA (Form 3)File: Ca certificate -8-13.pdf18 Nov 2017
Certificates of CA (Form 3)File: Ca certificate -14-19.pdf18 Nov 2017
Certificates of CA (Form 3)File: Ca certificate -20-26.pdf18 Nov 2017
Details of encumbrancesFile: encumbrance certificate-1-1.pdf15 Nov 2017
Proforma of Allotment letterFile: rera deed regular.pdf15 Nov 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Wellwisher Town on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near khopoli muncipal council5,900+ in Raigarh

2 kmWellwisher TownCompleted 25Lapsed / revoked 6Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 65 registered projects within 2 km.

Builder: Wellwisher Properties

Wellwisher Properties has 1 registration on MahaRERA, including Wellwisher Town. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Wellwisher Town is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Wellwisher Town?

The registered promoter entity is Wellwisher Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Wellwisher Town?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Wellwisher Town?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Wellwisher Town?

The professionals named in the filing: Architect: M/s. DESTINATION ARCHITECTURE INTERIOR DESIGNS; Engineer: Adarshila Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Wellwisher Town?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Wellwisher Town. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Wellwisher Town to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.