ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Godrej Hillview Estate

Completed No litigation declared Plotted project

Godrej Hillview Estate

By Godrej Projects Development Limited

RG-MH-17800 · RERA P52000055348 · Last updated on MahaRERA portal: 19 Jun 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedregistration recorded completed
378 of 970Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

Godrej Hillview Estate is a Plotted project by Godrej Projects Development Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000055348 on 18 Mar 2024. The registration is recorded completed; possession was promised by 31 Mar 2027. 592 of the 970 units on this registration are recorded sold or booked. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Hillview Estate
  • TypePlotted
  • Location
    • MDR 20
    • Golewadi
    • Khanav
    • Khalapur
    • Raigarh
    • 410203
  • Pincode410203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000055348
  • ReraGenie IDRG-MH-17800

Builder

  • NameGodrej Projects Development Limited
  • Entity typeCompany
  • Associate Vice President Region Head MMR TwoPriyamvada Navet
  • Other registrations5 more →
  • Completed5 of 6
  • Declared earlier projects16 →

Key dates

this monthRegisteredMar 2024PromisedMar 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Mar 2024
  • Promised completion31 Mar 2027
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed60 files

Current status

61%592 of 970 units booked

Figures as on 19 Jun 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes60%
Street LightingYes95%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes75%
Solid Waste Management And DisposalYes40%
Water conservation /Rain water harvestingYes55%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes40%
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area332,560 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Oct 2024

Approvals and building plan

Permissible FSI300937.67

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAxis Bank, Jeevan Prakash Building, Ground Floor, Sir Pirozshah Mehta Road, Fort, Mumbai, Maharashtr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR Design Architects
EngineerVINYASA CONSULTANTS
EngineerRajendra V Joshi
Chartered AccountantAKPJ & Associates Chartered Accountant
PartnerRole in project
Godrej Projects Development Limited-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12501291Jyoti SinghalGodrej Projects Development Limited18/04/2025
CC12501921Dharminder SalwanAbhijit S Mohite12/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Jul 2025

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Godrej Hillview Estate.pdf19 Jun 2026
Form 5 (FY 2024-2025)File: freecompress-Imagica Final Deliverable Signed.pdf30 Sep 2025
Completion CertificateFile: Completion certificate.pdf2 Jul 2025
Form 2A (FY 2024-2025)File: Hillview Estate _ Quality Assurance Certificate FY 25.pdf18 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 310225.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certificate Hillview March -25.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ HILLVIEW ESTATE_CERTIFICATE 31STMAR'25.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD - BOOKED INVENTORY - GHV.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certificate Hillview Dec 24.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Dec 24_compressed.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ HILLVIEW ESTATE_CERTIFICATE DEC'24.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold_Oct.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold_Oct.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Certificate Imagica Oct 2024.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_20241011_0001_compressed (1).pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ HILLVIEW ESTATE_CERTIFICATE SEPT'24 - Final.pdf17 Oct 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Imagica plotted.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Godrej Hillview Estate Form 5 FY 2023 24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Certificate Imagica.pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ HILLVIEW ESTATE_CERTIFICATE JUN'24 - Final.pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ HILLVIEW ESTATE_CERTIFICATE JUN'24 - Final.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE-compressed (1).pdf16 Jul 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Imagica plotted.pdf16 Jul 2024
Proforma of Agreement for saleFile: Godrej Hillview Estate - AFS.pdf10 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A -FY 2024- Plot Imagica 15-04-24.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certificate Imagica HIllview march 2024- Architect Certificate Revised.pdf15 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GODREJ HILLVIEW ESTATE_CERTIFICATE MAR'24 - Final.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold unsold.pdf15 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_compressed-compressed.pdf15 Apr 2024
Copy of the legal title reportFile: Legal Title Report_001 PrintPDF.pdf12 Mar 2024
Details of encumbrances concerned to FinanceFile: 3 Details of Encumbrance Financial Encumbrance Certificate 12032024.pdf12 Mar 2024
Details of encumbrances concerned to FinanceFile: Details of Encumbrance Legal Encumbrance Certificate 12032024.pdf12 Mar 2024
Details of encumbrances concerned to LegalFile: 3 Details of Encumbrance Financial Encumbrance Certificate 12032024.pdf12 Mar 2024
Details of encumbrances concerned to LegalFile: Details of Encumbrance Legal Encumbrance Certificate 12032024.pdf12 Mar 2024
CERSAI detailsFile: 8 Cersai Declaration 12032024.pdf12 Mar 2024
Proforma of Agreement for saleFile: 1 Proforma Agreement for sale 12032024.pdf12 Mar 2024
Deviation Report with respect to model copy of AgreementFile: 1a Deviation Report AFS 12032024.pdf12 Mar 2024
Building plan approval or NA orderFile: NA Order.pdf7 Mar 2024
Layout approvalFile: Layout Highlighted R1.pdf7 Mar 2024
PAN CardFile: GPDL PAN Card.pdf7 Mar 2024
Copy of Layout Approval (in case of layout)File: Layout Highlighted R1.pdf7 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf7 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf7 Mar 2024
Declaration about Commencement CertificateFile: Commencement Certificate Declaration.pdf7 Mar 2024
Declaration in FORM BFile: Form B.pdf7 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf7 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf7 Mar 2024
Proforma of Allotment letterFile: 2 Proforma Allotment Letter- 07032024.pdf7 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account Declaration.pdf7 Mar 2024
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment Letter.pdf7 Mar 2024
Other - LegalFile: 08- EXT_Liasoning_Imagica DSC signed.pdf7 Mar 2024
Other - LegalFile: Index 2 (conveyance 1099)_compressed.pdf7 Mar 2024
Other - LegalFile: Index 2 (1101).pdf7 Mar 2024
Other - LegalFile: Annexure A Order 50.pdf7 Mar 2024
Other - FinanceFile: 08- EXT_Liasoning_Imagica DSC signed.pdf7 Mar 2024
Other - FinanceFile: Annexure A Order 50.pdf7 Mar 2024
Other - TechnicalFile: 08- EXT_Liasoning_Imagica DSC signed.pdf7 Mar 2024
Other - TechnicalFile: Annexure A Order 50.pdf7 Mar 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Godrej Country EstateMHASROLI KURNZE ROAD VILLAGE KURNZE TALUKA VIKRAMGAD DISTRICT PALGHAR-OngoingApr 2026Apr 2026
Godrej RKSSion Trombay Rd Dreamland Society Borla Union Park Chembur Mumbai Maharashtra 400071147CompletedDec 2024Mar 2023

How this compares with Raigarh

61%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Hillview Estate on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Golewadi5,900+ in Raigarh

2 kmGodrej Hillview EstateOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: Godrej Projects Development Limited

Godrej Projects Development Limited has 6 registrations on MahaRERA, including Godrej RKS and GODREJ COUNTRY ESTATE. Its filings disclose 16 earlier MahaRERA projects: declares 10 of 16 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Godrej Hillview Estate is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Hillview Estate?

The registered promoter entity is Godrej Projects Development Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Hillview Estate?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Hillview Estate?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Hillview Estate?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Hillview Estate?

The professionals named in the filing: Architect: R Design Architects; Engineer: VINYASA CONSULTANTS; Engineer: Rajendra V Joshi; Chartered Accountant: AKPJ & Associates Chartered Accountant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Hillview Estate?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Hillview Estate. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Hillview Estate to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.