VRUNDAVAN RESIDENCY

By M/s. AAVISHKAR BUILDERS

RG-MH-33654 · RERA P49800017493 · Last updated on MahaRERA portal: 29 Mar 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 31 months past the filed date
  • Completion date moved by 38 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dhule registration emailed to you, free during the pilot beta.
Mar 2024Possession promised31 months past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 50 documents Report an error

VRUNDAVAN RESIDENCY is a Residential / Group Housing project by M/s. AAVISHKAR BUILDERS in Dhule, Maharashtra, registered with MahaRERA as P49800017493 on 23 Aug 2018. Possession was promised by 31 Mar 2024 and is now 31 months past that date. The completion date has moved by 38 months from the original filing.

At a glance

Project

  • NameVRUNDAVAN RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • SHRI SANT SENA CO OPERATIVE HOUSING SOCIETY LTD
    • DEOPUR DHULE
    • Dhule (M Corp.)
    • Dhule
    • 424002
  • Pincode424002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49800017493
  • ReraGenie IDRG-MH-33654

Builder

  • NameM/s. AAVISHKAR BUILDERS
  • Entity typePartnership
  • Declared earlier projects6 →

Key dates

31 months past promisethis monthRegisteredAug 2018First promiseJan 2021Revised toMar 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Aug 2018
  • Promised completion31 Mar 2024
  • Revised completionRevised to 31 Mar 2024 (originally 31 Jan 2021)
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VRUNDAVAN RESIDENCYNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

VRUNDAVAN RESIDENCY: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area520 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/s AAVISHKAR BUILDERSDhule (M Corp.)Dhule

Approvals and building plan

Permissible FSI936.81
Proposed, not sanctioned689 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUPPER GROUND FLOOR SHOP NO 6,7,9,10,11 ABASAHEB R R PATIL VYAPARI SANKUL CTS NO 1618A PAROLA ROAD DH

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAMEER NANDAKUMAR AUSEKAR
EngineerRAJESH VARGANTWAR
PartnerRole in project
M/s. AAVISHKAR BUILDERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT49800011533Jan 2021 → Apr 2023

Reason as filed by the promoterMNC is taking long time to furnish us the occupancy certificate.

EXT49800009735Jan 2021 → Jul 2021

Reason as filed by the promoterDUE TO NON AVAILABILITY OF TDR FOUTH FLOOR GOT DELAYED.

EXT49800010545Jan 2021 → Oct 2021

Reason as filed by the promoterDHULE MNC is taking time to furnish us the OCCUPATION CERTIFICATE.

EXT49800015063Jan 2021 → Mar 2024

Reason as filed by the promoterproject is completed but completion certificate not received

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Aug 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed50

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 PDF.pdf29 Mar 2023
Status of ConveyanceFile: DEED OF CONVEYANCE PG 11 TO 20.pdf2 Aug 2021
Status of ConveyanceFile: DEED OF CONVEYANCE PG 1 TO 10-compressed.pdf31 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 (18-19).pdf29 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 (18-19).pdf29 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 (19-20).pdf29 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 (20-21).pdf29 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY CERTIFICATE JUNE'2019.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY CERTIFICATE SEP'2019.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY CERTIFICATE DEC'2019.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY CERTIFICATE MAR'2020.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY CERTIFICATE JUNE'2020.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY CERTIFICATE SEP'2020.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY CERTIFICATE DEC'2020.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY CERTIFICATE MAR'2021.pdf28 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation set 1.pdf27 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation set2.pdf27 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation set 3.pdf27 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: BHANDHKAM PARWANGI 2018-2019.pdf26 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: BHANDHKAM PARWANGI 2018-2019.pdf26 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: BHANDHKAM PARWANGI 2019-2020.pdf26 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: BHANDHKAM PARWANGI 2020-2021.pdf26 Jul 2021
Declaration about Commencement CertificateFile: DECLERATION COMMENCEMENT CERTIFICATE PDF.pdf26 Jul 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY PDF.pdf26 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Audit Report 2018-2019.pdf26 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: AUDIT REPORT 2019-2020.pdf26 Jul 2021
Certificates of CA (Form 5)File: VRUNDAVAN FORM 5 SEP 18.pdf18 Dec 2018
Building plan approvalFile: Sanctioned Plan Original.pdf9 Aug 2018
Layout approvalFile: LAYOUT PDF.pdf9 Aug 2018
PAN CardFile: AAVISHKAR BUILDERS' PAN CARD PDF.pdf9 Aug 2018
PAN CardFile: SSS PAN.pdf9 Aug 2018
PAN CardFile: KKS PAN.pdf9 Aug 2018
Copy of the legal title reportFile: Title Search Report 44 PART 1.pdf9 Aug 2018
Copy of the legal title reportFile: Title Search Report 44 PART 2.pdf9 Aug 2018
Copy of the legal title reportFile: Title Search Report 44 PART 3.pdf9 Aug 2018
Details of encumbrancesFile: No encumbrance certificate 44.pdf9 Aug 2018
Copy of Layout Approval (in case of layout)File: LAYOUT PDF.pdf9 Aug 2018
Building Plan Approval (IOD)File: Sanctioned Plan Original.pdf9 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: Buiding Permission.pdf9 Aug 2018
Declaration in FORM BFile: Form B declaration 44.pdf9 Aug 2018
Certificates of CA (Form 3)File: C A CERTIFICATE 1.pdf9 Aug 2018
Proforma of Allotment letterFile: AGREEMENT FOR SALE WITH ALLOTTMENT LETTER FINAL PDF.pdf9 Aug 2018
OtherFile: DEED OF CONVEYANCE FINAL PDF.pdf9 Aug 2018
OtherFile: PROJECT SPECIFICATIONS FINAL PDF.pdf9 Aug 2018
OtherFile: COMMON AMENITIES FINAL PDF.pdf9 Aug 2018
OtherFile: COMMON AREAS FINAL PDF.pdf9 Aug 2018
OtherFile: MAINTAINANCE ITEMS FINAL PDF.pdf9 Aug 2018
OtherFile: DISCLAIMER FINAL PDF.pdf9 Aug 2018
OtherFile: Acc Details 44.pdf9 Aug 2018
OtherFile: 7-12 EXTRACT PDF.pdf9 Aug 2018

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
RAMKRUSHNA TWIN BUNGALOWS PHASE IIWALWADI DEOPUR DHULE4CompletedApr 2017Mar 2017
DHUVTARA APARTMENTSDIVERSION ROAD DEOPUR DHULE9CompletedApr 2017Mar 2017
SAHEB APARTMENTSOSWAL NAGAR DEOPUR DHULE12CompletedDec 2016Late, Dec 2016
DWARKADHEESH APARTMENTSDATTA COLONY DEOPUR DHULE12CompletedDec 2015Late, Mar 2016
RAMKRUSHNA TWIN BUNGALOWS PHASE IWALWADI DEOPUR DHULE4CompletedOct 2014Late, Dec 2014
RADHAKRUSHNA APARTMENTSDATTA COLONY DEOPUR DHULE12CompletedApr 2012Feb 2012

How this compares with Dhule

21%of Dhule projects moved their completion datethis one moved by 38 months
30%of Dhule registrations have lapsed or been cancelledthis one is among them

Computed across the 71 Dhule projects on ReraGenie, from their own filings.

Keep VRUNDAVAN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DEOPUR DHULE71 in Dhule

2 kmVRUNDAVAN RESIDENCYCompleted 3Lapsed / revoked 4Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: M/s. AAVISHKAR BUILDERS

M/s. AAVISHKAR BUILDERS has 1 registration on MahaRERA, including VRUNDAVAN RESIDENCY. Its filings disclose 6 earlier MahaRERA projects: declares 3 of 6 past projects completed on time. Read the full track record. See more projects on the Dhule district page.

Frequently asked questions

What does it mean that VRUNDAVAN RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VRUNDAVAN RESIDENCY is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VRUNDAVAN RESIDENCY?

The registered promoter entity is M/s. AAVISHKAR BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VRUNDAVAN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VRUNDAVAN RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VRUNDAVAN RESIDENCY?

The professionals named in the filing: Architect: SAMEER NANDAKUMAR AUSEKAR; Engineer: RAJESH VARGANTWAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRUNDAVAN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRUNDAVAN RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRUNDAVAN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.