ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / VRUNDAVAN RESIDENCIES

Registered No litigation declared Residential / Group Housing project

VRUNDAVAN RESIDENCIES

By ANIL JANARDHAN SARODE

RG-MH-83622 · RERA P52100015902 · Last updated on MahaRERA portal: 18 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 101 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2029Possession promisedmoved 101 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 80%
17 of 35Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

VRUNDAVAN RESIDENCIES is a Residential / Group Housing project by ANIL JANARDHAN SARODE in Pune, Maharashtra, registered with MahaRERA as P52100015902 on 9 Apr 2018. Possession is promised by 28 Feb 2029. The completion date has moved by 101 months from the original filing. 18 of the 35 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameVRUNDAVAN RESIDENCIES
  • TypeResidential / Group Housing
  • Location
    • DEHUGAON ROAD
    • DEHUGAON
    • DEHU
    • Haveli
    • Pune
    • 412109
  • Pincode412109
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015902
  • ReraGenie IDRG-MH-83622

Builder

  • NameANIL JANARDHAN SARODE
  • Entity typeIndividual

Key dates

this monthRegisteredApr 2018First promiseSep 2020Revised toFeb 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Apr 2018
  • Promised completion28 Feb 2029
  • Revised completionRevised to 28 Feb 2029 (originally 30 Sep 2020)
  • Buildings1 building record
  • Documents filed80 files

Current status

51%18 of 35 units booked
61.4%Work done, per cost certificate

Figures as on 18 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VRUNDAVAN RESIDENCIESNA6435035

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.

VRUNDAVAN RESIDENCIES: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor80%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,950 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Mar 2026

Approvals and building plan

Sanctioning authorityTown Planning & Valuation Department Pune Branch.
Permissible FSI1462.56
Proposed, not sanctioned1,463 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMOHAMADWADI PUNE
Estimated costRs 3.62 cr
Cost incurredRs 2.23 cr
Work done61.38%
BuildingWingEstimatedIncurred
VRUNDAVAN RESIDENCIESNARs 3.62 crRs 2.23 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANIRUDDHA SHINDE
ArchitectSHINDE JOSHI ASSOCIATES
EngineerADITYA YENPURE
EngineerROHAN KARKARE & ASSOCIATE
EngineerShahid Shaikh
Chartered AccountantSUNSVG & ASSOCIATES
Chartered AccountantAGHAV WAVHAL & ASSOCIATES
PartnerRole in project
ANIL JANARDHAN SARODE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20042620667Sep 2020 → Feb 2029

Reason as filed by the promoterDue to the absence of flat sales, the project has been facing limited cash inflow, which has adversely affected its financial position and slowed down the planned progress of work. As a result of these constraints, the project has remained stalled since 2020. We are now taking necessary steps to regularize the financial position and recommence the project work. In order to revive the project and complete the pending construction activities, additional time is required. We therefore respectfully request that an extension be granted to enable us to restart and complete the project in a systemati

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Mar 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Mar 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 28 Feb 2029

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Q3.pdf18 May 2026
Form 2File: Form 2 Q3.pdf18 May 2026
Form 3File: Form 3 Q3 (2).pdf18 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Book Inventory Q3.pdf18 May 2026
Withdrawal Update Form 1File: Form 1.pdf18 May 2026
Withdrawal Update Form 1File: Form 1.pdf18 May 2026
Withdrawal Update Form 1File: Form 1.pdf18 May 2026
Withdrawal Update Form 1File: Form 1 Q3.pdf18 May 2026
Withdrawal Update Form 1File: Form 1 Q3.pdf18 May 2026
Withdrawal Update Form 2File: Form 2.pdf18 May 2026
Withdrawal Update Form 2File: Form 2.pdf18 May 2026
Withdrawal Update Form 2File: Form 2.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 Q3.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 Q3.pdf18 May 2026
Withdrawal Update Form 3File: Form 3 Q3 (2).pdf18 May 2026
Withdrawal Update Form 3File: Form 3 Q3 (2).pdf18 May 2026
Withdrawal Update Form 3File: Form 3 Q3 (2).pdf18 May 2026
Withdrawal Update Form 3File: Form 3 Q3 (2).pdf18 May 2026
Withdrawal Update Form 3File: Form 3 Q3 (2).pdf18 May 2026
Withdrawal Update Form 1File: Form 1 Q4 (2).pdf14 May 2026
Withdrawal Update Form 2File: Form 2 Q4 (2).pdf14 May 2026
Withdrawal Update Form 3File: Form 3 Q4.pdf14 May 2026
Form 2A (FY 2020-2021)File: Form 2A.pdf27 Mar 2026
Form 1File: Form 1.pdf18 Mar 2026
Form 2File: Form 2.pdf18 Mar 2026
Form 3File: Form - 3 - Vrundavan Residencies (2).pdf18 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf18 Mar 2026
Form 1File: Form 1.pdf18 Mar 2026
Form 2File: Form 2.pdf18 Mar 2026
Form 3File: Form - 3 - Vrundavan Residencies (2).pdf18 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf18 Mar 2026
Form 1File: Form 1.pdf18 Mar 2026
Form 2File: Form 2.pdf18 Mar 2026
Form 3File: Form - 3 - Vrundavan Residencies (2).pdf18 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf18 Mar 2026
Form 5 (FY 2020-2021)File: Form 5.pdf18 Mar 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 18-06-2018-1.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cettificate 31-12-2018-2.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 07-05-2019-3.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 26-06-2020-5.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 31-03-2019-6.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 31-03-2020-7.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cettificate 31-12-2021-8.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cettificate 31-03-2021-9.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cettificate 31-03-2022-10.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cettificate 30-06-2022-11.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 30-09-2022-12.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cettificate 31-12-2022-13.pdf14 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cettificate 31-03-2023-14.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 31-12-2018_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 04-04-2019_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 05-04-2020_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 10-04-2021_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 25-12-2021_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 31-03-2022_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 05-07-2022_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 21-06-2023_compressed.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 31-12-2022_compressed.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Engineer Cetificate 2018-19.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Engineer Cetificate 2019-20.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineer Cetificate 2020-21.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Engineer Certificate 2021-22.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineer Certificate 2022-23.pdf14 Jul 2023
Building plan approvalFile: PLAN-1.pdf15 Mar 2018
Building plan approvalFile: PLAN -2.pdf15 Mar 2018
Building plan approvalFile: PLAN-3.pdf15 Mar 2018
Layout approvalFile: LATOUT.pdf15 Mar 2018
PAN CardFile: PAN CARD.pdf15 Mar 2018
Copy of the legal title reportFile: TITLE SEARCH REPORT.pdf15 Mar 2018
Details of encumbrancesFile: FORM B.pdf15 Mar 2018
Copy of Layout Approval (in case of layout)File: LATOUT.pdf15 Mar 2018
Building Plan Approval (IOD)File: PLAN-1.pdf15 Mar 2018
Building Plan Approval (IOD)File: PLAN -2.pdf15 Mar 2018
Building Plan Approval (IOD)File: PLAN-3.pdf15 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER.pdf15 Mar 2018
Declaration in FORM BFile: FORM B.pdf15 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFACATES.pdf15 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERT.pdf15 Mar 2018
Certificates of CA (Form 3)File: CA CERTIFICATES.pdf15 Mar 2018
Proforma of Allotment letterFile: AGREEMENT COPY.pdf15 Mar 2018

How this compares with Pune

51%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 101 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VRUNDAVAN RESIDENCIES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DEHUGAON13,700+ in Pune

2 kmVRUNDAVAN RESIDENCIESCompleted 14Lapsed / revoked 8Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: ANIL JANARDHAN SARODE

ANIL JANARDHAN SARODE has 1 registration on MahaRERA, including VRUNDAVAN RESIDENCIES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VRUNDAVAN RESIDENCIES is delayed beyond 28 Feb 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VRUNDAVAN RESIDENCIES?

The registered promoter entity is ANIL JANARDHAN SARODE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VRUNDAVAN RESIDENCIES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VRUNDAVAN RESIDENCIES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VRUNDAVAN RESIDENCIES?

The professionals named in the filing: Architect: ANIRUDDHA SHINDE; Architect: SHINDE JOSHI ASSOCIATES; Engineer: ADITYA YENPURE; Engineer: ROHAN KARKARE & ASSOCIATE; Engineer: Shahid Shaikh; Chartered Accountant: SUNSVG & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRUNDAVAN RESIDENCIES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRUNDAVAN RESIDENCIES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRUNDAVAN RESIDENCIES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.