Home / Browse projects / Pune, Maharashtra / Vrindavan Wing A

Completed No litigation declared Residential / Group Housing project

Vrindavan Wing A

By CHANDRASHEKHAR BALIRAM NAGPURE

RG-MH-58720 · RERA P52100016682 · Last updated on MahaRERA portal: 5 Jul 2023

Source: official MahaRERA filing

Red flags

  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 33 documents Report an error

Vrindavan Wing A is a Residential / Group Housing project by CHANDRASHEKHAR BALIRAM NAGPURE in Pune, Maharashtra, registered with MahaRERA as P52100016682 on 5 Jun 2018. The registration is recorded completed; possession was promised by 31 Dec 2019.

At a glance

Project

  • NameVrindavan Wing A
  • TypeResidential / Group Housing
  • Location
    • Rahatni
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411017
  • Pincode411017
  • RERA no.P52100016682
  • ReraGenie IDRG-MH-58720

Builder

  • NameCHANDRASHEKHAR BALIRAM NAGPURE
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredJun 2018PromisedDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Jun 2018
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed33 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vrindavan Wing ANA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Vrindavan Wing A: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area720 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI199.23
Proposed, not sanctioned199 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1259 JM road, deccan gymkhana Pune

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Shivaji Dange
PartnerRole in project
CHANDRASHEKHAR BALIRAM NAGPURE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100010589Dec 2019 → Jan 2022

Reason as filed by the promoterDue to covid situation and random lockdown Pimpari Chinchwad Municipal corporation is unable to provide us the Firm Demarcation which is require to submit Final Completion certificate. Our project is completed in all respect. All the internal & external works of building are completed. All the services like Water, electricity, drainage, solar, lift, backup, road, compound etc are completed. But without extension certificate we cant take any booking and we need it as we already paid excess cost to construction due to prolonged period and also paying higher interests to banks on loans. We sincer

EXT52100006034Dec 2019 → Mar 2021

Reason as filed by the promoterDear Sir/Madam, We have got the sanction & commencement from Pimpari Chinchwad Municipal Corporation for the said work 0n 06/03/2017 vide Letter No B.P./Rahatni/17/2017 and completed the plinth work within 4 months and applied for Plinth NOC from PCMC. But PCMC lost our application file and it's still missing so we cant get Plinth Certificate from them. Due to this problem we cant even apply for Lift Sanction also. Architect is saying that he is in continuous followup with PCMC officials but we will not get the letter from PCMC for atleast 3 months more as they are too busy in application of n

EXT52100016560Dec 2019 → Nov 2023

Reason as filed by the promoterDear Sir/Madam, We have completed our entire project work very long ago in Feb 2021 and applied to PCMC for completion certificate but unfortunately they lost our file along which was having all original documents. And it was not only our file which was lost but along with many others. We are desperately taking followup with architect to get that certificate since then. Our customers are well aware about this situation and they are agree to extend the project period. Once we get the certificate, we will form the society and hand over the premises to customers immediately. We really don't want

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Jul 2023

Documents filed33

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Vrindavan Wing A.pdf5 Jul 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Vrindavan Wing A.pdf5 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect.pdf9 May 2023
Certificates of CA (Form 3)File: Swami Vrindavan Rera Form 3.pdf9 May 2023
Annual Audit Report of Statutory CA (Form 5)File: Form 5 - Vrindavan - Swami Const 21-22.pdf9 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Vrindavan - Swami Const 21-22.pdf9 May 2023
Declaration about Commencement CertificateFile: Declaration for Commenement Certificate.pdf4 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf4 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf4 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf4 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf4 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21.pdf4 Aug 2021
OtherFile: Work Stage letter by Architect.pdf4 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Vrindavan Wing A Form 5 1.pdf18 Dec 2019
Annual Audit Report of Statutory CA (Form 5)File: Vrindavan Wing A Form 5 1.pdf30 Sep 2019
Building plan approvalFile: Sanctioned Plan 1.pdf15 May 2018
Building plan approvalFile: Sanctioned Plan 2.pdf15 May 2018
Building plan approvalFile: Sanctioned Plan 3.pdf15 May 2018
Layout approvalFile: Sanctioned Plan 1.pdf15 May 2018
Copy of the legal title reportFile: Title Opinion.pdf15 May 2018
Copy of Layout Approval (in case of layout)File: Sanctioned Plan 1.pdf15 May 2018
Building Plan Approval (IOD)File: Sanctioned Plan 1.pdf15 May 2018
Building Plan Approval (IOD)File: Sanctioned Plan 2.pdf15 May 2018
Building Plan Approval (IOD)File: Sanctioned Plan 3.pdf15 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf15 May 2018
Certificates of CA (Form 3)File: CA Certificate Form3.pdf15 May 2018
Proforma of Allotment letterFile: Agreement and Allotment Letter Format.pdf15 May 2018
OtherFile: MOU2.pdf15 May 2018
PAN CardFile: Nagpure Pan.pdf14 May 2018
Details of encumbrancesFile: Encumb Certificate.pdf14 May 2018
Declaration in FORM BFile: Form B 2.pdf14 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Architect.pdf14 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 Engineers Certificate.pdf14 May 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vrindavan Wing A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rahatni13,700+ in Pune

Builder: CHANDRASHEKHAR BALIRAM NAGPURE

CHANDRASHEKHAR BALIRAM NAGPURE has 2 registrations on MahaRERA, including SWAMI ANGAN and Vrindavan Wing A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Vrindavan Wing A is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vrindavan Wing A?

The registered promoter entity is CHANDRASHEKHAR BALIRAM NAGPURE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vrindavan Wing A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vrindavan Wing A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vrindavan Wing A?

The professionals named in the filing: Architect: Sandeep Shivaji Dange. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vrindavan Wing A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vrindavan Wing A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vrindavan Wing A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.