Home / Browse projects / Pune, Maharashtra / Tamara

Registered No litigation declared Residential / Group Housing project

Tamara

By Goldfinger Kataria Urban Developments

RG-MH-24497 · RERA P52100013230 · Last updated on MahaRERA portal: 3 Sep 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 112 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 112 months from the original
36 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 90%
166 of 396Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 207 documents Report an error

Tamara is a Residential / Group Housing project by Goldfinger Kataria Urban Developments in Pune, Maharashtra, registered with MahaRERA as P52100013230 on 21 Sep 2017. Possession is promised by 30 Apr 2027. The completion date has moved by 112 months from the original filing. 230 of the 396 units on this registration are recorded sold or booked, and 36 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTamara
  • TypeResidential / Group Housing
  • Location
    • Pimple Saudhagar
    • Pimpale Saudhagar
    • Rahatani
    • Haveli
    • Pune
    • 411017
  • Pincode411017
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100013230
  • ReraGenie IDRG-MH-24497

Builder

  • NameGoldfinger Kataria Urban Developments
  • Entity typePartnership
  • PartnerKumar Chainarai Kataria

Key dates

this monthRegisteredSep 2017First promiseDec 2017Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Sep 2017
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2017)
  • Buildings5 building records
  • Documents filed207 files

Current status

58%230 of 396 units booked
56.0%Work done, per cost certificate

Figures as on 3 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A buildingNA131143043
B BuildingNA131143043
C BuildingNA131143043
Wing D UpriseNA22191341135
Wing E UpriseNA222010923132

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 3 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

36 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 90%.

A building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C Building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing D Uprise51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor0%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing E Uprise42%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)50%
Plinth90%
Stilt Floor0%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed918

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots918
Closed/Covered914
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
A building1044108
B Building1080108
C Building1090109
Wing D Uprise2300230
Wing E Uprise3630363

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,700 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Sep 2025
LandownerVillageDistrict
Viraj Constructions through its partner Janta Harilal KatariaPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI44585.94
Proposed, not sanctioned44,584 sq m
Buildings approved6
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPimpri Chinchwad
Estimated costRs 144.62 cr
Cost incurredRs 81.03 cr
Work done56.03%
BuildingWingEstimatedIncurred
Wing D UpriseNARs 79.23 crRs 49.76 cr
Wing E UpriseNARs 63.74 crRs 31.27 cr
-NARs 1.65 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjvee Bhosale
EngineerG A Bhilare Consultants Private Limited
EngineerRanjeet Kadam
Chartered AccountantN L Bhakare & Associates
Chartered AccountantSagar B Shelvane
PartnerRole in project
Goldfinger Kataria Urban Developments-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002423Dec 2017 → Dec 2020

Reason as filed by the promoter"It was pleasure to complete the project 5 months before the date of completing the project announced in RERA. The date of completing the Project was given as 31.12.17 & we have received Completion Certificate from PCMC on 31.7.17. Completion from PCMC is pending for 6 flats sold, due to change in balcony location & the extension for the same is required for that purpose only. The Environment Clearance of the Project is also pending with the authorities from quite long time. Firm has proposal to construct 2 Residential & 1 Commercial building in the same project, which will be undertaken after

EXT52100013846Dec 2017 → Dec 2026

Reason as filed by the promoterDue to Covid 19 and Revise sanction as per new UDCPR Rule.

EA10082622084Dec 2017 → Apr 2027

Reason as filed by the promoterRespected Sir/Madam, We, the promoters of the project TAMARA, registered under Registration No. P52100013230, humbly submit this application seeking extension of project registration. The registration is presently valid till 30/12/2026, and we request the Authority to kindly extend the validity till 30/04/2027 to enable completion of the balance work and procurement of the Occupation Certificate. I. Grounds for Extension The project timeline was materially impacted by circumstances beyond our control: Asia-wide War & RMC Shortage - Severe disruption in supply of Ready-Mix Concrete (RMC) delaye

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12504065Sujit Shankar BhosaleGoldfinger Kataria Urban Developments18/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed207

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 207 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A.pdf3 Sep 2026
Form 5 (FY 2024-2025)File: Form 5.pdf3 Sep 2026
Form 2A (FY 2025-2026)File: FORM-2A.pdf10 Aug 2026
Withdrawal Update Form 1File: Q 1 Form 1.pdf7 Aug 2026
Withdrawal Update Form 2File: Q 1 Form 2.pdf7 Aug 2026
Withdrawal Update Form 3File: Q 1 form 3.pdf7 Aug 2026
Building plan approvalFile: Highlighted Layout.pdf3 Jul 2026
Layout approvalFile: Highlighted Layout.pdf22 May 2026
Layout approvalFile: Layout.pdf4 May 2026
Building plan approvalFile: D And E wing podium floor.pdf4 May 2026
Building plan approvalFile: D and E wing first floor.pdf4 May 2026
Building plan approvalFile: D wing typical E wing second floor.pdf4 May 2026
Building plan approvalFile: E wing typical floor.pdf4 May 2026
Building plan approvalFile: D And E wing refuge floor.pdf4 May 2026
Building plan approvalFile: D And E wing 18th floor.pdf4 May 2026
Building plan approvalFile: D And E wing recreational floor.pdf4 May 2026
Building plan approvalFile: D And E wing terrace floor.pdf4 May 2026
Building plan approvalFile: E wing section and elevation.pdf4 May 2026
Building plan approvalFile: D wing section and elevation.pdf4 May 2026
Building plan approvalFile: D And E wing basement and ground parking.pdf4 May 2026
Building plan approvalFile: club house.pdf4 May 2026
Withdrawal Update Form 1File: Q4 form 1.pdf2 May 2026
Withdrawal Update Form 2File: Q 4 form 2.pdf2 May 2026
Withdrawal Update Form 3File: q 4 form 3.pdf2 May 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Form 2 _Tarmara QPR 2025 Q1.pdf16 Mar 2026
Form 3File: TAMARA JAN TO MAR 2025 FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Form 2 _Tarmara QPR 2025 Q1.pdf16 Mar 2026
Form 3File: TAMARA OCT DEC 2024 QPR FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Form 2 _Tarmara QPR 2025 Q1.pdf16 Mar 2026
Form 3File: TAMARA OCT DEC 2024 QPR FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Tamara QPR _Q1 _ Form 1 _2025.pdf16 Mar 2026
Form 3File: TAMARA OCT DEC 2024 QPR FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Form 2 _Tarmara QPR 2025 Q1.pdf16 Mar 2026
Form 3File: TAMARA OCT DEC 2024 QPR FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Tamara QPR _Q1 _ Form 1 _2025.pdf16 Mar 2026
Form 3File: TAMARA OCT DEC 2024 QPR FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Tamara QPR _Q1 _ Form 1 _2025.pdf16 Mar 2026
Form 3File: TAMARA OCT DEC 2024 QPR FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Form 1File: TAMARA LETTER FORM 1 P QPR 2024.pdf16 Mar 2026
Form 2File: Tamara QPR _Q1 _ Form 1 _2025.pdf16 Mar 2026
Form 3File: TAMARA OCT DEC 2024 QPR FORM 3.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Building Wise TAMARA.pdf16 Mar 2026
Withdrawal Update Form 1File: TAMARA LETTER.pdf15 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate oct-dec25 (1).pdf15 Mar 2026
Withdrawal Update Form 3File: Form 3-Oct-Dec-2025-Tamara _compressed.pdf15 Mar 2026
Withdrawal Update Form 1File: TAMARA LETTER _QPR 2 _ Spet 2025.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 _Tarmara QPR 2025 Q2.pdf12 Mar 2026
Withdrawal Update Form 3File: Form 3 -july -sept 2025 -tamara.pdf12 Mar 2026
Withdrawal Update Form 1File: Tamara QPR _Q1 _ Form 1 _2025.pdf10 Mar 2026
Withdrawal Update Form 2File: Form 2 _Tarmara QPR 2025 Q1.pdf10 Mar 2026
Withdrawal Update Form 3File: Tamara form 3.pdf10 Mar 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate April to June 2024.pdf21 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate July to Sep 2024.pdf21 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Oct to Dec2024.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jan-March 2024.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apr-June2024 Engineer Certificate_compressed.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate July to Sep 24.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate Oct to Dec 2024.pdf21 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- jan-Mar 2019.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- Apr-Jun 2019.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- Jul-Sep 2019.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- Oct-Dec 2019.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- Jan-Mar2020.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- Apr-Jun 2020.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- Jul-Sep 2020.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng- Oct-Dec 2020.pdf9 Nov 2024

How this compares with Pune

58%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 112 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Tamara on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpale Saudhagar13,700+ in Pune

2 kmTamaraCompleted 85Lapsed / revoked 46Other 53Dot size: filed unitsN

Filed coordinates, straight-line distance. 184 registered projects within 2 km.

Builder: Goldfinger Kataria Urban Developments

Goldfinger Kataria Urban Developments has 1 registration on MahaRERA, including Tamara. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Tamara is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Tamara?

The registered promoter entity is Goldfinger Kataria Urban Developments, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Tamara?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Tamara?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Tamara?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Tamara?

The professionals named in the filing: Architect: Sanjvee Bhosale; Engineer: G A Bhilare Consultants Private Limited; Engineer: Ranjeet Kadam; Chartered Accountant: N L Bhakare & Associates; Chartered Accountant: Sagar B Shelvane. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tamara?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tamara. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tamara to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.