Home / Browse projects / Nagpur, Maharashtra / Vrindavan Phase 1

Registered No litigation declared Others project

Vrindavan Phase 1

By Radha Madhav Developers

RG-MH-00685 · RERA P50500002672 · Last updated on MahaRERA portal: 17 Apr 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
870 of 1221Construction stages doneacross 111 buildings; furthest along: Internal walls, 96%
4Complaints at MahaRERAon this registration
Jump to the 194 documents Report an error

Vrindavan Phase 1 is a Others project by Radha Madhav Developers in Nagpur, Maharashtra, registered with MahaRERA as P50500002672 on 2 Aug 2017. Possession is promised by 30 Dec 2028. 4 complaints are on record with the regulator.

At a glance

Project

  • NameVrindavan Phase 1
  • TypeOthers
  • Location
    • Vrindavan Marg
    • Vrindavan
    • Jamtha
    • Nagpur (Rural)
    • Nagpur
    • 441122
  • Pincode441122
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500002672
  • ReraGenie IDRG-MH-00685

Builder

  • NameRadha Madhav Developers
  • Entity typePartnership
  • PartnerSanjay Gaurishankar Agrawal
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredAug 2017PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Aug 2017
  • Promised completion30 Dec 2028
  • Revised completionNone
  • Buildings111 building records
  • Documents filed194 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Devaki B1NA11000
Devaki B2 TBNA11000
Devaki B2 RHNA11000
Devaki B3 A1NA65000
Devaki B3 A2NA11000
Devaki B3 B1NA65000
Devaki B3 B2NA55000
Devaki B3 C1NA55000
Devaki B3 C2NA55000
Devaki B3 D1NA55000
Devaki B3 D2NA55000
Devaki B3 E1NA55000
Devaki B3 E2NA55000
Devaki B3 F1NA55000
Devaki B3 F2NA11000
Vasudev B1NA333000
Vasudev B2NA522000
Vasudev B3NA522000
Vasudev B4-B5NA22000
Vasudev B6 A1NA55000
Vasudev B6 A2NA44000
Vasudev B6 B1NA55000
Vasudev B6 B2NA44000
Vasudev B7 - 1NA44000
Vasudev B7 - 2NA44000
Vasudev B8 ANA98000
Vasudev B8 BNA98000
Vasudev B9NA98000
Vasudev B10NA98000
Vasudev B11NA98000
Vasudev B12NA22000
Vasudev B13NA22000
Rukmani B1NA522000
Rukmani B2NA542000
Rukmani B3NA202000
Rukmani B4NA282000
Rukmani B5NA62000
Rukmani B6NA62000
Rukmani B7NA62000
Rukmani B8NA62000
Rukmani B9NA33000
Rukmani B10NA33000
Rukmani B11NA33000
Rukmani B12NA33000
Rukmani B13NA33000
Rukmani B14 A1NA54000
Rukmani B14 A2NA55000
Rukmani B14 B1NA54000
Rukmani B14 B2NA55000
Rukmani B14 C1NA54000
Rukmani B14 C2NA55000
Rukmani B14 D1NA54000
Rukmani B14 D2NA55000
Rukmani B15 A1NA54000
Rukmani B15 A2NA55000
Rukmani B15 B1NA54000
Rukmani B15 B2NA55000
Rukmani B15 C1NA54000
Rukmani B15 C2NA55000
Rukmani B15 D1NA54000
Rukmani B15 D2NA55000
Sudama B1NA11000
Sudama B2NA11000
Sudama B3NA11000
Sudama B4NA11000
Sudama B5NA11000
Sudama B6NA11000
Sudama B7NA11000
Sudama B8 A1NA44000
Sudama B8 A2NA44000
Sudama B8 B1NA44000
Sudama B8 B2NA44000
Sudama B9 A1NA44000
Sudama B9 A2NA44000
Sudama B9 B1NA44000
Sudama B9 B2NA44000
Sudama B9 C1NA44000
Sudama B9 C2NA44000
Sudama B10NA98000
Yashoda B1NA102000
Yashoda B2NA202000
Yashoda B3NA262000
Yashoda B4NA362000
Yashoda B5NA242000
Yashoda B6NA242000
Yashoda B7NA122000
Yashoda B8 A1NA55000
Yashoda B8 A2NA44000
Yashoda B8 B1NA55000
Yashoda B8 B2NA44000
Yashoda B8 C1NA55000
Yashoda B8 C2NA44000
Yashoda B8 D1NA55000
Yashoda B8 D2NA44000
Yashoda B8 E1NA55000
Yashoda B8 E2NA44000
Nand B1NA22000
Nand B2NA11000
Nand B3NA22000
Nand B4 A1NA44000
Nand B4 A2NA44000
Nand B4 B1NA44000
Nand B4 B2NA44000
Nand B4 C1NA44000
Nand B4 C2NA44000
Nand B4 D1NA44000
Nand B4 D2NA44000
Nand B4 E1NA44000
Nand B4 E2NA44000
Nand B4 F1NA44000
Nand B4 F2NA44000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 17 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 111 buildings; the table lists the first 20.

870 of 1221 construction stages are filed complete across 111 buildings. The stage furthest along is Internal walls, at 96%.

Devaki B182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B2 TB82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B2 RH82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 A191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 A264%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 B191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 B264%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 C191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 C291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 D191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 D291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 E191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 E291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 F191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Devaki B3 F291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Vasudev B191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Vasudev B291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Vasudev B391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Vasudev B4-B591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Vasudev B6 A190%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes65%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed7161

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots7,161
Closed/Covered3,139
Open Space4,022
BuildingClosed/CoveredOpen SpaceTotal
Devaki B3 A2233053
Devaki B3 B2233053
Devaki B3 C1283159
Devaki B3 C2273057
Devaki B3 D1283159
Devaki B3 D2273057
Devaki B3 E1283159
Devaki B3 E2273057
Devaki B3 F1343064
Devaki B3 F2293059
Vasudev B1312051
Vasudev B210446150
Vasudev B310447151
Vasudev B6 A17445119
Vasudev B6 A27245117
Vasudev B6 B1305585
Vasudev B6 B2305585
Vasudev B7 - 1164965
Vasudev B7 - 2164460
Vasudev B8 A524092
Vasudev B8 B534093
Vasudev B9323062
Vasudev B10323062
Vasudev B11323062
Vasudev B12257
Vasudev B13257
Rukmani B1253560
Rukmani B2273461
Rukmani B330434
Rukmani B436440
Rukmani B5121022
Rukmani B6121022
Rukmani B7121022
Rukmani B8121022
Rukmani B971017
Rukmani B1031013
Rukmani B1131013
Rukmani B1231013
Rukmani B1371017
Rukmani B14 A1711081
Rukmani B14 A2691079
Rukmani B14 B1711081
Rukmani B14 B2701080
Rukmani B14 C1711081
Rukmani B14 C2701080
Rukmani B14 D1711081
Rukmani B14 D2691079
Rukmani B15 A1711081
Rukmani B15 A2691079
Rukmani B15 B1711081
Rukmani B15 B2701080
Rukmani B15 C1711081
Rukmani B15 C2701080
Rukmani B15 D1711081
Rukmani B15 D2691079
Sudama B14103107
Sudama B24103107
Sudama B34103107
Sudama B449397
Sudama B54110114
Sudama B64103107
Sudama B74103107
Sudama B8 A1108494
Sudama B8 A297786
Sudama B8 B1108494
Sudama B8 B297786
Sudama B9 A1108494
Sudama B9 A297786
Sudama B9 B1108494
Sudama B9 B297786
Sudama B9 C1108494
Sudama B9 C297786
Sudama B1020161181
Yashoda B1261036
Yashoda B2531063
Yashoda B3351045
Yashoda B438947
Yashoda B528937
Yashoda B628937
Yashoda B712921
Yashoda B8 A1362056
Yashoda B8 A2362056
Yashoda B8 B1262248
Yashoda B8 B2252045
Yashoda B8 C1262248
Yashoda B8 C2252045
Yashoda B8 D1262248
Yashoda B8 D2252045
Yashoda B8 E1362056
Yashoda B8 E2362056
Nand B15051101
Nand B2286593
Nand B33694130
Nand B4 A186573
Nand B4 A284553
Nand B4 B186068
Nand B4 B284553
Nand B4 C186068
Nand B4 C284553
Nand B4 D186068
Nand B4 D284553
Nand B4 E186068
Nand B4 E284553
Nand B4 F186573
Nand B4 F284553

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area188,529 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNagpur Improvement Trust
Permissible FSI145090.46
Proposed, not sanctioned81,324 sq m
Buildings approved111
Buildings sanctioned111

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchG1 2 3 4 saraf court, opp yashwant stadium, dhantoli, nagpur 440012 maharashtra

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMs Sanghi Consulting Engineers
EngineerMs Sanghi Consulting Engineers
Chartered AccountantCA MUKUND SARDA
Chartered AccountantM A M P & CO
Chartered AccountantRAVINDRA
PartnerRole in project
Radha Madhav Developers-

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC004000000010042DEEPAK PRADYUMNA MOHTARAJESH N AGARWAL07/03/2018
CC004000000020107MANOJ NAMDEO SHENDERAJESH NAVRANGLALJI AGRAWAL & HARDIK RAJESH AGRAWAL22/07/2019
CC004000000030341Vinod Kumar AgarwalRajesh Navranglal Agrawal09/03/2022
CC004000000030512MUTHIAH RAVINDRANSHRI RAJESH AGRAWAL19/05/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2028

Documents filed194

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 194 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1_ MARCH 26_ VRINDAVAN PHASE 1.pdf17 Apr 2026
Form 2File: FORM 2_ MARCH 26_ VRINDAVAN PHASE 1.pdf17 Apr 2026
Form 3File: FORM 3_ MARCH 26_ VRINDAVAN PHASE 1.pdf17 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 26_ VRINDAVAN PHASE 1-1-26.pdf17 Apr 2026
Form 5 (FY 2024-2025)File: FORM 5_ MARCH 25_ RADHAMADHAV (1).pdf21 Jan 2026
Form 1File: FORM 1_ DEC 25_ VRINDAVAN PHASE I.pdf19 Jan 2026
Form 2File: FORM 2_ DEC 25_ VRINDAVAN PHASE I.pdf19 Jan 2026
Form 3File: FORM 3_ DEC 25_ VRINDAVAN PHASE I.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ DEC 25_ VRINDAVAN PHASE I_compressed (1).pdf19 Jan 2026
Form 2A (FY 2024-2025)File: FORM 2A_ 25.pdf19 Jan 2026
Form 1File: FORM 1_ SEP 25_ VRINDAVAN PHASE I.pdf17 Oct 2025
Form 2File: FORM 2_ SEP 25_ VRINDAVAN PHASE I.pdf17 Oct 2025
Form 3File: FORM 3_ SEP 25_ VRINDAVAN PHASE I.pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ SEP 25_ VRINDAVANPHASE 1.pdf17 Oct 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ 25.pdf22 Apr 2025
Certificates of CA (Form 3)File: FORM 3_ 25_11zon.pdf22 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_ 25.pdf22 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ 25.pdf22 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_ 25.pdf22 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A_ 25.pdf22 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_ 25.pdf22 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PHASE - 1 ARCHITECT CERTIFICATE.pdf20 Jan 2025
Certificates of CA (Form 3)File: PHASE 1 FORM 3.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PHASE -1 - ENGINEER CERTIFICATE - R1.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold-Phase-1.pdf20 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 FORM1_ SEP 24.pdf20 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 FORM 2_ SEP 24.pdf20 Oct 2024
Disclosure of sold/ booked inventoryFile: 4 SOLD UNSOLD_ SEP 24.pdf20 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1_Vrindavan Phase 1.pdf20 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2_Vrindavan Phase 1.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold-Phase-1_Vrindavan Phase 1.pdf20 Jul 2024
Certificates of CA (Form 3)File: FORM-3_Vrindavan Phase 1.pdf20 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold-Phase-1.pdf20 Apr 2024
Certificates of CA (Form 3)File: FORM-3.pdf20 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: efdsEDFSDF.pdf13 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_compressed.pdf12 Jan 2024
Certificates of CA (Form 3)File: FORM 3_compressed.pdf12 Jan 2024
Certificates of CA (Form 3)File: FORM 3 copy.pdf10 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT - A PHASE-1.PDF10 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-VRINDAVAN PHASE 1_SEP 23_compressed.pdf20 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-VRINDAVAN PHASE 1_SEP 23.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-VRINDAVAN PHASE 1_SEP 23.pdf20 Oct 2023
Certificates of CA (Form 3)File: FORM 3-VRINDAVAN PHASE 1_SEP 23.pdf20 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-VRINDAVAN 1_JUN 23_compressed.pdf20 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-VRINDAVAN 1_JUN 23.pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-VRINDAVAN 1_JUN 23.pdf20 Jul 2023
Certificates of CA (Form 3)File: FORM 3-VRINDAVAN 1_JUN 23.pdf20 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-VRINDAVAN PHASE 1_MAR 23_compressed.pdf22 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-VRINDAVAN PHASE 1_MAR 23.pdf22 Apr 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-VRINDAVAN PHASE 1_MAR 23.pdf22 Apr 2023
Certificates of CA (Form 3)File: FORM 3-VRINDAVAN PHASE 1_MAR 23.pdf22 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Phase-1.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Phase-1.pdf6 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold-Phase-1.pdf6 Feb 2023
Certificates of CA (Form 3)File: Form-3 Phase-1.pdf6 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 1.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 2.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 3.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 4.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 5.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 6-1-15.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 6-16-30.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 7.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 8.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 9.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 10.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 11.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 12.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 13.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 14.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 15.pdf12 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 16.pdf12 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ANNUAL REPORT VRINDAVANFORM 5.pdf9 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 PHASE-1.pdf16 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 PHASE -1.pdf16 Dec 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Phase-1.pdf16 Dec 2022

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vrindavan Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vrindavan2,800+ in Nagpur

2 kmVrindavan Phase 1Completed 25Lapsed / revoked 5Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 56 registered projects within 2 km.

Builder: Radha Madhav Developers

Radha Madhav Developers has 3 registrations on MahaRERA, including Gokul and Vrindavan Phase 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Vrindavan Phase 1 is delayed beyond 30 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vrindavan Phase 1?

The registered promoter entity is Radha Madhav Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vrindavan Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Vrindavan Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Vrindavan Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vrindavan Phase 1?

The professionals named in the filing: Architect: Ms Sanghi Consulting Engineers; Engineer: Ms Sanghi Consulting Engineers; Chartered Accountant: CA MUKUND SARDA; Chartered Accountant: M A M P & CO; Chartered Accountant: RAVINDRA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vrindavan Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vrindavan Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vrindavan Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.