VIVANTA
RG-MH-97225 · RERA P53100049872 · Last updated on MahaRERA portal: 22 Jan 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 4 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIVANTA is a Residential / Group Housing project by SA BUILDERS AND DEVELOPERS in Sangli, Maharashtra, registered with MahaRERA as P53100049872 on 6 Mar 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 4 months from the original filing. 11 of the 17 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameVIVANTA
- TypeResidential / Group Housing
- Location
- DADGAE HIGH SCHOOL
- NORTH SHIVAJINAGAR
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416416
- Pincode416416
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100049872
- ReraGenie IDRG-MH-97225
Builder
- NameSA BUILDERS AND DEVELOPERS
- Entity typePartnership
- Partnersagar dinkar chavan
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on6 Mar 2023
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Aug 2025)
- Buildings1 building record
- Documents filed86 files
Current status
Figures as on 22 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VIVANTA | NA | 7 | 6 | 17 | 0 | 17 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
VIVANTA: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 22 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| VIVANTA | NA | Rs 2.80 cr | Rs 2.55 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AMBER SHINDE |
| Engineer | SAMBHAJI salunkhe |
| Engineer | ONKAR UDYA SANMUKH |
| Chartered Accountant | sanket v chavan |
| Chartered Accountant | BPCH & COMPANY |
| Partner | Role in project |
|---|---|
| SA BUILDERS AND DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterthe work has been completed as per sanctioned plan. proposal submit to authority but delay by authority because of transfer of tp and adtp. submitted the proposal of this project to smkc sangli project alreday complted in the time of rera there is no need cpm/pert chart.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed86
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: FULL OCCUPANCY certificate_vivanta.pdf | 22 Jan 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 30-9-25.pdf | 30 Dec 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 30-9-25.pdf | 30 Dec 2025 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 30-9-25.pdf | 30 Dec 2025 |
| Occupational CertificateFile: FULL OCCUPANCY certificate_vivanta.pdf | 30 Dec 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1_upto 30062025 final.pdf | 18 Sep 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1_upto 30062025 final.pdf | 18 Sep 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1_upto 30062025 final.pdf | 18 Sep 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 _upto 30062025 final.pdf | 18 Sep 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 _upto 30062025 final.pdf | 18 Sep 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 _upto 30062025 final.pdf | 18 Sep 2025 |
| Withdrawal Update Form 3File: FORM-3 30062025_ 11-09-25.pdf | 18 Sep 2025 |
| Withdrawal Update Form 3File: FORM-3 30062025_ 11-09-25.pdf | 18 Sep 2025 |
| Withdrawal Update Form 3File: FORM-3 30062025_ 11-09-25.pdf | 18 Sep 2025 |
| Form 2A (FY 2024-2025)File: 2A 24-25.pdf | 18 Sep 2025 |
| Form 5 (FY 2024-2025)File: form 5 24-25.pdf | 18 Sep 2025 |
| Withdrawal Update Form 1File: Withdrawal Application Form1_upto 30062025 final.pdf | 11 Sep 2025 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 _upto 30062025 final.pdf | 11 Sep 2025 |
| Withdrawal Update Form 3File: FORM-3 30062025_ 11-09-25.pdf | 11 Sep 2025 |
| Form 1File: form 1 31-3-25.pdf | 30 Aug 2025 |
| Form 2File: form 2 31-3-25.pdf | 30 Aug 2025 |
| Form 3File: form 3 31-3-25.pdf | 30 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 31-3-25.pdf | 30 Aug 2025 |
| Withdrawal Update Form 1File: FORM 1 30-06-2025.pdf | 30 Aug 2025 |
| Withdrawal Update Form 2File: FORM 2 30 6 25.pdf | 30 Aug 2025 |
| Withdrawal Update Form 3File: FORM 3 30 6 25.pdf | 30 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 24-01-25.pdf | 30 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 24-01-23.pdf | 30 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 17-01-25.pdf | 30 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 14-01-25.pdf | 30 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 14-01-25.pdf | 30 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM -3 16-01-25.pdf | 30 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 24-01-25.pdf | 30 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 24-01-25.pdf | 30 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 17-01-25.pdf | 30 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD 30-06-24.pdf | 30 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD 30-09-24.pdf | 30 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD 31-12-24.pdf | 30 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2A 24-01-25.pdf | 30 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31 12 2023.pdf | 12 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 12 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 12 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 12 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf | 12 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf | 12 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 12 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 12 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 12 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf | 8 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate - 14102023.pdf | 8 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate 01042013.pdf | 8 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate - 14102023.pdf | 8 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 31-3-2023.pdf | 8 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 30-9-2023.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate - 14102023.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate 01042023 to 30062023.pdf | 8 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate 01072023 to 30092023.pdf | 8 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: annual report statement of account.pdf | 8 Nov 2023 |
| CERSAI detailsFile: CERSAI REPORT.pdf | 23 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTREST IN OTHER REAL ESTATE ORGANIZATION - SAGAR CHAVAN1_compressed.pdf | 23 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTREST IN OTHER REAL ESTATE ORGANAZATION abhijit_compressed.pdf | 23 Feb 2023 |
| Proforma of Allotment letterFile: allotment final.pdf | 23 Feb 2023 |
| Other - LegalFile: PLOT SALE DEED.pdf | 23 Feb 2023 |
| Layout approvalFile: nakasha.pdf | 22 Feb 2023 |
| Building plan approvalFile: mun dwg.pdf | 22 Feb 2023 |
| Layout approvalFile: amalgamation dwg.pdf | 22 Feb 2023 |
| PAN CardFile: companies pan card.pdf | 22 Feb 2023 |
| Copy of the legal title reportFile: search title inspection report.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: no encumbrance certificate - financial.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: no encumbrance certificate - legal.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to LegalFile: no encumbrance certificate - financial.pdf | 22 Feb 2023 |
| Details of encumbrances concerned to LegalFile: no encumbrance certificate - legal.pdf | 22 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: nakasha.pdf | 22 Feb 2023 |
| Copy of Layout Approval (in case of layout)File: amalgamation dwg.pdf | 22 Feb 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: mun dwg.pdf | 22 Feb 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: building permission certificate.pdf | 22 Feb 2023 |
| Declaration about Commencement CertificateFile: declaration about commencement certificate.pdf | 22 Feb 2023 |
| Declaration in FORM BFile: FORM B.pdf | 22 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf | 22 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 86 filed documents as one ZIP, foldered, with a manifest
Keep VIVANTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NORTH SHIVAJINAGAR790+ in Sangli
Filed coordinates, straight-line distance. 141 registered projects within 2 km.
SIDDHI VASTU Puram
SIDDHIVINAYAK PLATINUM
SEVEN HILLS
SHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP
EVARA ESTATE
DSDB REALTY LLP
VISION CITY
VISION GROUP
NAKSHTRA
SHIV-NAKSHTRA DEVELOPERS LLP
SAHYADRISIDDHI
SAHYADRIDEVELOPERS
See every Sangli project, with the district possession charts
Builder: SA BUILDERS AND DEVELOPERS
SA BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including VIVANTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What are my rights if VIVANTA is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIVANTA?
The registered promoter entity is SA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIVANTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VIVANTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIVANTA?
The professionals named in the filing: Architect: AMBER SHINDE; Engineer: SAMBHAJI salunkhe; Engineer: ONKAR UDYA SANMUKH; Chartered Accountant: sanket v chavan; Chartered Accountant: BPCH & COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIVANTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback