Home / Browse projects / Mumbai Suburban, Maharashtra / VIVANTA
VIVANTA
By KEYLAND DEVELOPERS PRIVATE LIMITED
RG-MH-06143 · RERA P51800052409 · Last updated on MahaRERA portal: 29 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 19 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIVANTA is a Others project by KEYLAND DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800052409 on 22 Aug 2023. Possession is promised by 31 Jul 2031. The completion date has moved by 19 months from the original filing. 0 of the 99 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.
At a glance
Project
- NameVIVANTA
- TypeOthers
- Location
- OF VILLAGE PAHADI
- GOREGAON (EAST)
- GOREGAON (EAST)
- Pahadi-Goregaon
- Borivali
- Mumbai Suburban
- 400063
- Pincode400063
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800052409
- ReraGenie IDRG-MH-06143
Builder
- NameKEYLAND DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- GSTIN27AADCK1746M2Z8
- DirectorsBHAVESH VIRJIBHAI PARMAR, JITESH VIRJIBHAI PARMAR, LALITKUMAR BABUBHAI KAVA, DILIP GOVINDBHAI CHITRODA
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Aug 2023
- Promised completion31 Jul 2031
- Revised completionRevised to 31 Jul 2031 (originally 31 Dec 2029)
- Buildings1 building record
- Documents filed88 files
Current status
Figures as on 29 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SALE BUILDING NO 2 | NA | 22 | 21 | 98 | 1 | 99 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
SALE BUILDING NO 2: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed70
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SALE BUILDING NO 2 | NA | Rs 45.00 cr | Rs 3.73 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VISHWAS SATODIA |
| Engineer | DINESH H MEHTA |
| Engineer | Dinesh Mehta |
| Chartered Accountant | NEHALI & CO |
| Chartered Accountant | NEHALI DOSHI |
| Chartered Accountant | Rajendra Karia |
| Partner | Role in project |
|---|---|
| KEYLAND DEVELOPERS PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterSubject: Submission of Technical Reasons for Delay in Completion of the Project: VIVANTA, Plot Bearing/CTS/Survey/Final Plot No.: 181, 181/1 TO 71 at Pahadi Goregaon, Borivali, Mumbai Suburban, 400063. Maha RERA Reg. No. P51800052409. Respected Sir, We, MR. Bhavesh Parmar / Keyland Developers Private Limited, are the promoters of the real estate project known as "VIVANTA" bearing Maha RERA Registration No. P51800052409 Reason for Delay of Project The project work has been delayed due to non-availability of road access to the project site. As per BMC policy and regulations, construction of a ro
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Aug 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Jun 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Jun 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Jul 2031
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Arch Cert of Rera June 2026.pdf | 29 Jul 2026 |
| Withdrawal Update Form 2File: Engineers certificate june 26.pdf | 29 Jul 2026 |
| Withdrawal Update Form 3File: Signed CA Certificate-Vivanta-June 26.pdf | 29 Jul 2026 |
| Layout approvalFile: p1.pdf | 23 Jun 2026 |
| Layout approvalFile: p2.pdf | 23 Jun 2026 |
| Withdrawal Update Form 1File: Arch Cert of Rera dtd 08 10 2025.pdf | 6 Jun 2026 |
| Withdrawal Update Form 1File: Architect Certificate dec25.pdf | 6 Jun 2026 |
| Withdrawal Update Form 1File: Architects Certificate march 26.pdf | 6 Jun 2026 |
| Withdrawal Update Form 2File: Engineers certificate sep 25.pdf | 6 Jun 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 6 Jun 2026 |
| Withdrawal Update Form 2File: Engineers certificate march 26.pdf | 6 Jun 2026 |
| Withdrawal Update Form 3File: Signed CA Certificate Vivanta Sept 25.pdf | 6 Jun 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 6 Jun 2026 |
| Withdrawal Update Form 3File: Signed CA Certificate-Vivanta-March 26.pdf | 6 Jun 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 5 Jun 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 5 Jun 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 5 Jun 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 5 Jun 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 5 Jun 2026 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf | 21 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf | 21 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certifi.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 12 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 30 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 10 23.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 12 23.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 03 24.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 06 24.pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 july 23 to sep 23 revised .pdf | 21 Oct 2024 |
| Form 2File: form 2 july 23 to sep 23.pdf | 25 Sep 2024 |
| Form 3File: form 3 july 23 to sep 23.pdf | 25 Sep 2024 |
| Form 1File: form 1 july 23 to sep 23.pdf | 25 Sep 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 20 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 20 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 20 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 19 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 19 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 19 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 19 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 16 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 16 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 16 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 16 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 16 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 16 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 16 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 16 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 16 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 16 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 16 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 16 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 6 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: NEW SIGNED FORM 5 23-24 VIVANTA.pdf | 6 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf | 5 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 5 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A.pdf | 5 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 1 Aug 2024 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf | 14 Aug 2023 |
| Details of encumbrances concerned to FinanceFile: No encumbrance self declaration vivanta.pdf | 14 Aug 2023 |
| Details of encumbrances concerned to LegalFile: No encumbrance self declaration vivanta.pdf | 14 Aug 2023 |
| Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf | 14 Aug 2023 |
| Copy of the legal title reportFile: TITLE REPORT.pdf | 2 Aug 2023 |
| Proforma of Agreement for saleFile: agreement for sale.pdf | 29 Jul 2023 |
| Declaration in FORM BFile: DocScanner 20 Jul 2023 16-50.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SIGNED_Signed CA Certificate-Vivanta.pdf | 20 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: VIVANTA DEVIATION AGREEMENT _1-11.pdf | 12 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: VIVANTA DEVIATION AGREEMENT _12-21.pdf | 12 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: VIVANTA DEVIATION AGREEMENT _22-end.pdf | 12 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE.pdf | 21 Jun 2023 |
| Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE.pdf | 21 Jun 2023 |
| Declaration about Commencement CertificateFile: CC DECLARATION.pdf | 21 Jun 2023 |
| CERSAI detailsFile: Cersai declaration vivanta.pdf | 21 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DOI.pdf | 21 Jun 2023 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER FINAL.pdf | 21 Jun 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Formate A vivanta (1).pdf | 21 Jun 2023 |
| Deviation Report with respect to Allotment letterFile: DEVIATION ALLOTMENT.pdf | 21 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VIVANTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GOREGAON (EAST)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 434 registered projects within 2 km.
Elysian Tower C, D, E
Oberoi Realty Limited
Elysian Tower B
Oberoi Realty Limited
Elysian Tower A
Oberoi Realty Limited
Sheetal Sangam
DGS Township Pvt Ltd
SEJAL SQUARE
ALCHEMI DEVELOPERS PRIVATE LIMITED
Mehta Marquina 1978
Shreeram Builders
See every Mumbai Suburban project, with the district possession charts
Builder: KEYLAND DEVELOPERS PRIVATE LIMITED
KEYLAND DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including VIVANTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if VIVANTA is delayed beyond 31 Jul 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIVANTA?
The registered promoter entity is KEYLAND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its GSTIN 27AADCK1746M2Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIVANTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VIVANTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIVANTA?
The professionals named in the filing: Architect: VISHWAS SATODIA; Engineer: DINESH H MEHTA; Engineer: Dinesh Mehta; Chartered Accountant: NEHALI & CO; Chartered Accountant: NEHALI DOSHI; Chartered Accountant: Rajendra Karia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIVANTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback