Home / Browse projects / Palghar, Maharashtra / VIVA SHELTER - I

Completed No litigation declared Others project

VIVA SHELTER - I

By CHETANA BUILDERS AND DEVELOPERS

RG-MH-24997 · RERA P99000012456 · Last updated on MahaRERA portal: 24 Jun 2021

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jan 2021Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 75%
1Complaints at MahaRERAon this registration
Jump to the 18 documents Report an error

VIVA SHELTER - I is a Others project by CHETANA BUILDERS AND DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000012456 on 1 Sep 2017. The registration is recorded completed; possession was promised by 30 Jan 2021. The completion date has moved by 18 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVIVA SHELTER - I
  • TypeOthers
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000012456
  • ReraGenie IDRG-MH-24997

Builder

  • NameCHETANA BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersVINOD BHOLANATH PATHAK, VIJAY RAMTIRTH PATHAK, ARUNKUMAR ASHOK PATHAK, SANTOSH MATAPRASAD TIWARI, PANNALAL RAMACHARYA MISHRA

Key dates

this monthRegisteredSep 2017First promiseJul 2019Revised toJan 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2017
  • Promised completion30 Jan 2021
  • Revised completionRevised to 30 Jan 2021 (originally 31 Jul 2019)
  • Buildings1 building record
  • Documents filed18 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GURUDUTT TOWERNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jun 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 75%.

GURUDUTT TOWER: 63% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 24 Jun 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes50%

Parking filed58

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots58
Closed/Covered22
Open Space36

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,466 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5150.24
Proposed, not sanctioned5,150 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSUMANT CHHAYA, PURANDREWADI, VIRAR EAST

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY S NARANG
PartnerRole in project
CHETANA BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000002092Jul 2019 → Jul 2020

Reason as filed by the promoterThe Reason for seeking extension in completion date is due to the fact that the revised MOEF clearance, MPCB, Consent to Operate is pending due to which Occupancy certificate in not Issue by VVCMC.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000100531Francis DmonteVIVA SHELTER AND CHETNA DEVLOPERS14/08/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Jun 2021

Documents filed18

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: architect certificate form 4.pdf24 Jun 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE.pdf22 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT CERTIFICATE.pdf22 Jun 2021
Certificates of CA (Form 5)File: CA LETTER FORM 5.pdf16 Jul 2019
Building plan approvalFile: bld plan 2.pdf28 Jul 2017
Layout approvalFile: layout plan.pdf28 Jul 2017
Building plan approvalFile: bld plan.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: layout plan.pdf28 Jul 2017
Building Plan Approval (IOD)File: bld plan.pdf28 Jul 2017
Building Plan Approval (IOD)File: bld plan 2.pdf28 Jul 2017
Declaration in FORM BFile: form b.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ENGINEER FORM 1.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf28 Jul 2017
Proforma of Allotment letterFile: AGREEMENT.pdf28 Jul 2017
PAN CardFile: PANCARD.pdf27 Jul 2017
Copy of the legal title reportFile: TITLE REPORT 1.pdf27 Jul 2017
Details of encumbrancesFile: ENCUMBRANCE LETTER.pdf27 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 18 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIVA SHELTER - I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmVIVA SHELTER - ICompleted 36Lapsed / revoked 21Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: CHETANA BUILDERS AND DEVELOPERS

CHETANA BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including VIVA SHELTER - I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if VIVA SHELTER - I is delayed beyond 30 Jan 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIVA SHELTER - I?

The registered promoter entity is CHETANA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIVA SHELTER - I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VIVA SHELTER - I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VIVA SHELTER - I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIVA SHELTER - I?

The professionals named in the filing: Architect: SANJAY S NARANG. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIVA SHELTER - I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIVA SHELTER - I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIVA SHELTER - I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.