Mayfair Virar Gardens Cluster-VI
RG-MH-48310 · RERA P99000046231 · Last updated on MahaRERA portal: 17 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Rs 100.00 crore secured on the land, in favour of ICICI BANK LIMITED
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mayfair Virar Gardens Cluster-VI is a Residential / Group Housing project by MAYFAIR HOUSING in Palghar, Maharashtra, registered with MahaRERA as P99000046231 on 20 Jun 2022. Possession is promised by 30 Jun 2028. 1,454 of the 1,504 units on this registration are recorded sold or booked, and 58 of 99 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameMayfair Virar Gardens Cluster-VI
- TypeResidential / Group Housing
- Location
- Virar Agashi Road
- Virar West
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401303
- Pincode401303
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000046231
- ReraGenie IDRG-MH-48310
Builder
- NameMAYFAIR HOUSING
- Entity typePartnership
- GSTIN27AAHFM7843A1ZC
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersANURADHA NAYAN SHAH, MAYFAIR HOUSING PRIVATE LIMITED, NAYAN ARVIND SHAH
- Other registrations6 more →
- Completed2 of 7
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on20 Jun 2022
- Promised completion30 Jun 2028
- Revised completionNone
- Buildings9 building records
- Documents filed151 files
Current status
Figures as on 17 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 34 | NA | 23 | 22 | 172 | 0 | 172 |
| Building No 35 | NA | 23 | 22 | 172 | 0 | 172 |
| Building No 36 | NA | 23 | 22 | 172 | 0 | 172 |
| Building No 37 | NA | 23 | 22 | 172 | 0 | 172 |
| Building No 38 | NA | 23 | 22 | 128 | 0 | 128 |
| Building No 39 | NA | 23 | 22 | 172 | 0 | 172 |
| Building No 40 | NA | 23 | 22 | 172 | 0 | 172 |
| Building No 41 | NA | 23 | 22 | 172 | 0 | 172 |
| Building No 42 | NA | 23 | 22 | 172 | 0 | 172 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 17 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
58 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Internal walls, at 95%.
Building No 3466%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Building No 3551%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 3682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 3782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 3850%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 3971%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Building No 4078%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Building No 4182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 4282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 85% |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 55% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 80% |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed78
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building No 34 | 6 | 6 |
| Building No 35 | 12 | 12 |
| Building No 36 | 6 | 6 |
| Building No 37 | 4 | 4 |
| Building No 38 | 6 | 6 |
| Building No 39 | 6 | 6 |
| Building No 40 | 6 | 6 |
| Building No 41 | 16 | 16 |
| Building No 42 | 16 | 16 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building No 34 | NA | Rs 25.49 cr | Rs 24.42 cr |
| Building No 36 | NA | Rs 25.49 cr | Rs 25.49 cr |
| Building No 37 | NA | Rs 25.49 cr | Rs 25.49 cr |
| Building No 39 | NA | Rs 25.49 cr | Rs 25.49 cr |
| Building No 40 | NA | Rs 25.49 cr | Rs 25.49 cr |
| Building No 41 | NA | Rs 25.49 cr | Rs 25.49 cr |
| Building No 42 | NA | Rs 25.49 cr | Rs 25.49 cr |
| Building No 35 | NA | Rs 23.29 cr | Rs 22.32 cr |
| Building No 38 | NA | Rs 18.31 cr | Rs 17.54 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JAI MISTRY |
| Engineer | SANJEEV Basavantappa TIGADI |
| Engineer | S S PATNE ASSOCIATES |
| Chartered Accountant | MEHERNOSH DARA DUMASIA |
| Chartered Accountant | HEMANT JAIN |
| Partner | Role in project |
|---|---|
| MAYFAIR HOUSING | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600767 | Suvarna Shivram Lot | MAYFAIR HOUSING | 10/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2028
Documents filed151
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A MVG Cluster VI.pdf | 17 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 MVG VI 31Mar26.pdf | 6 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 MVG VI 31Mar26.pdf | 6 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 MVG VI 31Mar26.pdf | 6 Jun 2026 |
| Withdrawal Update Form 1File: MVG VI Form 1 31Dec2025.pdf | 14 Feb 2026 |
| Withdrawal Update Form 2File: MVG VI Form 2 31Dec2025.pdf | 14 Feb 2026 |
| Withdrawal Update Form 3File: MVG VI Form 3 31Dec2025.pdf | 14 Feb 2026 |
| Withdrawal Update Form 1File: MVG VI Form 1 30Sep25.pdf | 22 Dec 2025 |
| Withdrawal Update Form 2File: MVG VI Form 2 30Sep25.pdf | 22 Dec 2025 |
| Withdrawal Update Form 3File: MVG VI Form 3 30Sep25.pdf | 22 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5 31Mar2025 MVG VI.pdf | 23 Sep 2025 |
| Form 5 (FY 2022-2023)File: MVG Cluster-VI Form 5 31Mar23.pdf | 22 Sep 2025 |
| Form 5 (FY 2023-2024)File: MVG Cluster VI Form 5 31Mar24.pdf | 22 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 30June25.pdf | 18 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 30June25.pdf | 18 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 30June25.pdf | 18 Sep 2025 |
| Form 1File: Form 1 31Mar25.pdf | 5 Sep 2025 |
| Form 2File: Form 2 31Mar25.pdf | 5 Sep 2025 |
| Form 3File: Form 3 31Mar25.pdf | 5 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory 31Mar25.pdf | 5 Sep 2025 |
| Form 2A (FY 2024-2025) | 30 Jun 2025 |
| Form 1File: Form 1 30June2024.pdf | 24 Jun 2025 |
| Form 2File: Form 2 30June2024.pdf | 24 Jun 2025 |
| Form 3File: Form 3 30June2024.pdf | 24 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory 30June2024.pdf | 24 Jun 2025 |
| Form 1File: Form 1 30Sept2024.pdf | 24 Jun 2025 |
| Form 2File: Form 2 30Sept2024.pdf | 24 Jun 2025 |
| Form 3File: Form 3 30Sept2024.pdf | 24 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory 30Sept2024.pdf | 24 Jun 2025 |
| Form 1File: Form 1 31Dec2024.pdf | 24 Jun 2025 |
| Form 2File: Form 2 31Dec2024.pdf | 24 Jun 2025 |
| Form 3File: Form 3 31Dec2024.pdf | 24 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory 31Dec2024.pdf | 24 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MVG VI 31Dec24.pdf | 6 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MVG VI 31Dec24.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MVG VI 31Dec24.pdf | 6 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory 31Dec24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 2 MVG VI.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 MVG Cluster VI 30Sep24.pdf | 17 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 MVG Cluster VI 30Sep24.pdf | 17 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 MVG Cluster VI 30Sep24.pdf | 17 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 MVG Cluster VI 30Sep24.pdf | 17 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory MVG VI 30Sep24.pdf | 17 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory MVG VI 30Sep24.pdf | 17 Dec 2024 |
| Layout approvalFile: RDP LETTER Dt 15 07 2024 1 3.pdf | 30 Nov 2024 |
| Layout approvalFile: Assessment Order aw RDP 1.pdf | 30 Nov 2024 |
| Building plan approvalFile: Assessment Order aw RDP 2.pdf | 30 Nov 2024 |
| Building plan approvalFile: Assessment Order aw RDP 3.pdf | 30 Nov 2024 |
| Building plan approvalFile: Assessment Order aw RDP 4.pdf | 30 Nov 2024 |
| Building plan approvalFile: Assessment Order aw RDP 5.pdf | 30 Nov 2024 |
| Building plan approvalFile: Assessment Order aw RDP 6.pdf | 30 Nov 2024 |
| Building plan approvalFile: Assessment Order aw RDP 7.pdf | 30 Nov 2024 |
| Building plan approvalFile: Assessment Order aw RDP 8.pdf | 30 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: RDP LETTER Dt 15 07 2024 1 3.pdf | 30 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: Assessment Order aw RDP 1.pdf | 30 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Assessment Order aw RDP 2.pdf | 30 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Assessment Order aw RDP 3.pdf | 30 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Assessment Order aw RDP 4.pdf | 30 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Assessment Order aw RDP 5.pdf | 30 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Assessment Order aw RDP 6.pdf | 30 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Assessment Order aw RDP 7.pdf | 30 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Assessment Order aw RDP 8.pdf | 30 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: MVG VI RERA Audit Report 31Mar2024.pdf | 6 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE FINAL.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate MVG Cluster VI 30 06 2024.pdf | 29 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 MVG Cluster VI 30June2024.pdf | 29 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: MVG Cluster VI Disclosure of Sold Inventory 30 06 2024.pdf | 29 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate MVG Cluster VI 30 06 2024.pdf | 29 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MVG VI FORM 2.pdf | 12 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: MVG VI SOLD UNSOLD.pdf | 12 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MVG VI FORM 3.pdf | 12 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MVG VA Engineers Certificate 31Mar2024.pdf | 10 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: MVG VA Disclosure of Inventory 31Mar2024.pdf | 10 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MVG VA CA Certificate 31Mar2024.pdf | 10 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect MVG Cluster VI.pdf | 5 Jul 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: GRIEVANCE REDRESSAL CELL MVG VI.pdf | 2 Jul 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: GRIEVANCE REDRESSAL CELL MVG VI.pdf | 2 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: MVG-VI.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate MVG Cluster VI.pdf | 7 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate MVG Cluster VI.pdf | 7 Feb 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Mayfair Hillcrest | Plot Bearing CTS No 2A-3B of Village Ghatkopar Vikhroli West Mumbai 400079 | 167 | Completed | Mar 2015 | Late, Jun 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 151 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Mayfair Virar Gardens Cluster-VI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Virar West3,200+ in Palghar
Filed coordinates, straight-line distance. 139 registered projects within 2 km.
MAYFAIR VIRAR GARDENS CLUSTER IV
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19,
MAYFAIR HOUSING
Agarwal Infinity
Laxminarayan Prabhudayal Agarwal
GOKUL HARI ANANTA
Mehta Ventures
GOKUL NAKSHATRA II
JSB HOMEMAKERS PRIVATE LIMITED
EVERSHINE AMAVI 303 PHASE 3
EVERSHINE DEVELOPERS
See every Palghar project, with the district possession charts
Builder: MAYFAIR HOUSING
MAYFAIR HOUSING has 7 registrations on MahaRERA, including Mayfair The View and MAYFAIR VIRAR GARDENS BUILDING NO 23, 24 and 25. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if Mayfair Virar Gardens Cluster-VI is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mayfair Virar Gardens Cluster-VI?
The registered promoter entity is MAYFAIR HOUSING, a partnership as per the filing. Its GSTIN 27AAHFM7843A1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mayfair Virar Gardens Cluster-VI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Mayfair Virar Gardens Cluster-VI?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Mayfair Virar Gardens Cluster-VI?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mayfair Virar Gardens Cluster-VI?
The professionals named in the filing: Architect: JAI MISTRY; Engineer: SANJEEV Basavantappa TIGADI; Engineer: S S PATNE ASSOCIATES; Chartered Accountant: MEHERNOSH DARA DUMASIA; Chartered Accountant: HEMANT JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mayfair Virar Gardens Cluster-VI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback