ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / VIVA CITY - A11

Registration lapsed No litigation declared Residential / Group Housing project

VIVA CITY - A11

By VIVA WINNER VENTURE RELATORS LLP

RG-MH-20007 · RERA P99000008138 · Last updated on MahaRERA portal: 15 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
4 of 11Construction stages donefurthest along: Staircases, 30%
1Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

VIVA CITY - A11 is a Residential / Group Housing project by VIVA WINNER VENTURE RELATORS LLP in Palghar, Maharashtra, registered with MahaRERA as P99000008138 on 18 Aug 2017. Possession was promised by 29 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVIVA CITY - A11
  • TypeResidential / Group Housing
  • Location
    • STATION ROAD
    • VIRAR WEST
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000008138
  • ReraGenie IDRG-MH-20007

Builder

  • NameVIVA WINNER VENTURE RELATORS LLP
  • Entity typePartnership
  • PartnerROHIL JAYENDRA THAKUR
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live2 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredAug 2017First promiseJun 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion29 Jun 2025
  • Revised completionRevised to 29 Jun 2025 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A11NA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 30%.

A11: 41% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed53

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots53
Closed/Covered18
Open Space35

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,413 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
VIVA WINNER VENTURE REALTORS LLPVasai-Virar City (M Corp)Palghar
VIVA HOLDINGSVasai-Virar City (M Corp)Palghar

Approvals and building plan

Permissible FSI5574.08
Proposed, not sanctioned5,574 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch11, VITHAL NAGAR CO-OP HSG SOCIETY, 10TH ROAD, JVPD SCHEME, VILE PARLE WEST 400049

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS ENCON
EngineerPARESH UNNARKAR
PartnerRole in project
VIVA WINNER VENTURE RELATORS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000024216Jun 2024 → Jun 2025

Reason as filed by the promoterWe are highly regretful for the delay in handing over the possession of the said project. We are in the final phase of completion of the project. Progress of the work hampered due to the cash flow which was impacted due to current market scenario in the region. Also, we faced material supply issue which also affected the progress of the work causing delay beyond our control.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000198713Mrs Daxa Bodha and Mr Nirmal BodhaViva Winner Venture Realtors LLP18/10/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3 for A11.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: A11 Inventory.pdf15 Feb 2025
Deviation Report with respect to model copy of AgreementFile: DEVIATION SHEET - A11.pdf15 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A of A11.pdf15 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Declaration of Secured or Unsecured finance A11.pdf15 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 of A11.pdf7 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 of A11.pdf7 Feb 2025
Disclosure of sold/ booked inventoryFile: A11 Inventory.pdf3 Feb 2025
Layout approvalFile: Layout 09-07-2021.pdf28 Jun 2024
Details of encumbrances concerned to FinanceFile: Legal Title Report 1-16.pdf28 Jun 2024
Details of encumbrances concerned to FinanceFile: Legal Title Report 17-32.pdf28 Jun 2024
Details of encumbrances concerned to LegalFile: Legal Title Report 1-16.pdf28 Jun 2024
Details of encumbrances concerned to LegalFile: Legal Title Report 17-32.pdf28 Jun 2024
Copy of Layout Approval (in case of layout)File: Layout 09-07-2021.pdf28 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A A11 2023.pdf28 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A A11 2024.pdf28 Jun 2024
CERSAI detailsFile: CERSAI Search Report.pdf28 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VIVA CITY A11 FY-23.pdf28 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VIVA CITY A11 FY-24.pdf28 Jun 2024
Disclosure of sold/ booked inventoryFile: Inventory of A11.pdf1 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: RDP 2023.pdf30 May 2024
Declaration about Commencement CertificateFile: Declaration of CC.pdf30 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other real estate organisation.pdf30 May 2024
Proforma of Agreement for saleFile: Agreement for Sale - Draft A11.pdf30 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank details of A11.pdf30 May 2024
Declaration about Commencement CertificateFile: CC Declaration.pdf5 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: A11 FORM 2A 2020.pdf4 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: A11 FORM 2A 2021.pdf4 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: A11 FORM 2A 2022.pdf4 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: A11 FORM 5 18-19.pdf4 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: A11 FORM 5 19-20.pdf4 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: A11 FORM 5 20-21.pdf4 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: A11 FORM 5 21-22.pdf4 May 2023
Disclosure of sold/ booked inventoryFile: INVENTORY A11.pdf2 May 2023
Certificates of CA (Form 5)File: Viva 11.pdf9 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A11 Engineer Certificate 31-3-18.pdf1 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: VIVA CITY CC.pdf5 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A11 Architect Certificate.pdf16 Jan 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A11 Engineer Certificate.pdf16 Jan 2018
Details of encumbrancesFile: ENCUMBRANCES A11.pdf29 Jul 2017
Declaration in FORM BFile: FORM 'B' A11.pdf29 Jul 2017
Proforma of Allotment letterFile: DECLARATION FOR ALLOTMENT LETTER AND AGREEMENT LETTER A11.pdf29 Jul 2017
Copy of the legal title reportFile: FINAL TITLE AND SEARCH REPORT.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE A11.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE A11.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE A11.pdf28 Jul 2017
OtherFile: SELF DECLERATION A11.pdf28 Jul 2017
OtherFile: DECLERATION BY ARCHITECT A11.pdf28 Jul 2017
Building plan approvalFile: A11.pdf26 Jul 2017
Layout approvalFile: Layout.pdf26 Jul 2017
PAN CardFile: Pan Card VIVA WINNER VENTURE REALTORS LLP.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf26 Jul 2017
Building Plan Approval (IOD)File: A11.pdf26 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIVA CITY - A11 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIRAR WEST3,200+ in Palghar

2 kmVIVA CITY - A11Completed 19Lapsed / revoked 14Other 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 87 registered projects within 2 km.

Builder: VIVA WINNER VENTURE RELATORS LLP

VIVA WINNER VENTURE RELATORS LLP has 6 registrations on MahaRERA, including VIVA CITY - A1 and VIVA CITY - A4. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that VIVA CITY - A11 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VIVA CITY - A11 is delayed beyond 29 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIVA CITY - A11?

The registered promoter entity is VIVA WINNER VENTURE RELATORS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIVA CITY - A11?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VIVA CITY - A11?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VIVA CITY - A11?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIVA CITY - A11?

The professionals named in the filing: Architect: MS ENCON; Engineer: PARESH UNNARKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIVA CITY - A11?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIVA CITY - A11. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIVA CITY - A11 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.