ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / VITHAL HARI TOWER

Completed No litigation declared Others project

VITHAL HARI TOWER

By VITHAL ENTERPRISES

RG-MH-54614 · RERA P99000006107 · Last updated on MahaRERA portal: 15 Dec 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2024Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 50%
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

VITHAL HARI TOWER is a Others project by VITHAL ENTERPRISES in Palghar, Maharashtra, registered with MahaRERA as P99000006107 on 14 Aug 2017. The registration is recorded completed; possession was promised by 19 Mar 2024. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameVITHAL HARI TOWER
  • TypeOthers
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000006107
  • ReraGenie IDRG-MH-54614

Builder

  • NameVITHAL ENTERPRISES
  • Entity typePartnership
  • PartnersRAJESH GHANSHYAM SHAH, KIRAN TUKARAM THAKUR, AMIT BALKRISHNA PATIL, MITAL ARVIND SHAH

Key dates

this monthRegisteredAug 2017First promiseMar 2023Revised toMar 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion19 Mar 2024
  • Revised completionRevised to 19 Mar 2024 (originally 20 Mar 2023)
  • Buildings1 building record
  • Documents filed104 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VITHAL HARI TOWERNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 50%.

VITHAL HARI TOWER: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes50%

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered1
Open Space8

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,122 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
HARI NIWAS CHSVasai-Virar City (M Corp)Palghar
SHREE VITHAL NAGAR CHSVasai-Virar City (M Corp)Palghar

Approvals and building plan

Permissible FSI4250.66
Proposed, not sanctioned2,111 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEAR SAI BABA MANDIR VIRAR WEST

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY NARANG
PartnerRole in project
VITHAL ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000011518Mar 2023 → Mar 2024

Reason as filed by the promoterWork in progress as per Architect and Engineer and CA certificate pl check

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Dec 2023

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE - 31-08-2023.pdf15 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE - FORM -1 - 11-4-2023.pdf6 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER - FORM -2 - 11-04-2023.pdf6 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEER - FORM -2 - 11-04-2023.pdf6 May 2023
Disclosure of sold/ booked inventoryFile: SOLD - INVENTRY - 31 MARCH - 2023.pdf6 May 2023
Certificates of CA (Form 3)File: CA - FORM- 3 - MARCH- 2023.pdf6 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: BALANCE SHEET - 31-MARCH -2023.pdf6 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH - FROM -1- 16-01-2023.pdf20 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER -FORM- 2- 16-01-2023.pdf20 Feb 2023
Certificates of CA (Form 3)File: CA -FROM-3- 25-01-2023.pdf20 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf16 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf16 Jun 2022
Certificates of CA (Form 3)File: SEPTEMBER-2021.pdf16 Jun 2022
Certificates of CA (Form 3)File: DECEMBER-2021.pdf16 Jun 2022
Certificates of CA (Form 3)File: MARCH-2022.pdf16 Jun 2022
Building plan approvalFile: 1 LAYOUT.pdf29 Sep 2021
Building plan approvalFile: 2 GR 1st.pdf29 Sep 2021
Building plan approvalFile: 3 2nd 3rd 4th.pdf29 Sep 2021
Building plan approvalFile: 4 5th 6th 7th 8th.pdf29 Sep 2021
Building plan approvalFile: 5 9th.pdf29 Sep 2021
Building Plan Approval (IOD)File: 1 LAYOUT.pdf29 Sep 2021
Building Plan Approval (IOD)File: 2 GR 1st.pdf29 Sep 2021
Building Plan Approval (IOD)File: 3 2nd 3rd 4th.pdf29 Sep 2021
Building Plan Approval (IOD)File: 4 5th 6th 7th 8th.pdf29 Sep 2021
Building Plan Approval (IOD)File: 5 9th.pdf29 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf29 Sep 2021
Building plan approvalFile: SHEET NO - 1.pdf18 Sep 2021
Building plan approvalFile: SHEET NO - 2.pdf18 Sep 2021
Building plan approvalFile: SHEET NO -4.pdf18 Sep 2021
Building Plan Approval (IOD)File: SHEET NO - 1.pdf18 Sep 2021
Building Plan Approval (IOD)File: SHEET NO - 2.pdf18 Sep 2021
Building Plan Approval (IOD)File: SHEET NO -4.pdf18 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH.pdf18 Sep 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER.pdf18 Sep 2021
PAN CardFile: PANCARD.pdf9 Apr 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER.pdf9 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: IT-2017.pdf9 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: IT-2018.pdf9 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: IT-2019.pdf9 Apr 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITEC.pdf9 Apr 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITEC MARCH.pdf9 Apr 2021
OtherFile: Vasai Janta.pdf16 Mar 2021
Details of Restarting of Construction work post lockdownFile: COVID -19 LETTER.pdf15 Mar 2021
OtherFile: Vasai Janta.pdf15 Mar 2021
OtherFile: Vasai Janta.pdf15 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM -A ARCHETECT.pdf3 Mar 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2 ENGINEER.pdf3 Mar 2020
Certificates of CA (Form 3)File: FORM - 3 C A.pdf3 Mar 2020
OtherFile: FORM -A ARCHETECT.pdf3 Mar 2020
OtherFile: FORM - 3 C A.pdf3 Mar 2020
OtherFile: FORM 2 ENGINEER.pdf3 Mar 2020
OtherFile: ARCHITECHFORM-1.pdf29 Nov 2019
OtherFile: ENGINEER -FORM - 2.pdf29 Nov 2019
OtherFile: CA -FORM -3.pdf29 Nov 2019
OtherFile: sam_0001.pdf24 Oct 2019
OtherFile: sam_0002.pdf24 Oct 2019
OtherFile: sam_0003.pdf24 Oct 2019
OtherFile: sam_0004.pdf24 Oct 2019
OtherFile: Architec 09-05-2019.pdf9 May 2019
OtherFile: CA Certificate -09-05-2019.pdf9 May 2019
OtherFile: Eng 09-05-2019.pdf9 May 2019
OtherFile: OC.pdf27 Apr 2019
OtherFile: CA REPORT.pdf20 Feb 2019
OtherFile: jpg2pdf.pdf20 Feb 2019
OtherFile: ENGINEER CERT.pdf20 Feb 2019
OtherFile: ENGINEER CERT - 1.pdf20 Feb 2019
OtherFile: ARCHITECT - OCT -2018.pdf22 Oct 2018
OtherFile: C A REPORT - OCT - 2018.pdf22 Oct 2018
OtherFile: C A REPORT.pdf11 Sep 2018
OtherFile: C A CERTIFICATE.pdf28 May 2018
OtherFile: TDR PART - 1.pdf2 Apr 2018
OtherFile: TDR PART - 2.pdf2 Apr 2018
OtherFile: TDR PART - 3.pdf2 Apr 2018
OtherFile: CA REPORT - DEC- 2017.pdf3 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT - OCT -2017.pdf14 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER -OCT - 2017.pdf14 Nov 2017
Certificates of CA (Form 3)File: CA -OCT -2017.pdf14 Nov 2017
OtherFile: DECLARATION - OCT-2017.pdf14 Nov 2017
Building plan approvalFile: MYSCAN_20170717_0012.pdf31 Jul 2017
Building plan approvalFile: MYSCAN_20170717_0011.pdf31 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VITHAL HARI TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmVITHAL HARI TOWERCompleted 36Lapsed / revoked 21Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: VITHAL ENTERPRISES

VITHAL ENTERPRISES has 1 registration on MahaRERA, including VITHAL HARI TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if VITHAL HARI TOWER is delayed beyond 19 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VITHAL HARI TOWER?

The registered promoter entity is VITHAL ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VITHAL HARI TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VITHAL HARI TOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VITHAL HARI TOWER?

The professionals named in the filing: Architect: SANJAY NARANG. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VITHAL HARI TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VITHAL HARI TOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VITHAL HARI TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.