ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / VISTA CORNER

Registered No litigation declared Others project

VISTA CORNER

By MJ INFRA

RG-MH-18079 · RERA P52000055870 · Last updated on MahaRERA portal: 25 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2029Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 35%
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

VISTA CORNER is a Others project by MJ INFRA in Raigarh, Maharashtra, registered with MahaRERA as P52000055870 on 29 Apr 2024. Possession is promised by 31 Mar 2029.

At a glance

Project

  • NameVISTA CORNER
  • TypeOthers
  • Location
    • NODE PUSHPAK
    • NA
    • Owle
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000055870
  • ReraGenie IDRG-MH-18079

Builder

  • NameMJ INFRA
  • Entity typePartnership
  • PartnersPRAKASH J THAKKAR, OMKAR YASHWANT HUDAR, GORDEN DAS JAGWANI, JETHANAND MEHRUMAL JAGWANI

Key dates

this monthRegisteredApr 2024PromisedMar 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Apr 2024
  • Promised completion31 Mar 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed65 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VISTA CORNERNA1110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 35%.

VISTA CORNER: 31% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor10%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed80

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots80
Closed/Covered80

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,549 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
VASANT CHANDAR GHARATOwleRaigarh
BHAGWAN CHANDAR GHARATOwleRaigarh
RAMDAS CHANDAR GHARATOwleRaigarh
RAGHUNATH CHANDAR GHARATOwleRaigarh

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI5495.43
Proposed, not sanctioned4,995 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, UNIT NO 18, 19 AND 36, B WING, SHREE NAND DHAM, PLOT NO 59, SECTOR-11, CBD BELAPUR,

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMITKUMAR PATEL
EngineerBAHUBALI T DHAMANE
Chartered AccountantDHARA GADA
Chartered AccountantPRITESH GADA & CO
PartnerRole in project
MJ INFRA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2029

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1_ MARCH 26_ VISTA CORNER.pdf25 Apr 2026
Form 2File: FORM 2_ MARCH 26_ VISTA CORNER.pdf25 Apr 2026
Form 3File: FORM 3_ MARCH 26_ VISTA CORNER.pdf25 Apr 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 26_ VISTA CORNER.pdf25 Apr 2026
Form 1File: FORM 1_ DEC 25_ VISTA CORNER.pdf23 Jan 2026
Form 2File: FORM 2_DEC 25_VISTA CORNER.pdf23 Jan 2026
Form 3File: FORM 3_ DEC 25_ VISTA CORNER.pdf23 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ DEC 25_ VISTA CORNER.pdf23 Jan 2026
Form 1File: FORM 1_ JUNE 25_ VISTA CORNER.pdf14 Nov 2025
Form 2File: FORM 2_ JUNE 25_ VISTA CORNER.pdf14 Nov 2025
Form 3File: FORM 3_ JUNE 25_ VISTA CORNER.pdf14 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_JUNE 25_VISTA CORNER.pdf14 Nov 2025
Form 1File: FORM 1_ SEP 25_ VISTA CORNER.pdf14 Nov 2025
Form 2File: FORM 2_ SEP 25_ VISTA CORNER.pdf14 Nov 2025
Form 3File: FORM 3_SEP 25_VISTA CORNER.pdf14 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_SEP 25_VISTA CORNER.pdf14 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5_ MARCH 25_ VISTA CORNER.pdf27 Oct 2025
Form 1File: FORM 1_ MARCH 25_ VISTA CORNER.pdf1 Aug 2025
Form 2File: FORM 2_ MARCH 25_ VISTA CORNER.pdf1 Aug 2025
Form 3File: FORM 3_ MARCH 25_ VISTA CORNER_compressed.pdf1 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 25_ VISTA CORNER.pdf1 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_FORM 1_ Mj Infra_VISTA CORNER_JUNE 24.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_FORM 1_Mj Infra_VISTA CORNER_SEP 24.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_FORM 1_ Mj Infra_VISTA CORNER_DEC 24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_FORM 3_Mj Infra_VISTA CORNER_ JUNE 24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_FORM 3_ Mj Infra_VISTA CORNER_SEP 24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_FORM 3_ Mj Infra_VISTA CORNER_DEC 24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_FORM 2_Mj Infra_VISTA CORNER_JUNE 24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_FORM 2_Mj Infra_VISTA CORNER_SEP 24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_FORM 2_Mj Infra_VISTA CORNER_DEC 24.pdf18 Feb 2025
Disclosure of sold/ booked inventoryFile: 4_SOLD UNSOLD_Mj Infra_VISTA CORNER_ JUNE 24.pdf18 Feb 2025
Disclosure of sold/ booked inventoryFile: 4_SOLD UNSOLD_Mj Infra_VISTA CORNER_ SEP 24.pdf18 Feb 2025
Disclosure of sold/ booked inventoryFile: 4_SOLD UNSOLD_ Mj Infra_VISTA CORNER_DEC 24-1-3.pdf18 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: RERA MAIL.pdf11 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf11 Apr 2024
Other - TechnicalFile: 2 Other - Technical (1).pdf11 Apr 2024
Layout approvalFile: CC DWG-1_compressed.pdf29 Mar 2024
Building plan approvalFile: CC DWG-2.pdf29 Mar 2024
Building plan approvalFile: CC DWG-3.pdf29 Mar 2024
Copy of the legal title reportFile: 2 Copy of the legal title report-1-6 (1).pdf29 Mar 2024
Copy of the legal title reportFile: 2 Copy of the legal title report-7-12.pdf29 Mar 2024
Copy of Layout Approval (in case of layout)File: CC DWG-1_compressed.pdf29 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: CC DWG-2.pdf29 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: CC DWG-3.pdf29 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: CC COPY.pdf29 Mar 2024
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (1).pdf29 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 14 Disclosure of Interest in Other Real Estate Organizations.pdf29 Mar 2024
PAN CardFile: 1 PAN CARD.pdf28 Mar 2024
Details of encumbrances concerned to FinanceFile: 3 a Details of encumbrances concerned to Finance.pdf28 Mar 2024
Details of encumbrances concerned to FinanceFile: 4 b Details of encumbrances concerned to Legal.pdf28 Mar 2024
Details of encumbrances concerned to LegalFile: 3 a Details of encumbrances concerned to Finance.pdf28 Mar 2024
Details of encumbrances concerned to LegalFile: 4 b Details of encumbrances concerned to Legal.pdf28 Mar 2024
Declaration in FORM BFile: 9 Declaration in FORM B.pdf28 Mar 2024
CERSAI detailsFile: 12 CERSAI details.pdf28 Mar 2024
Proforma of Agreement for saleFile: 15 Proforma of Agreement for sale.pdf28 Mar 2024
Proforma of Allotment letterFile: 16 Proforma of Allotment letter.pdf28 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 22 Separate Bank Account details including no encumbrances on the Bank Account or no escro28 Mar 2024
Deviation Report with respect to Allotment letterFile: 23 Deviation Report with respect to Allotment letter.pdf28 Mar 2024
Deviation Report with respect to model copy of AgreementFile: 24 Deviation Report with respect to model copy of Agreement.pdf28 Mar 2024
Other - LegalFile: 17 LEGAL OTHER_LEASE DEED_compressed-1-20.pdf28 Mar 2024
Other - LegalFile: 17 LEGAL OTHER_LEASE DEED_compressed-21-40.pdf28 Mar 2024
Other - LegalFile: 17 LEGAL OTHER_LEASE DEED_compressed-41-61.pdf28 Mar 2024
Other - LegalFile: 18 Legal Other - Partnership Deed.pdf28 Mar 2024
Other - FinanceFile: 19 Finance - Partnership Deed.pdf28 Mar 2024
Other - TechnicalFile: 20 Technical - Partnership Deed.pdf28 Mar 2024

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VISTA CORNER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA5,900+ in Raigarh

2 kmVISTA CORNERCompleted 7Lapsed / revoked 5Other 103Dot size: filed unitsN

Filed coordinates, straight-line distance. 115 registered projects within 2 km.

Builder: MJ INFRA

MJ INFRA has 1 registration on MahaRERA, including VISTA CORNER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if VISTA CORNER is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VISTA CORNER?

The registered promoter entity is MJ INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VISTA CORNER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VISTA CORNER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VISTA CORNER?

The professionals named in the filing: Architect: AMITKUMAR PATEL; Engineer: BAHUBALI T DHAMANE; Chartered Accountant: DHARA GADA; Chartered Accountant: PRITESH GADA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VISTA CORNER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VISTA CORNER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VISTA CORNER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.