ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / Vista 3A

De-registered No litigation declared Residential / Group Housing project

Vista 3A

By Samsara Fund Advisors Pvt. Ltd.

RG-MH-35378 · RERA P50500051699 · Last updated on MahaRERA portal: 6 Dec 2025

Source: official MahaRERA filing

Red flags

  • De-registered
  • Possession 4 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
1 of 11Construction stages donefurthest along: Plinth, 90%
84 of 84Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

Vista 3A is a Residential / Group Housing project by Samsara Fund Advisors Pvt. Ltd. in Nagpur, Maharashtra, registered with MahaRERA as P50500051699 on 27 Jun 2023. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 0 of the 84 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameVista 3A
  • TypeResidential / Group Housing
  • Location
    • Basa Pipla
    • Mouza
    • Pipla
    • Nagpur (Rural)
    • Nagpur
    • 440034
  • Pincode440034
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500051699
  • ReraGenie IDRG-MH-35378

Builder

  • NameSamsara Fund Advisors Pvt. Ltd.
  • Entity typeCompany
  • CINU74140MH2006PTC162693
  • GSTIN27AAKCS0235J1ZA
  • DirectorsGayatri Rangachari Shah, Viral Chittaranjan Shah, Dharmendra Satiram Shastri

Key dates

4 months past promisethis monthRegisteredJun 2023PromisedJun 2026

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on27 Jun 2023
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed125 files

Current status

0%0 of 84 units booked
4.9%Work done, per cost certificate

Figures as on 6 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vista 3ANA8784084

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Plinth, at 90%.

Vista 3A: 18% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure12%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes80%
Street LightingYes0%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed224

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots224
Closed/Covered148
Open Space76

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,934 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Jul 2025

Approvals and building plan

Sanctioning authorityJoint Director Town Planning/Collectors Office Nagpur
Permissible FSI7692.73
Proposed, not sanctioned7,693 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Industry House, Opp Ramon House, 159 H T Parekh Marg, Churchgate, Mumbai 400020
Estimated costRs 18.05 cr
Cost incurredRs 87.83 lakh
Work done4.87%
BuildingWingEstimatedIncurred
Vista 3ANARs 17.83 crRs 74.63 lakh
-NARs 22.00 lakhRs 13.20 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectStudio Eleven
EngineerStudio Eleven
EngineerJeevan Ramkrishna Kute
Chartered AccountantShivnandan N Katdare
Chartered AccountantJain Nirmal Kumar & Associates
PartnerRole in project
Samsara Fund Advisors Pvt. Ltd.-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM-1_JUNE-2023.pdf6 Dec 2025
Form 2File: FORM-2_JUNE-2023.pdf6 Dec 2025
Form 3File: FORM-3_JUNE-2023.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_JUNE-2023.pdf6 Dec 2025
Form 1File: FORM-1_SEPTEMBER-2023.pdf6 Dec 2025
Form 2File: FORM-2_SEPTEMBER-2023.pdf6 Dec 2025
Form 3File: FORM-3_SEPTEMBER-2023.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_SEPTEMBER-2023.pdf6 Dec 2025
Form 1File: FORM-1_DECEMBER-2023.pdf6 Dec 2025
Form 2File: FORM-2_DECEMBER-2023.pdf6 Dec 2025
Form 3File: FORM-3_DECEMBER-2023.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_DECEMBER-2023.pdf6 Dec 2025
Form 1File: FORM-1_MARCH-2024.pdf6 Dec 2025
Form 2File: FORM-2_MARCH-2024.pdf6 Dec 2025
Form 3File: FORM-3_MARCH-2024.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_MARCH-2024.pdf6 Dec 2025
Form 1File: FORM-1_JUNE-2024.pdf6 Dec 2025
Form 2File: FORM-2_JUNE-2024.pdf6 Dec 2025
Form 3File: FORM-3_JUNE-2024.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_JUNE-2024.pdf6 Dec 2025
Form 1File: FORM-1_SEPTEMBER-2024.pdf6 Dec 2025
Form 2File: FORM-2_SEPTEMBER-2024.pdf6 Dec 2025
Form 3File: FORM-3_SEPTEMBER-2024.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_SEPTEMBER-2024.pdf6 Dec 2025
Form 1File: FORM-1_DECEMBER-2024.pdf6 Dec 2025
Form 2File: FORM-2_DECEMBER-2024.pdf6 Dec 2025
Form 3File: FORM-3_DECEMBER-2024.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_DECEMBER-2024.pdf6 Dec 2025
Form 1File: FORM-1_MARCH-2025.pdf6 Dec 2025
Form 2File: FORM-2_MARCH-2025.pdf6 Dec 2025
Form 3File: FORM-3_MARCH-2025.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD-UNSOLD_MARCH-2025.pdf6 Dec 2025
Withdrawal Update Form 1File: FORM-1_SEPTEMBER-2025.pdf6 Dec 2025
Withdrawal Update Form 2File: FORM-2_SEPTEMBER-2025.pdf6 Dec 2025
Withdrawal Update Form 3File: FORM-3_SEPTEMBER-2025.pdf6 Dec 2025
Form 2A (FY 2023-2024)File: FORM-2A_MARCH-2024.pdf8 Nov 2025
Form 5 (FY 2023-2024)File: FORM-5_MARCH-2024.pdf8 Nov 2025
Withdrawal Update Form 1File: Arch_Cert_Samsara_Jun_25.pdf30 Jul 2025
Withdrawal Update Form 2File: Engg_Cert_Samsara_Jun_25.pdf30 Jul 2025
Withdrawal Update Form 3File: CA_Cert_Samsara_Jun_25_signed.pdf30 Jul 2025
Form 5 (FY 2024-2025)File: FORM-5_MARCH-2025.pdf18 Jul 2025
Form 2A (FY 2024-2025)File: QA_Cert_Vista 3A_Mar_25.pdf17 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Samsara_Mar_25.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Samsara_Mar_25.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Samsara_Dec_24.pdf11 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Samsara_Dec_24.pdf11 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5(FY23-24).pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Samsara_Jun_24.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate_Samsara_Sep_24.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Samsara_Sep 24.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate _Samsara_Sep_24.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert_Vista 3A_S_Dec_23.pdf1 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert_Vista 3A_S_Jun_24.pdf1 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Vista 3A_S_Jun_24.pdf1 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA_Cert_Vista 3A_S_Mar 24.pdf1 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_S_Mar 24.pdf1 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Vista 3A.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Vista 3A.pdf28 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Dec 2023.pdf29 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Dec 2023.pdf29 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_ Sep_23_New.pdf20 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Samsara_Jun_23.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Samsara_Sep_23.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Samsara_Jun_23.pdf21 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert_Samsara_Sep_23.pdf21 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Samsara_Jun_23.pdf21 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert_Samsara_Sep_23.pdf21 Dec 2023
Other - LegalFile: FSA_Vista 3A_Samsara Fund Advisors Private Limited 1-35.pdf12 Jun 2023
Other - LegalFile: FSA_Vista 3A_Samsara Fund Advisors Private Limited 36-75.pdf12 Jun 2023
Other - LegalFile: FSA_Vista 3A_Samsara Fund Advisors Private Limited 76-100.pdf12 Jun 2023
Building plan approvalFile: R-1_2-Midrise-02_Details_with_Parking.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-03_Stilt.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-04_1st Floor.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-05_2nd Floor.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-06_3rd Floor.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-07_4th Floor.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-08_5th Floor.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-09_6th Floor.pdf31 May 2023
Building plan approvalFile: R-1_2-Midrise-10_7th Floor.pdf31 May 2023
Building Plan Approval / NA Order for plotted developmentFile: R-1_2-Midrise-02_Details_with_Parking.pdf31 May 2023

How this compares with Nagpur

0%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vista 3A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mouza2,800+ in Nagpur

2 kmVista 3ACompleted 19Lapsed / revoked 13Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: Samsara Fund Advisors Pvt. Ltd.

Samsara Fund Advisors Pvt. Ltd. has 1 registration on MahaRERA, including Vista 3A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that Vista 3A shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vista 3A is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vista 3A?

The registered promoter entity is Samsara Fund Advisors Pvt. Ltd., a company as per the filing. Its CIN U74140MH2006PTC162693 and GSTIN 27AAKCS0235J1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vista 3A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vista 3A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vista 3A?

The professionals named in the filing: Architect: Studio Eleven; Engineer: Studio Eleven; Engineer: Jeevan Ramkrishna Kute; Chartered Accountant: Shivnandan N Katdare; Chartered Accountant: Jain Nirmal Kumar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vista 3A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vista 3A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vista 3A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.