Home / Browse projects / Nagpur, Maharashtra / Vista 3A
Vista 3A
By Luxora Infrastructure Private Limited
RG-MH-03888 · RERA P50500032662 · Last updated on MahaRERA portal: 7 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vista 3A is a Plotted project by Luxora Infrastructure Private Limited in Nagpur, Maharashtra, registered with MahaRERA as P50500032662 on 17 Jan 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 36 months from the original filing. 1 of the 1 unit on this registration is recorded sold or booked.
At a glance
Project
- NameVista 3A
- TypePlotted
- Location
- Besa Pipla Road
- Mouza
- Pipla
- Nagpur (Rural)
- Nagpur
- 440034
- Pincode440034
- RERA no.P50500032662
- ReraGenie IDRG-MH-03888
Builder
- NameLuxora Infrastructure Private Limited
- Entity typeCompany
- CINU70100MH2007PTC166943
- GSTIN27AABCL2854K2ZA
- DirectorsDeepak Mahadeo Vasandani, Tarun Hundalani
- Other registrations22 more →
- Completed8 of 23
- No longer live4 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Jan 2022
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2022)
- BuildingsNot stated in filing
- Documents filed75 files
Current status
Figures as on 7 Jan 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 7 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 7 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Chartered Accountant | Neha Joshi |
| Partner | Role in project |
|---|---|
| Luxora Infrastructure Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo, The Real Estate Regulatory Authority (RERA), 6th Floor, Housfin Bhavan, Plot No. C-21, E Block, BKC, Bandra East, Mumbai - 400051. Subject: Declaration for Extension of Project - Vista 3A RERA Registration No. P50500032662 Respected Sir/Madam, We, Luxora Infrastructure Pvt. Ltd., the promoter of the project Vista 3A, bearing RERA Registration No. P50500032662, hereby submit this declaration for extension of the project completion timeline. We wish to inform you that the construction work for the above-mentioned project has been fully completed. However, the delay in formally updating the p
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Dec 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Nov 2024
Documents filed75
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Form 5_Upload_Vista 3A_FY24_25.pdf | 7 Jan 2026 |
| Declaration in FORM BFile: Rera Form B.pdf | 7 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form-2A.pdf | 7 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5.pdf | 7 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Jun_22.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Sep_22.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Dec_22.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Mar_23.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Jun_23.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Sep_23.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Dec_23.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Mar_24.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Jun_24.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Sep_24.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Dec_24.pdf | 1 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Vista 3A_Mar_25.pdf | 1 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Mar_22.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Sep_22.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Jun_22.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Dec_22.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Mar_23.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Jun_23.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Sep_23.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3ADec_23.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Mar_24.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Jun_24.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Sep_24.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Dec_24.pdf | 23 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Cert_Vista 3A_Mar_25.pdf | 23 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Vista 3A_March_2025.pdf | 21 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Vista 3A_Mar_2025.pdf | 15 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Vista 3A_Dec_24.pdf | 7 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Vista 3A_Dec_24.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Vista 3A_2(FY 23-24).pdf | 29 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Vista 3A_Form 4_Final_signed.pdf | 25 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Vista 3A_Form 4_Application for Completion_Merged.pdf | 25 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Vista 3A_Mar_24.pdf | 5 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Vista 3A_Jun_24.pdf | 5 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA_Cert_Vista 3A_Mar_24.pdf | 15 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: VISTA 3A FY 22-23.pdf | 16 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vista 3A.pdf | 5 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Vista 3A_Jun_22.pdf | 5 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg_Cert_Vista 3A_Sep_22.pdf | 5 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC Vista 3A _Jun_22.pdf | 21 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC Vista 3A 2_Sep_22.pdf | 21 Jun 2023 |
| Proforma of Agreement for saleFile: Proforma of Agreement for Sale.pdf | 15 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Vista 3A_Completion Certificate.pdf | 11 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Vista 3A_QA_Cert_Form 2A.pdf | 6 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Cert_Vista 3A_Mar_22.pdf | 18 May 2022 |
| Layout approvalFile: Vista 3A Layout 2 New.pdf | 7 Jan 2022 |
| Layout approvalFile: Vista 3A 1 Layout_New.pdf | 7 Jan 2022 |
| Layout approvalFile: Vista 3A Layout 3_New.pdf | 7 Jan 2022 |
| Layout approvalFile: EMP_Vista 3A IOD_Updated.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Vista 3A Layout 2 New.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Vista 3A 1 Layout_New.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Vista 3A Layout 3_New.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: EMP_Vista 3A IOD_Updated.pdf | 7 Jan 2022 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate_with stamp.pdf | 7 Jan 2022 |
| Declaration in FORM BFile: Form B_Vista_3A_with Date.pdf | 26 Dec 2021 |
| Proforma of Allotment letterFile: Proforma of agreement for sale.pdf | 24 Dec 2021 |
| Proforma of Allotment letterFile: Allotment Letter_Vista 3A_Generic.pdf | 24 Dec 2021 |
| Building plan approval or NA orderFile: Commencement Certificate_Vista 3A.pdf | 23 Dec 2021 |
| Building plan approval or NA orderFile: Vista 3A_IOD.pdf | 23 Dec 2021 |
| Building plan approval or NA orderFile: EMP_Vista 3A IOD_Updated.pdf | 23 Dec 2021 |
| Copy of the legal title reportFile: Vista 3A_Title 2_compressed.pdf | 23 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Commencement Certificate_Vista 3A.pdf | 23 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Vista 3A_IOD.pdf | 23 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: EMP_Vista 3A IOD_Updated.pdf | 23 Dec 2021 |
| Copy of the legal title reportFile: Vista 3A_Title 1_compressed.pdf | 14 Dec 2021 |
| CERSAI detailsFile: CERSAI 97 (BOB)-merged.pdf | 7 Dec 2021 |
| PAN CardFile: LIPL PAN.pdf | 1 Dec 2021 |
| Details of encumbrancesFile: Encumbrance_Vista 3A.pdf | 1 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Vista 3A_Highlighted.pdf | 1 Dec 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate_Vista 3A _compressed.pdf | 1 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate_Vista 3A_compressed.pdf | 1 Dec 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 22 other registrations, which the RERA portal never shows together
- All 75 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vista 3A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mouza2,800+ in Nagpur
BHEDE NAGARI -CHARITON
DILIP GANPATRAO BHEDE
Godrej Orchard Estate
Godrej Properties Limited
MELBOURNE CITY
M/S 4 PILLARS REALTY
GARDEN HOMES ATHARVA NAGARI VII
ATHARVA INFRASTRUCTURES
ROYAL EMPIRE
M B INFRA
Ved Vidhi Ventures
Ved Vidhi Ventures
See every Nagpur project, with the district possession charts
Builder: Luxora Infrastructure Private Limited
Luxora Infrastructure Private Limited has 23 registrations on MahaRERA, including Treeline 5 and Vista 3B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What does it mean that Vista 3A shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Vista 3A is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vista 3A?
The registered promoter entity is Luxora Infrastructure Private Limited, a company as per the filing. Its CIN U70100MH2007PTC166943 and GSTIN 27AABCL2854K2ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vista 3A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vista 3A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vista 3A?
The professionals named in the filing: Chartered Accountant: Neha Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vista 3A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback