Home / Browse projects / Nagpur, Maharashtra / VISHWABHARTI RESIDENCY

Registered No litigation declared Residential / Group Housing project

VISHWABHARTI RESIDENCY

By BHAVESH KUCHANWAR

RG-MH-33430 · RERA P50500080723 · Last updated on MahaRERA portal: 19 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jun 2029Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
61 of 61Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

VISHWABHARTI RESIDENCY is a Residential / Group Housing project by BHAVESH KUCHANWAR in Nagpur, Maharashtra, registered with MahaRERA as P50500080723 on 27 Jun 2025. Possession is promised by 30 Jun 2029. 0 of the 61 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameVISHWABHARTI RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • EWS PLOT
    • CTS NO 571
    • KH NO 45/4
    • MOUZA- MANEWADA
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440027
  • Pincode440027
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500080723
  • ReraGenie IDRG-MH-33430

Builder

  • NameBHAVESH KUCHANWAR
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2025PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jun 2025
  • Promised completion30 Jun 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Current status

0%0 of 61 units booked

Figures as on 19 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AGASTYNA10861061

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

AGASTY: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed103

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots103
Closed/Covered86
Open Space17

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,092 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
VISHWABHARTI CO OPERATIVE HOUSING SOCIETYNagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNagpur Municipal Corporation (NMC)
Permissible FSI6716.02
Proposed, not sanctioned5,151 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDHARAMPETH BRANCH,PLOT NO.8,WHC ROAD,SHANKAR NAGAR DHARAMPETH NAGPUR 440010

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANDEEP PANDIT ARCHITECTS
EngineerVIKESH MESHRAM
Chartered AccountantSUMIT CHANDWANI
PartnerRole in project
BHAVESH KUCHANWAR-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Apr 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2029

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Architect certificate Sept 25.pdf19 Jun 2026
Form 2File: Form 2 Engineer certificate Sept 25.pdf19 Jun 2026
Form 3File: Form 3 CA Certificate Sept 25.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory Sept 25.pdf19 Jun 2026
Form 1File: Form1 Architect Certificate Dec 25.pdf19 Jun 2026
Form 2File: Form 2 Engineer certificate Dec 25.pdf19 Jun 2026
Form 3File: Form 3 CA Certificate Dec 25.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory Dec 25.pdf19 Jun 2026
Form 1File: Form 1 Architect Certificate Mar 26.pdf19 Jun 2026
Form 2File: Form 2 Engineer certificate Mar 26.pdf19 Jun 2026
Form 3File: Form 3 CA Certificate March 2026.pdf19 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory March 26.pdf19 Jun 2026
Other - FinanceFile: Declaration for revenue.pdf16 Jun 2025
Other - TechnicalFile: 6_compressed.pdf14 Jun 2025
Other - TechnicalFile: SANCTION PLAN 6.pdf6 Jun 2025
Other - TechnicalFile: Declaration for revenue.pdf6 Jun 2025
Other - LegalFile: DEVELOPMENT AGREEMENT.pdf31 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ews Engineer Certificate.pdf7 May 2025
Declaration in FORM BFile: sanskruti.pdf5 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A certificate ews.pdf5 May 2025
Other - TechnicalFile: GetUserDocumentFileContent (1).pdf5 May 2025
Proforma of Allotment letterFile: Allotment Letter Ews new.pdf1 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Ews.pdf1 May 2025
Other - FinanceFile: DECLARATION FOR NO SEPARATE BANK ACCOUNT.pdf1 May 2025
Proforma of Agreement for saleFile: AGREEMENT TO SELL.pdf1 May 2025
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf30 Apr 2025
Details of encumbrances concerned to FinanceFile: FINANCIAL ENCUMBRANCE.pdf30 Apr 2025
Declaration about Commencement CertificateFile: FORM D.pdf30 Apr 2025
CERSAI detailsFile: CERSAI DECLARATION.pdf30 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf30 Apr 2025
Deviation Report with respect to Allotment letterFile: DEVIATION IN ALLOTMENT LETTER.pdf30 Apr 2025
Details of encumbrances concerned to LegalFile: FINANCIAL ENCUMBRANCE.pdf30 Apr 2025
Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE.pdf30 Apr 2025
Other - TechnicalFile: ORDER 50.pdf30 Apr 2025
Other - TechnicalFile: PAN CARD DECLARATION.pdf30 Apr 2025
Deviation Report with respect to model copy of AgreementFile: DEVIATION IN AFS.pdf30 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A.pdf30 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE OF FINANCE.pdf30 Apr 2025
Layout approvalFile: SANCTION PLAN 1.pdf29 Apr 2025
Layout approvalFile: SANCTION PLAN 2.pdf29 Apr 2025
Building plan approvalFile: SANCTION PLAN 3.pdf29 Apr 2025
Building plan approvalFile: SANCTION PLAN 4.pdf29 Apr 2025
Building plan approvalFile: SANCTION PLAN 5.pdf29 Apr 2025
Building plan approvalFile: SANCTION PLAN 6.pdf29 Apr 2025
PAN CardFile: PAN CARD.pdf29 Apr 2025
Copy of the legal title reportFile: TITLE REPORT.pdf29 Apr 2025
Copy of Layout Approval (in case of layout)File: SANCTION PLAN 1.pdf29 Apr 2025
Copy of Layout Approval (in case of layout)File: SANCTION PLAN 2.pdf29 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMIT.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN 3.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN 4.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN 5.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN 6.pdf29 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: DocScanner 31 May 2025 4-13 pm.pdf29 Apr 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VISHWABHARTI RESIDENCYP50500035066MANEWADA, Nagpur284May 2022OngoingDec 2025Not delivered

How this compares with Nagpur

0%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VISHWABHARTI RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOUZA- MANEWADA2,800+ in Nagpur

2 kmVISHWABHARTI RESIDENCYCompleted 7Lapsed / revoked 8Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: BHAVESH KUCHANWAR

BHAVESH KUCHANWAR has 1 registration on MahaRERA, including VISHWABHARTI RESIDENCY. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if VISHWABHARTI RESIDENCY is delayed beyond 30 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VISHWABHARTI RESIDENCY?

The registered promoter entity is BHAVESH KUCHANWAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VISHWABHARTI RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VISHWABHARTI RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VISHWABHARTI RESIDENCY?

The professionals named in the filing: Architect: SANDEEP PANDIT ARCHITECTS; Engineer: VIKESH MESHRAM; Chartered Accountant: SUMIT CHANDWANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VISHWABHARTI RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VISHWABHARTI RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VISHWABHARTI RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.