Viraj Sequoia
RG-MH-12060 · RERA P52100012411 · Last updated on MahaRERA portal: 3 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 35 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Viraj Sequoia is a Residential / Group Housing project by SEQUOIA REALTY LLP in AUNDH, 411007, registered with MahaRERA as P52100012411 on 1 Sep 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 35 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameViraj Sequoia
- TypeResidential / Group Housing
- Location
- Mangesh Society Road
- AUNDH
- 411007
- Pincode411007
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100012411
- ReraGenie IDRG-MH-12060
Builder
- NameSEQUOIA REALTY LLP
- Entity typeOthers
- Named personsNEELESH NANDAKUMAR AGARWAL, SWANAND RAJARAM AROLE, AALOK VASANT KHANDELWAL, AJAY ISHWARCHAND AGARWAL, ANKUSH GOPAL GUPTA, BANSILAL CHANDAGIRAM AGARWAL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 31 Jan 2021)
- Buildings1 building record
- Documents filed75 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VIRAJ SEQUOIA | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
VIRAJ SEQUOIA: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Malwadkar Architects |
| Engineer | Dhananjay Hirve |
| Partner | Role in project |
|---|---|
| SEQUOIA REALTY LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid Pandemic situation we are facing problem of Labour, Material Supplies and other unavoidable reason so we request you to grant us the extension
Reason as filed by the promoterChange in TDR rules in January 2017 caused a delay in the sanctioning of additional FSI, which was finally obtained on 7th January 2020. Thereafter, the project was closed for 6 months due to Covid 19. We have restarted the construction of the project and shall be completing it by the new date given above. We have not sold any flats nor taken any bookings for the same for the said project till date. Request you to please be so kind as to extend the date of completion of the project. Regards.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12500605 | Omprakash Indradatta Thapliyal | SEQUOIA REALTY LLP | 21/02/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 19 Nov 2024
Documents filed75
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: Plan 1 OF 4_1_11zon.pdf | 3 Dec 2024 |
| Building plan approvalFile: Plan 2 OF 4_2_11zon.pdf | 3 Dec 2024 |
| Building plan approvalFile: Plan 3 OF 4_3_11zon.pdf | 3 Dec 2024 |
| Building plan approvalFile: Plan 4 OF 4_4_11zon.pdf | 3 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE RELATED TO FINANCE.pdf | 3 Dec 2024 |
| Details of encumbrancesFile: self declaration regarding encumbrance.pdf | 3 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE RELATED TO LEGAL.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1- Certificate-31-03-2019.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 - Rera Certificate-31-03-2020.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 - Rera Certificate-31-03-2018.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 - Rera Certificate-08-02-2021.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form - 1 Rera Certificate-03-08-2021.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 - Rera Certificate-11-07-2022.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1- Certificate-2024.pdf | 3 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Form 4.pdf | 3 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf | 3 Dec 2024 |
| Building Plan Approval (IOD)File: Plan 4 OF 4_4_11zon.pdf | 3 Dec 2024 |
| Building Plan Approval (IOD)File: Plan 3 OF 4_3_11zon.pdf | 3 Dec 2024 |
| Building Plan Approval (IOD)File: Plan 1 OF 4_1_11zon.pdf | 3 Dec 2024 |
| Building Plan Approval (IOD)File: Plan 2 OF 4_2_11zon.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: C A - FORM 5 F Y 20-21.pdf | 3 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - Unsold Inventory List.pdf | 3 Dec 2024 |
| CERSAI detailsFile: Cersai Report - Sequoia Realty.pdf | 3 Dec 2024 |
| CERSAI detailsFile: UNDERTAKING FOR CERSAI REPORT.pdf | 3 Dec 2024 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE RELATED TO LEGAL.pdf | 3 Dec 2024 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE RELATED TO FINANCE.pdf | 3 Dec 2024 |
| Other - FinanceFile: Reconveyance Deed_5_11zon.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: C A FORM 5 F Y 21-22.pdf | 3 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 21-22.pdf | 3 Dec 2024 |
| Proforma of Agreement for saleFile: Sequoia Realty Agreement.pdf | 3 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: C A FORM 5 F Y 22-23.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: C A FORM 5 F Y 23-24.pdf | 3 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC SEQUOIA AUNDH.pdf | 19 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 19 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf | 19 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf | 19 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 19 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC SEQUOIA AUNDH.pdf | 19 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf | 19 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf | 19 Nov 2024 |
| Declaration about Commencement CertificateFile: CC DECLARATION.pdf | 21 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance Certificate_30-06-2022.pdf | 21 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Sequoia Inventory sold Booked.pdf | 28 Mar 2022 |
| Declaration about Commencement CertificateFile: Format D Commencement certificate declaration.pdf | 13 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engineer certificate for quality assurance.pdf | 13 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Declaration of sold unsold.pdf | 13 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 19 20.pdf | 3 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 20 21.pdf | 3 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: SOLD and UNSOLD.pdf | 3 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: CA FORM 5 17-18.pdf | 3 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA FORM 5 18-19.pdf | 3 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA FORM 5 19-20.pdf | 3 Aug 2021 |
| Declaration about Commencement CertificateFile: Declaration for commencement.pdf | 2 Aug 2021 |
| Certificates of CA (Form 3)File: RERA CERTIFICATE SIGN.pdf | 28 Jul 2017 |
| Building plan approvalFile: scan01233.pdf | 27 Jul 2017 |
| Building plan approvalFile: scan01234.pdf | 27 Jul 2017 |
| Building plan approvalFile: scan01235.pdf | 27 Jul 2017 |
| Layout approvalFile: scan01233.pdf | 27 Jul 2017 |
| PAN CardFile: PAN CARD.pdf | 27 Jul 2017 |
| Copy of the legal title reportFile: 51(1).pdf | 27 Jul 2017 |
| Copy of the legal title reportFile: 52(1).pdf | 27 Jul 2017 |
| Details of encumbrancesFile: AKOLA URBAN BANK 1.pdf | 27 Jul 2017 |
| Details of encumbrancesFile: AKOLA URBAN BANK 2.pdf | 27 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: scan01233.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: scan01233.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: scan01234.pdf | 27 Jul 2017 |
| Building Plan Approval (IOD)File: scan01235.pdf | 27 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert.pdf | 27 Jul 2017 |
| Declaration in FORM BFile: Affidavit Form B.pdf | 27 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf | 27 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: pdf form.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 27 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT.pdf | 27 Jul 2017 |
| OtherFile: Development AGreement-ilovepdf- (1).pdf | 27 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 75 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Viraj Sequoia on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AUNDH
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
THE ANTHEM
C S Sanghavi Estate Division
Aundh Renaissance
SKYCRAFT BUILDCOM LLP
Ruhi Mangalam Niyoshi
Ruhi Mangalam Associates
UDYAM NAGARI
MAP ASSOCIATES
Megha Terrace Co-Operative Housing Society Lim
Raichandani Constructions Private Limited
Geras Affinia
Gera Developments Private Limited
Builder: SEQUOIA REALTY LLP
SEQUOIA REALTY LLP has 1 registration on MahaRERA, including Viraj Sequoia. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that Viraj Sequoia shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Viraj Sequoia is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Viraj Sequoia?
The registered promoter entity is SEQUOIA REALTY LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Viraj Sequoia?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Viraj Sequoia?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Viraj Sequoia?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Viraj Sequoia?
The professionals named in the filing: Architect: Malwadkar Architects; Engineer: Dhananjay Hirve. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Viraj Sequoia?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.