Home / Browse projects / Palghar, Maharashtra / VIMALNATH Building no-2
VIMALNATH Building no-2
By V HOUSING
RG-MH-07103 · RERA P99000056242 · Last updated on MahaRERA portal: 5 Oct 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 4 months
- 1 extension taken
- Rs 3.00 crore secured on the land, in favour of Tru home finance limited
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIMALNATH Building no-2 is a Others project by V HOUSING in Palghar, Maharashtra, registered with MahaRERA as P99000056242 on 22 May 2024. Possession is promised by 31 Dec 2027. The completion date has moved by 4 months from the original filing. 37 of the 63 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameVIMALNATH Building no-2
- TypeOthers
- Location
- M B ESTATE ROAD
- VIRAR
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401303
- Pincode401303
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000056242
- ReraGenie IDRG-MH-07103
Builder
- NameV HOUSING
- Entity typePartnership
- PartnersPRAVIN LAXMILAL JAIN, HITESH LALCHAND JAIN, VINOD SHANTILAL JAIN, NARESH BHAWARLAL JAIN, TULSIRAM HIRALAL JAIN, AKSHAY UDAYALAL JAIN, MAYUR NALINKANT SHAH
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 May 2024
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 31 Aug 2027)
- Buildings1 building record
- Documents filed54 files
Current status
Figures as on 5 Oct 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VIMALNATH BUILDING NO-2 | NA | 8 | 7 | 48 | 15 | 63 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 5 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 50%.
VIMALNATH BUILDING NO-2: 77% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 5 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| VIMALNATH CO-OPERATIVE HOSUING SOCIETY LTD | Vasai-Virar City (M Corp) | Palghar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| VIMALNATH BUILDING NO-2 | NA | Rs 7.54 cr | Rs 7.09 cr |
| - | NA | Rs 83.81 lakh | Rs 46.09 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | UMESH KEKRE |
| Engineer | DEVANG DILIP MHATRE |
| Engineer | s s & associates |
| Chartered Accountant | R D LUKAD & CO |
| Chartered Accountant | RAMESH DHONDIRAM LUKAD |
| Partner | Role in project |
|---|---|
| V HOUSING | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Nov 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Nov 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Nov 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: dm vimalnath form 2a 2.pdf | 5 Oct 2026 |
| Form 2A (FY 2025-2026)File: dm vimalnath form 2a 1.pdf | 5 Oct 2026 |
| Withdrawal Update Form 1File: VIMALNATH F1 Q126.pdf | 19 Aug 2026 |
| Withdrawal Update Form 2File: VIMALNATH.pdf | 19 Aug 2026 |
| Withdrawal Update Form 3File: VIMALNATH BLDG 2 FORM 3.pdf | 19 Aug 2026 |
| Withdrawal Update Form 1File: FORM-1 VIMALNATH (31-03-26).pdf | 12 May 2026 |
| Withdrawal Update Form 2File: FORM-2 VIMALNATH.pdf | 12 May 2026 |
| Withdrawal Update Form 3File: form 3_11zon.pdf | 12 May 2026 |
| Form 5 (FY 2024-2025)File: v housing Form 5 Vimalnath 24-25.pdf | 11 May 2026 |
| Form 5 (FY 2025-2026)File: v housing Form 5 vimalnath 25-26.pdf | 11 May 2026 |
| Withdrawal Update Form 1File: form 1.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: form 2.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: form 3_11zon.pdf | 3 Feb 2026 |
| Withdrawal Update Form 1File: FORM-1 VIMALNATH JULY TO SEP_0001.pdf | 8 Dec 2025 |
| Withdrawal Update Form 2File: VIMALNATH.pdf | 8 Dec 2025 |
| Withdrawal Update Form 3File: V HOUSING.pdf | 8 Dec 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIMALNATH FORM-1 .pdf | 12 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VIMALNATH FORM-2.pdf | 12 Apr 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Vimalnath.pdf | 11 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrance Vimalnath.pdf | 11 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: v housing 2_0001.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIMALNATH FORM-1 OCT TO DEC24_0001.pdf | 3 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Vimalnath_(11-01-25)_compressed.pdf | 3 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: VIMALNATH SOLD UNSOLD.pdf | 3 Feb 2025 |
| Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate(1)_page-0001.pdf | 6 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 6 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 6 May 2024 |
| Other - TechnicalFile: 2 Other - Technical.pdf | 6 May 2024 |
| Declaration in FORM BFile: FORMB-06-04-2024.pdf | 6 Apr 2024 |
| Details of encumbrances concerned to FinanceFile: Finance Declaration.pdf | 28 Mar 2024 |
| Details of encumbrances concerned to LegalFile: Finance Declaration.pdf | 28 Mar 2024 |
| CERSAI detailsFile: 1 CERSAI details.pdf | 28 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 28 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Mayur Jain- Disclosuer.pdf | 28 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Pravin Jain- Disclosuer.pdf | 28 Mar 2024 |
| Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf | 28 Mar 2024 |
| Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf | 28 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow | 28 Mar 2024 |
| Other - TechnicalFile: 1 Copy of Layout Approval (in case of layout).pdf | 28 Mar 2024 |
| Copy of the legal title reportFile: vimalnath title search new_compressed.pdf | 30 Nov 2023 |
| Layout approvalFile: LAYOUT PLAN (1)_compressed.pdf | 10 Nov 2023 |
| Building plan approvalFile: BLDG NO-2 _1ST FLOOR PLAN_compressed.pdf | 10 Nov 2023 |
| Building plan approvalFile: BLDG NO2 _ TIPICLE PLAN_compressed.pdf | 10 Nov 2023 |
| Building plan approvalFile: BLDG NO-2 7TH FLOOR PLAN_compressed.pdf | 10 Nov 2023 |
| PAN CardFile: COMPANY PANCARD.pdf | 10 Nov 2023 |
| Details of encumbrances concerned to FinanceFile: legal encumbrance.pdf | 10 Nov 2023 |
| Details of encumbrances concerned to LegalFile: legal encumbrance.pdf | 10 Nov 2023 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN (1)_compressed.pdf | 10 Nov 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG NO-2 _1ST FLOOR PLAN_compressed.pdf | 10 Nov 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG NO2 _ TIPICLE PLAN_compressed.pdf | 10 Nov 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: BLDG NO-2 7TH FLOOR PLAN_compressed.pdf | 10 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: VIMALNATH CC_compressed.pdf | 10 Nov 2023 |
| Deviation Report with respect to Allotment letterFile: rera allotment.pdf | 10 Nov 2023 |
| Deviation Report with respect to model copy of AgreementFile: rera agreement.pdf | 10 Nov 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 54 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep VIMALNATH Building no-2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VIRAR3,200+ in Palghar
Filed coordinates, straight-line distance. 232 registered projects within 2 km.
Mayfair Virar Gardens Cluster-VI
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS CLUSTER IV
MAYFAIR HOUSING
MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19,
MAYFAIR HOUSING
Agarwal Infinity
Laxminarayan Prabhudayal Agarwal
GOKUL HARI ANANTA
Mehta Ventures
GOKUL NAKSHATRA II
JSB HOMEMAKERS PRIVATE LIMITED
See every Palghar project, with the district possession charts
Builder: V HOUSING
V HOUSING has 2 registrations on MahaRERA, including SHREE JAY VISHAL BLDG NO-1 and VIMALNATH Building no-2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if VIMALNATH Building no-2 is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIMALNATH Building no-2?
The registered promoter entity is V HOUSING, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIMALNATH Building no-2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VIMALNATH Building no-2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIMALNATH Building no-2?
The professionals named in the filing: Architect: UMESH KEKRE; Engineer: DEVANG DILIP MHATRE; Engineer: s s & associates; Chartered Accountant: R D LUKAD & CO; Chartered Accountant: RAMESH DHONDIRAM LUKAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIMALNATH Building no-2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback