ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / VIMALNATH Building no-2

Registered No litigation declared Others project

VIMALNATH Building no-2

By V HOUSING

RG-MH-07103 · RERA P99000056242 · Last updated on MahaRERA portal: 5 Oct 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 3.00 crore secured on the land, in favour of Tru home finance limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 4 months from the original
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 50%
26 of 63Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

VIMALNATH Building no-2 is a Others project by V HOUSING in Palghar, Maharashtra, registered with MahaRERA as P99000056242 on 22 May 2024. Possession is promised by 31 Dec 2027. The completion date has moved by 4 months from the original filing. 37 of the 63 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameVIMALNATH Building no-2
  • TypeOthers
  • Location
    • M B ESTATE ROAD
    • VIRAR
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000056242
  • ReraGenie IDRG-MH-07103

Builder

  • NameV HOUSING
  • Entity typePartnership
  • PartnersPRAVIN LAXMILAL JAIN, HITESH LALCHAND JAIN, VINOD SHANTILAL JAIN, NARESH BHAWARLAL JAIN, TULSIRAM HIRALAL JAIN, AKSHAY UDAYALAL JAIN, MAYUR NALINKANT SHAH
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2024First promiseAug 2027Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 May 2024
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Aug 2027)
  • Buildings1 building record
  • Documents filed54 files

Current status

59%37 of 63 units booked
90.1%Work done, per cost certificate

Figures as on 5 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VIMALNATH BUILDING NO-2NA87481563

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 50%.

VIMALNATH BUILDING NO-2: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed54

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots54
Closed/Covered54

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,003 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofTru home finance limited
Secured amountRs 3.00 crore
CERSAI search filedYes
Declared on30 Jun 2026
LandownerVillageDistrict
VIMALNATH CO-OPERATIVE HOSUING SOCIETY LTDVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVVCMC
Permissible FSI3821.0
Proposed, not sanctioned3,814 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR NEW GULMOHAR CHS RAMWADI KARPEWADA PARNAKA VASAI W TAL VASAI VASAI MAHARASHTRA 401201
Estimated costRs 8.38 cr
Cost incurredRs 7.55 cr
Work done90.1%
BuildingWingEstimatedIncurred
VIMALNATH BUILDING NO-2NARs 7.54 crRs 7.09 cr
-NARs 83.81 lakhRs 46.09 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUMESH KEKRE
EngineerDEVANG DILIP MHATRE
Engineers s & associates
Chartered AccountantR D LUKAD & CO
Chartered AccountantRAMESH DHONDIRAM LUKAD
PartnerRole in project
V HOUSING-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P99000056242/WarAug 2027 → Dec 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: dm vimalnath form 2a 2.pdf5 Oct 2026
Form 2A (FY 2025-2026)File: dm vimalnath form 2a 1.pdf5 Oct 2026
Withdrawal Update Form 1File: VIMALNATH F1 Q126.pdf19 Aug 2026
Withdrawal Update Form 2File: VIMALNATH.pdf19 Aug 2026
Withdrawal Update Form 3File: VIMALNATH BLDG 2 FORM 3.pdf19 Aug 2026
Withdrawal Update Form 1File: FORM-1 VIMALNATH (31-03-26).pdf12 May 2026
Withdrawal Update Form 2File: FORM-2 VIMALNATH.pdf12 May 2026
Withdrawal Update Form 3File: form 3_11zon.pdf12 May 2026
Form 5 (FY 2024-2025)File: v housing Form 5 Vimalnath 24-25.pdf11 May 2026
Form 5 (FY 2025-2026)File: v housing Form 5 vimalnath 25-26.pdf11 May 2026
Withdrawal Update Form 1File: form 1.pdf3 Feb 2026
Withdrawal Update Form 2File: form 2.pdf3 Feb 2026
Withdrawal Update Form 3File: form 3_11zon.pdf3 Feb 2026
Withdrawal Update Form 1File: FORM-1 VIMALNATH JULY TO SEP_0001.pdf8 Dec 2025
Withdrawal Update Form 2File: VIMALNATH.pdf8 Dec 2025
Withdrawal Update Form 3File: V HOUSING.pdf8 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIMALNATH FORM-1 .pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VIMALNATH FORM-2.pdf12 Apr 2025
Details of encumbrances concerned to FinanceFile: Encumbrance Vimalnath.pdf11 Feb 2025
Details of encumbrances concerned to LegalFile: Encumbrance Vimalnath.pdf11 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: v housing 2_0001.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VIMALNATH FORM-1 OCT TO DEC24_0001.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Vimalnath_(11-01-25)_compressed.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: VIMALNATH SOLD UNSOLD.pdf3 Feb 2025
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate(1)_page-0001.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf6 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf6 May 2024
Other - TechnicalFile: 2 Other - Technical.pdf6 May 2024
Declaration in FORM BFile: FORMB-06-04-2024.pdf6 Apr 2024
Details of encumbrances concerned to FinanceFile: Finance Declaration.pdf28 Mar 2024
Details of encumbrances concerned to LegalFile: Finance Declaration.pdf28 Mar 2024
CERSAI detailsFile: 1 CERSAI details.pdf28 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf28 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Mayur Jain- Disclosuer.pdf28 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Pravin Jain- Disclosuer.pdf28 Mar 2024
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf28 Mar 2024
Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf28 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow28 Mar 2024
Other - TechnicalFile: 1 Copy of Layout Approval (in case of layout).pdf28 Mar 2024
Copy of the legal title reportFile: vimalnath title search new_compressed.pdf30 Nov 2023
Layout approvalFile: LAYOUT PLAN (1)_compressed.pdf10 Nov 2023
Building plan approvalFile: BLDG NO-2 _1ST FLOOR PLAN_compressed.pdf10 Nov 2023
Building plan approvalFile: BLDG NO2 _ TIPICLE PLAN_compressed.pdf10 Nov 2023
Building plan approvalFile: BLDG NO-2 7TH FLOOR PLAN_compressed.pdf10 Nov 2023
PAN CardFile: COMPANY PANCARD.pdf10 Nov 2023
Details of encumbrances concerned to FinanceFile: legal encumbrance.pdf10 Nov 2023
Details of encumbrances concerned to LegalFile: legal encumbrance.pdf10 Nov 2023
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN (1)_compressed.pdf10 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: BLDG NO-2 _1ST FLOOR PLAN_compressed.pdf10 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: BLDG NO2 _ TIPICLE PLAN_compressed.pdf10 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: BLDG NO-2 7TH FLOOR PLAN_compressed.pdf10 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: VIMALNATH CC_compressed.pdf10 Nov 2023
Deviation Report with respect to Allotment letterFile: rera allotment.pdf10 Nov 2023
Deviation Report with respect to model copy of AgreementFile: rera agreement.pdf10 Nov 2023

How this compares with Palghar

59%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 4 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIMALNATH Building no-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VIRAR3,200+ in Palghar

2 kmVIMALNATH Building no-2Completed 81Lapsed / revoked 50Other 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 232 registered projects within 2 km.

Builder: V HOUSING

V HOUSING has 2 registrations on MahaRERA, including SHREE JAY VISHAL BLDG NO-1 and VIMALNATH Building no-2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if VIMALNATH Building no-2 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIMALNATH Building no-2?

The registered promoter entity is V HOUSING, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIMALNATH Building no-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIMALNATH Building no-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIMALNATH Building no-2?

The professionals named in the filing: Architect: UMESH KEKRE; Engineer: DEVANG DILIP MHATRE; Engineer: s s & associates; Chartered Accountant: R D LUKAD & CO; Chartered Accountant: RAMESH DHONDIRAM LUKAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIMALNATH Building no-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIMALNATH Building no-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIMALNATH Building no-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.