Home / Browse projects / Palghar, Maharashtra / VIMAL'S RAMJANKI CHSL

Registered No litigation declared Others project

VIMAL'S RAMJANKI CHSL

By OMVIMAL BUILTCON LLP

RG-MH-18314 · RERA P99000077212 · Last updated on MahaRERA portal: 19 Aug 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jul 2028Possession promisedno revision filed
20 of 55Construction stages doneacross 5 buildings; furthest along: Slabs of Super Structure, 71%
128 of 131Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

VIMAL'S RAMJANKI CHSL is a Others project by OMVIMAL BUILTCON LLP in Palghar, Maharashtra, registered with MahaRERA as P99000077212 on 31 Jul 2024. Possession is promised by 15 Jul 2028. 3 of the 131 units on this registration are recorded sold or booked, and 20 of 55 construction stages are filed complete.

At a glance

Project

  • NameVIMAL'S RAMJANKI CHSL
  • TypeOthers
  • Location
    • 30MT ROAD
    • NILEMORE
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000077212
  • ReraGenie IDRG-MH-18314

Builder

  • NameOMVIMAL BUILTCON LLP
  • Entity typePartnership
  • PartnersGANESH NARAYAN PATIL, ASHOK MANILAL SHAH
  • PartnerSAHIL ASHOK SHAH

Key dates

this monthRegisteredJul 2024PromisedJul 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Jul 2024
  • Promised completion15 Jul 2028
  • Revised completionNone
  • Buildings5 building records
  • Documents filed67 files

Current status

2%3 of 131 units booked
57.7%Work done, per cost certificate

Figures as on 19 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RAMJANK CHSL WING ANA7714317
RAM JANKI CHS WING BNA7728230
RAM JANKI CHS WING CNA8828028
RAM JANKI CHS WING DNA8828028
RAM JANKI CHS WING ENA8828028

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 19 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 71%.

RAMJANK CHSL WING A25%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor50%
Slabs of Super Structure15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RAM JANKI CHS WING B48%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure71%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises28%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RAM JANKI CHS WING C56%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises42%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RAM JANKI CHS WING D56%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises42%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RAM JANKI CHS WING E56%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises42%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed129

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots129
Closed/Covered129
BuildingClosed/CoveredTotal
RAMJANK CHSL WING A1616
RAM JANKI CHS WING B2929
RAM JANKI CHS WING C2828
RAM JANKI CHS WING D2828
RAM JANKI CHS WING E2828

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,470 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
Declared on5 Jun 2025
LandownerVillageDistrict
RAMJANKI CHSLVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVVCMC
Permissible FSI6711.86
Proposed, not sanctioned6,712 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSTAR APARTMENT, S V ROAD, NEW BORIVALI POLICE STATION, OPP SBI, BORIVALI WEST 400092
Estimated costRs 17.70 cr
Cost incurredRs 10.21 cr
Work done57.67%
BuildingWingEstimatedIncurred
RAM JANKI CHS WING BNARs 4.19 crRs 1.51 cr
RAM JANKI CHS WING CNARs 3.27 crRs 2.62 cr
RAM JANKI CHS WING DNARs 2.81 crRs 2.25 cr
RAM JANKI CHS WING ENARs 2.81 crRs 2.25 cr
RAMJANK CHSL WING ANARs 2.63 crRs 78.77 lakh
-NARs 1.99 crRs 79.71 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNISHIT PATEL NUANCED
ArchitectNUANCED
EngineerDARSH CONSULT
EngineerPIYUSH JAYANTILAL GANDHI
Chartered AccountantJ J GANATRA & CO
Chartered AccountantJ.J.GANATRA & CO
Chartered AccountantSAMBHAV SHAH
PartnerRole in project
OMVIMAL BUILTCON LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Jul 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Jul 2028

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: FORM 2A 2024-25.pdf19 Aug 2026
Form 2A (FY 2025-2026)File: FORM 2A 2025-26.pdf19 Aug 2026
Withdrawal Update Form 1File: Architect Certificate Form 1.pdf28 Jul 2026
Withdrawal Update Form 2File: FORM-2.pdf28 Jul 2026
Withdrawal Update Form 3File: CA Certificate Form 3.pdf28 Jul 2026
Withdrawal Update Form 1File: Form 1 3rd Quater.pdf3 Jun 2026
Withdrawal Update Form 2File: Form 2 3rd Quater.pdf3 Jun 2026
Withdrawal Update Form 3File: Form 03.pdf3 Jun 2026
Withdrawal Update Form 1File: Form 1 3rd Quater.pdf30 Apr 2026
Withdrawal Update Form 2File: Form 2 3rd Quater.pdf30 Apr 2026
Withdrawal Update Form 3File: Form 3 3rd Quater.pdf30 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE FORM 1.pdf11 Mar 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE FORM 1.pdf11 Mar 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE FORM 1.pdf11 Mar 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE FORM 2 DATE 28-02-2026.pdf11 Mar 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE FORM 2 DATE 28-02-2026.pdf11 Mar 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE FORM 2 DATE 28-02-2026.pdf11 Mar 2026
Withdrawal Update Form 3File: CA CERTIFICATE FORM 3.pdf11 Mar 2026
Withdrawal Update Form 3File: CA CERTIFICATE FORM 3.pdf11 Mar 2026
Withdrawal Update Form 3File: CA CERTIFICATE FORM 3.pdf11 Mar 2026
Form 1File: ARCHITECT CERTIFICATE FORM -1.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: Inventory Disclosure.pdf27 Feb 2026
Form 2File: FORM 2.pdf27 Feb 2026
Form 3File: FORM 3.pdf27 Feb 2026
Form 1File: FORM 1.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY SOLD UNSOLD.pdf27 Feb 2026
Form 2File: FORM 2.pdf27 Feb 2026
Form 3File: FORM 3.pdf27 Feb 2026
Withdrawal Update Form 1File: FORM 1.pdf27 Feb 2026
Withdrawal Update Form 2File: FORM 2.pdf27 Feb 2026
Withdrawal Update Form 3File: FORM 3.pdf27 Feb 2026
Form 1File: Form 1 Architect Certificate.pdf18 Feb 2026
Form 2File: form 2 (engineer certificate) pdf.pdf18 Feb 2026
Form 3File: form 3 (CA certificate) pfd_compressed.pdf18 Feb 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure format pdf.pdf18 Feb 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: output (4) (1).pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf23 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 (CA certificate) pfd.pdf23 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 (engineer certificate) pdf.pdf23 Dec 2024
Disclosure of sold/ booked inventoryFile: inventory disclosure format pdf.pdf23 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_compressed.pdf25 Jul 2024
Proforma of Agreement for saleFile: 2024-06-29- MahaRERA - AFS_Omvimal Builtcon.pdf19 Jul 2024
Other - LegalFile: Declaration- Regarding CC.pdf19 Jul 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Letter- Agreement for Sale.pdf3 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INT.pdf2 Jul 2024
Other - LegalFile: LETTER OF ORDER NO 45 OF 2023.pdf2 Jul 2024
Copy of the legal title reportFile: TITLE CERTIFICATE 28-6-24.pdf1 Jul 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf18 Jun 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER 4-6-24_compressed.pdf18 Jun 2024
Other - LegalFile: LLP PARTNERSHIP DEED_compressed.pdf18 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 18-5-24.pdf22 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 21-5-24.pdf22 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Letter.pdf22 May 2024
Other - TechnicalFile: ANNEXURE A- DECLARATION CUM UNDERTAKING.pdf22 May 2024
Layout approvalFile: LAYOUT_compressed.pdf21 May 2024
Building plan approvalFile: BLDG PLAN_compressed_compressed.pdf21 May 2024
Details of encumbrances concerned to FinanceFile: LEGAL.pdf21 May 2024
Details of encumbrances concerned to LegalFile: LEGAL.pdf21 May 2024
Copy of Layout Approval (in case of layout)File: LAYOUT_compressed.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: BLDG PLAN_compressed_compressed.pdf21 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC COPY_compressed.pdf21 May 2024
CERSAI detailsFile: CERSAI.pdf21 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION ABOUT SEPRATE BANK ACCOUNT.pdf21 May 2024
Building plan approvalFile: NA.pdf17 May 2024
PAN CardFile: PAN CARD pdf.pdf17 May 2024
Building Plan Approval / NA Order for plotted developmentFile: NA.pdf17 May 2024
Declaration in FORM BFile: FORM B -Promoter_compressed.pdf17 May 2024

How this compares with Palghar

2%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIMAL'S RAMJANKI CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NILEMORE3,200+ in Palghar

2 kmVIMAL'S RAMJANKI CHSLCompleted 55Lapsed / revoked 47Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 222 registered projects within 2 km.

Builder: OMVIMAL BUILTCON LLP

OMVIMAL BUILTCON LLP has 1 registration on MahaRERA, including VIMAL'S RAMJANKI CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if VIMAL'S RAMJANKI CHSL is delayed beyond 15 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIMAL'S RAMJANKI CHSL?

The registered promoter entity is OMVIMAL BUILTCON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIMAL'S RAMJANKI CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIMAL'S RAMJANKI CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIMAL'S RAMJANKI CHSL?

The professionals named in the filing: Architect: NISHIT PATEL NUANCED; Architect: NUANCED; Engineer: DARSH CONSULT; Engineer: PIYUSH JAYANTILAL GANDHI; Chartered Accountant: J J GANATRA & CO; Chartered Accountant: J.J.GANATRA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIMAL'S RAMJANKI CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIMAL'S RAMJANKI CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIMAL'S RAMJANKI CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.