Home / Browse projects / Palghar, Maharashtra / VIMAL RESIDENCY
VIMAL RESIDENCY
RG-MH-58249 · RERA P99000011244 · Last updated on MahaRERA portal: 22 Apr 2025
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 59 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIMAL RESIDENCY is a Residential / Group Housing project by VIMAL DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000011244 on 31 Aug 2017. The registration is recorded completed; possession was promised by 16 Feb 2024. The completion date has moved by 59 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameVIMAL RESIDENCY
- TypeResidential / Group Housing
- Location
- VASAI ROAD
- NILEMORE
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401203
- Pincode401203
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000011244
- ReraGenie IDRG-MH-58249
Builder
- NameVIMAL DEVELOPERS
- Entity typePartnership
- PartnersBHARAT MANILAL SHAH, NIRAV BHARAT SHAH, SATISH PARMANAND SHAH, MILAN KANTILAL SHAH, FANCY P BAFNA, USHA ASHOK JAIN
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on31 Aug 2017
- Promised completion16 Feb 2024
- Revised completionRevised to 16 Feb 2024 (originally 15 Mar 2019)
- Buildings3 building records
- Documents filed50 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| VIMAL RESIDENCY A | NA | 12 | 0 | 0 | 0 | 0 |
| VIMAL RESIDENCY B | NA | 12 | 0 | 0 | 0 | 0 |
| VIMAL RESIDENCY C | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 22 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
31 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 98%.
VIMAL RESIDENCY A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
VIMAL RESIDENCY B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
VIMAL RESIDENCY C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Progress on shared amenities15
As on 22 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 98% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed26
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| VIMAL RESIDENCY A | 1 | 8 | 9 |
| VIMAL RESIDENCY B | 1 | 8 | 9 |
| VIMAL RESIDENCY C | 1 | 7 | 8 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANAT MEHTA & ASOCIATES |
| Partner | Role in project |
|---|---|
| VIMAL DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterENVIRONMENT PERMISSION IS PENDING FOR LAY OUT
Reason as filed by the promoterwe have completed the project and obtained OC for the project. we want a closure of the project under RERA so we have applied for back dated extension as informed to us by the authorities. we do not want any extension, since closure can happen only on the basis of extension upto OC date, so aacordingly we have applied for back dated extension. please grant us the extension so we can close the project
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000193187 | Chetan Pednekar | Bharat Shah | 27/06/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 10 Jun 2024
Documents filed50
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE 31-1-24 FORM I.pdf | 22 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 19-3-25.pdf | 22 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE 16-2-24.pdf | 5 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory disclosure (1).pdf | 26 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23 DATE - 21-3-25.pdf | 26 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-24- DATE- 21-3-25.pdf | 26 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory disclosure.pdf | 8 Mar 2025 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 8 Mar 2025 |
| CERSAI detailsFile: Cersai.pdf | 8 Mar 2025 |
| Declaration in FORM BFile: FORM B (5).pdf | 24 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 19-20.pdf | 24 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 20-21.pdf | 24 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 21-22.pdf | 24 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 22-23.pdf | 24 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 23-24.pdf | 24 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf | 12 Nov 2024 |
| OtherFile: CLOSURE OF PROJECT - VIMAL RESIDENCY_compressed.pdf | 18 Jun 2024 |
| Other - TechnicalFile: CLOSURE OF PROJECT - VIMAL RESIDENCY_compressed.pdf | 18 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 10 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 5 2020-21.pdf | 19 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 5 2021-22.pdf | 19 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 2020-21.pdf | 19 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 2021-22.pdf | 19 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 1 Feb 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Vimal Residency Society Formation Certificate.pdf | 6 Jul 2022 |
| OtherFile: Rera Extension Letter 14-9-21.pdf | 14 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: Vimal Residency A Wing_compressed.pdf | 14 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Vimal Residency B Wing_compressed.pdf | 14 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Vimal Residency C Wing_compressed.pdf | 14 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 13 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 01 vimal scan.pdf | 7 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 02 vimal scan.pdf | 7 Jul 2021 |
| Certificates of CA (Form 5)File: FORM 5 - VD.pdf | 4 Apr 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC COPY VD.pdf | 29 Mar 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY FORMATION.pdf | 29 Mar 2018 |
| OtherFile: NO CHANGE LETTER.pdf | 29 Mar 2018 |
| OtherFile: WAITING FOR OC.pdf | 29 Mar 2018 |
| OtherFile: WAITING FOR OC.pdf | 29 Mar 2018 |
| Building plan approvalFile: Blue Print Plan VD.pdf | 30 Aug 2017 |
| Layout approvalFile: Phase I Sec 3 Nilemore Layout.pdf | 30 Aug 2017 |
| Copy of the legal title reportFile: TITLE CLEARANCE CERTIFICATE VD (1).pdf | 30 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: Phase I Sec 3 Nilemore Layout.pdf | 30 Aug 2017 |
| Building Plan Approval (IOD)File: Blue Print Plan VD.pdf | 30 Aug 2017 |
| Declaration in FORM BFile: AFFIDIVATE VD.pdf | 30 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (2) (1).pdf | 30 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERING CERTIFICATE VD(NEW ).pdf | 30 Aug 2017 |
| Certificates of CA (Form 3)File: CA Certificate VD (1).pdf | 30 Aug 2017 |
| Proforma of Allotment letterFile: LETTER RERA VD.pdf | 30 Aug 2017 |
| PAN CardFile: S V D PAN CARD 001.pdf | 29 Aug 2017 |
| Details of encumbrancesFile: NIL.pdf | 29 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 50 filed documents as one ZIP, foldered, with a manifest
Keep VIMAL RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NILEMORE3,200+ in Palghar
Filed coordinates, straight-line distance. 224 registered projects within 2 km.
Sheetal Yash
DGS BUILDERS AND DEVELOPERS
DEEP SKYRISE
DEEP REALCON LLP
VIMAL CLASSIC
OM VIMAL DEVELOPERS
DHANANJAY HILL VIEW
DHANLAXMI DEVELOPERS
NAKSHATRA AURIS
RAJLAXMI JSB REALTY LLP
COMFORT HERITAGE
SAI RYDAM REAL ESTATE DEVELOPERS LLP
See every Palghar project, with the district possession charts
Builder: VIMAL DEVELOPERS
VIMAL DEVELOPERS has 1 registration on MahaRERA, including VIMAL RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if VIMAL RESIDENCY is delayed beyond 16 Feb 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIMAL RESIDENCY?
The registered promoter entity is VIMAL DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIMAL RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VIMAL RESIDENCY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VIMAL RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIMAL RESIDENCY?
The professionals named in the filing: Architect: SANAT MEHTA & ASOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIMAL RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback