ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Vikram Delite CHSL

Registered Litigation declared Residential / Group Housing project

Vikram Delite CHSL

By Shree Ramkrishn Enterprises

RG-MH-48223 · RERA P51800017268 · Last updated on MahaRERA portal: 24 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • Completion date moved by 84 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 84 months from the original
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
105 of 105Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

Vikram Delite CHSL is a Residential / Group Housing project by Shree Ramkrishn Enterprises in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800017268 on 27 Jul 2018. Possession is promised by 31 Dec 2028. The completion date has moved by 84 months from the original filing. 0 of the 105 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameVikram Delite CHSL
  • TypeResidential / Group Housing
  • Location
    • Behind Ramleela Ground
    • Maneklal
    • Ghatkoper (West)
    • Kurla
    • Mumbai Suburban
    • 400086
  • Pincode400086
  • RERA no.P51800017268
  • ReraGenie IDRG-MH-48223

Builder

  • NameShree Ramkrishn Enterprises
  • Entity typePartnership
  • PartnerPraveenkumar Uttamchand Miglani

Key dates

this monthRegisteredJul 2018First promiseDec 2021Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jul 2018
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed117 files

Current status

0%0 of 105 units booked
99.4%Work done, per cost certificate

Figures as on 24 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vikram ResidencyNA12101050105

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Vikram Residency: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed186

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots186
Closed/Covered178
Open Space8

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,590 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Aug 2026

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI8960.31
Proposed, not sanctioned2,197 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround and Mezzanine Floor, Botwala Chambers, 2, Sir P M Road, Fort, Mumbai - 400001
Estimated costRs 46.55 cr
Cost incurredRs 46.25 cr
Work done99.36%
BuildingWingEstimatedIncurred
Vikram ResidencyNARs 28.69 crRs 28.69 cr
-NARs 17.86 crRs 17.56 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVistar Architects
EngineerVedika Enterprises
EngineerMandeep Desai
Chartered AccountantShahnaz & co.
Chartered AccountantLalit R Mehta
PartnerRole in project
Shree Ramkrishn Enterprises-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017254Dec 2021 → Dec 2028

Reason as filed by the promoterDue to Navel Permission not being given Project is stuck

Litigation declared3

CaseCourtStatus
SL/413/2016/2016High CourtClosed
WP/3543/2018/2018High CourtClosed
SL/413/2016/2016Mumbai High CourtClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jul 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Aug 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: Further CC -8th Floor.pdf24 Aug 2026
Withdrawal Update Form 1File: Form 1 Q4 25-26 Vikram Delite.pdf24 Aug 2026
Withdrawal Update Form 1File: Form 1 Q1 26-27 Vikram Delite.pdf24 Aug 2026
Withdrawal Update Form 2File: FORM 2 Q4 25-26 Vikram Delite.pdf24 Aug 2026
Withdrawal Update Form 2File: FORM 2 Q1 26-27 Vikram Delite.pdf24 Aug 2026
Withdrawal Update Form 3File: Form 3 Q4 25-26 Vikram Delite New.pdf24 Aug 2026
Withdrawal Update Form 3File: Form 3 Q1 26-27 Vikram Delite.pdf24 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26 Vikram Delite.pdf24 Aug 2026
Form 1File: FORM-1 Q2 25-26.pdf4 Mar 2026
Form 2File: FORM-2 Q2 25-26.pdf4 Mar 2026
Form 3File: FORM-3 Q2 25-26.pdf4 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND BOOKED INVENTORY Q2 25-26.pdf4 Mar 2026
Form 1File: Form 1 Q3 25-26.pdf4 Mar 2026
Form 2File: Form 2 Q3 25-26.pdf4 Mar 2026
Form 3File: Form 3 Q3 25-26.pdf4 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND BOOKED INVENTORY Q3 25-26.pdf4 Mar 2026
Form 1File: Form 1 Q1 25-26.pdf29 Jan 2026
Form 2File: Form 2 Q1 25-26.pdf29 Jan 2026
Form 3File: Form 3 Q1 25-26 FINAL.pdf29 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked Q1 25-26 FINAL.pdf29 Jan 2026
Form 5 (FY 2024-2025)File: FORM-5 24-25.pdf7 Jan 2026
Form 1File: Form-1 Q4 24-25.pdf18 Jul 2025
Form 2File: Form-2 Q4 24-25.pdf18 Jul 2025
Form 3File: Form-3 Q4 24-25.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and unsold inventory Q4 24-25.pdf18 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf8 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q3 24-25.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q3 24-25.pdf3 Mar 2025
Certificates of CA (Form 3)File: Form 3 Q3 24-25.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Q3 24-25.pdf3 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold and booked inventory Q3 24-25.pdf3 Mar 2025
CERSAI detailsFile: Cersai declaration Q3 24-25.pdf3 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Q22425.pdf14 Nov 2024
Certificates of CA (Form 3)File: Form3Q22425.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Q22425.pdf14 Nov 2024
Disclosure of sold/ booked inventoryFile: InventoryQ22425.pdf14 Nov 2024
CERSAI detailsFile: CersaiQ22425.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Q12425.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Q12425.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: soldandbooked inventoryQ12425.pdf13 Aug 2024
CERSAI detailsFile: CersaiQ12425.pdf13 Aug 2024
Certificates of CA (Form 3)File: Form3Q12425.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate Q-4 -23-24.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineeers certificate Q-4-23-24.pdf21 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- Engineers certificate of quality compliance Q4-23-24.pdf21 May 2024
CERSAI detailsFile: Declaration for cersai Q4- 23-24.pdf21 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and booked inventory Q-4 -23-24.pdf21 May 2024
Certificates of CA (Form 3)File: Form-3 CA certificate Q-4-23-24.pdf21 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf21 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q 3 F Y 23-24.pdf23 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q 3 F Y 23-24.pdf23 Feb 2024
CERSAI detailsFile: Declaration for CERSAI q3 FY 23-24.pdf23 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and booked flat inventory Q 3 FY 23-24.pdf23 Feb 2024
Certificates of CA (Form 3)File: Form 3 Q3 f y 23-24_compressed.pdf23 Feb 2024
Certificates of CA (Form 3)File: SRE - FORM 3.pdf19 Dec 2023
Certificates of CA (Form 3)File: Form-3 IInd qtr -FY2023-24.pdf19 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Q-2 (23-24).pdf23 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineeers Certificate Q-2 (23-24).pdf23 Nov 2023
CERSAI detailsFile: cersai declaraton Q-2 (23-24).pdf23 Nov 2023
Disclosure of sold/ booked inventoryFile: sold and booked inventory Q-2 (23-24).pdf23 Nov 2023
Certificates of CA (Form 3)File: FORM 3-4qtr FY 2022-23.pdf8 Sep 2023
Certificates of CA (Form 3)File: Foam3 oct-22 to dec-22.pdf8 Sep 2023
Declaration in FORM BFile: FORM B.pdf23 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure B Q-1 2023-24.pdf23 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2023-06-30 Form 1Architect certificate vikram.pdf22 Aug 2023
CERSAI detailsFile: Declaration for CERSAI Q 1 (2023-24).pdf22 Aug 2023
Disclosure of sold/ booked inventoryFile: Q4 23-24 DISCLOSURE OF SOLD BOOKED INVENTORY.pdf22 Aug 2023
Disclosure of sold/ booked inventoryFile: Q1 23-24 DISCLOSURE OF SOLD BOOKED INVENTORY.pdf22 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4 22_23 Form 31032023.pdf19 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q4 22-23 Form -2 QTR 4 -310323.pdf19 Aug 2023
CERSAI detailsFile: Declaration for CERSAI 310323.pdf19 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 22-23.pdf17 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SRE - RERA FORM 5 - CA CERTIFICATE.pdf17 Aug 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY- SIGNED.pdf11 Aug 2023
Declaration about Commencement CertificateFile: Declaration about commencement certificate.pdf20 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: status of formation of legal entity.pdf20 Apr 2023
Status of ConveyanceFile: status of conveyance.pdf20 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SRE RERA FORM 5 FY 21-22.pdf4 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate (vedika) for rera purpose-310322.pdf16 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate (vedika) for rera purpose-300622.pdf16 Mar 2023

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 84 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vikram Delite CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Maneklal, Ghatkoper (West)6,700+ in Mumbai Suburban

Builder: Shree Ramkrishn Enterprises

Shree Ramkrishn Enterprises has 1 registration on MahaRERA, including Vikram Delite CHSL. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Vikram Delite CHSL is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vikram Delite CHSL?

The registered promoter entity is Shree Ramkrishn Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vikram Delite CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vikram Delite CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vikram Delite CHSL?

The professionals named in the filing: Architect: Vistar Architects; Engineer: Vedika Enterprises; Engineer: Mandeep Desai; Chartered Accountant: Shahnaz & co.; Chartered Accountant: Lalit R Mehta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vikram Delite CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vikram Delite CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vikram Delite CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.