Home / Browse projects / Mumbai Suburban, Maharashtra / VIJAYA HEIGHTS

Registered Litigation declared Residential / Group Housing project

VIJAYA HEIGHTS

By VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED

RG-MH-52880 · RERA P51800007143 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • Completion date moved by 88 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedmoved 88 months from the original
0 of 11Construction stages donefurthest along: Excavation, 0%
35 of 85Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

VIJAYA HEIGHTS is a Residential / Group Housing project by VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007143 on 17 Aug 2017. Possession is promised by 31 Dec 2030. The completion date has moved by 88 months from the original filing. 50 of the 85 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameVIJAYA HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • 472 PT
    • CHANDAVARKAR ROAD
    • -
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007143
  • ReraGenie IDRG-MH-52880

Builder

  • NameVIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorSANTUSH PANDURANG MANE
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseAug 2023Revised toDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2030
  • Revised completionRevised to 31 Dec 2030 (originally 28 Aug 2023)
  • Buildings1 building record
  • Documents filed74 files

Current status

59%50 of 85 units booked
20.5%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sale BuildingNA302277885

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Sale Building: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed176

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots176
Closed/Covered176

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,278 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2025

Approvals and building plan

Sanctioning authoritySLUM REHABILATION AUHTORITY
Permissible FSI10600.22
Proposed, not sanctioned10,600 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAGAR BAZAR DADAR WEST MUMBAI 400028
Estimated costRs 103.62 cr
Cost incurredRs 21.25 cr
Work done20.5%
BuildingWingEstimatedIncurred
Sale BuildingNARs 103.62 crRs 21.25 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSURESH GAIKAWAD
EngineerNILESH DIVEKAR
EngineerKRISHNAKUMAR LALJIBHAI GOHEL
Chartered AccountantCHANDRAKANT BAGAL AND ASSOCIATES
Chartered AccountantNehali & Co.
PartnerRole in project
VIGNAHARTA BUILDERS AND PROJECTS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017846Aug 2023 → Dec 2030

Reason as filed by the promoterThe construction activities were halted due to Work Stop Orders issued by the Hon’ble High Court on 13/01/2016 and 07/04/2017, thereby mandating suspension of all construction work pertaining to the said project. We need to construct Mamledar Office in C Wing of Phase III. Although we applied for the collectors permission in 2010 we received it on 2/08/2022. We were unable to proceed with construction until we received the necessary permissions from the government. The said Work Stop Orders were subsequently revoked by the Hon’ble High Court vide its Orders dated 18/10/2024 and 28/04/2025, the

Litigation declared3

CaseCourtStatus
134/2016BOMBAY HIGH COURTClosed
232/2017BOMBAY HIGH COURTClosed
SUIT (L) NO.232 OF 2017/2017IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTIONOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1.pdf20 Apr 2026
Withdrawal Update Form 2File: form 2.pdf20 Apr 2026
Withdrawal Update Form 3File: form 3.pdf20 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf23 Feb 2026
Layout approvalFile: Layout 1.pdf20 Feb 2026
Layout approvalFile: Plan - 4.pdf20 Feb 2026
Layout approvalFile: Plan - 9.pdf20 Feb 2026
Layout approvalFile: Plan 2-14.pdf20 Feb 2026
Form 2A (FY 2019-2020)File: FORM 2A 2019-20..pdf20 Feb 2026
Form 2A (FY 2020-2021)File: FORM 2A 2020-21..pdf20 Feb 2026
Form 2A (FY 2021-2022)File: FORM 2A 2021-22 ..pdf20 Feb 2026
Form 2A (FY 2023-2024)File: FORM 2A 2023-24..pdf20 Feb 2026
Form 2A (FY 2024-2025)File: FORM 2A 2024-25..pdf20 Feb 2026
Form 2A (FY 2022-2023)File: FORM 2A 2022-23..pdf20 Feb 2026
Withdrawal Update Form 1File: Form 1 - Dec 25.pdf22 Jan 2026
Withdrawal Update Form 2File: Form 2 - Dec 25.pdf22 Jan 2026
Withdrawal Update Form 3File: Form 3 - Dec 25.pdf22 Jan 2026
Withdrawal Update Form 1File: Form 1 - Dec 25.pdf21 Jan 2026
Withdrawal Update Form 2File: Form 2 - Dec 25.pdf21 Jan 2026
Withdrawal Update Form 3File: Form 3 - Dec 25.pdf21 Jan 2026
Form 1File: FORM 1 (Vighnaharta) 24-12-2025.pdf26 Dec 2025
Form 2File: engineer certificate 30-06-25.pdf26 Dec 2025
Form 3File: Resigned 16-12-25 CA Certificate vighnaharta June 25.pdf26 Dec 2025
Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD 30-06-2025.pdf26 Dec 2025
Form 1File: FORM 1.pdf26 Dec 2025
Form 2File: engineer certificate 30-09-25.pdf26 Dec 2025
Form 3File: Resigned 16-12-25 CA Certificate vighnaharta Sept 25.pdf26 Dec 2025
Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD 30-09-2026.pdf26 Dec 2025
Certificates of CA (Form 3)File: FORM 3 (1).pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: CA FORM 5 17-18.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA FORM 5 18-19.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA FORM 5 19-20.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA FORM 5 20-21.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - 2021-22.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 2022-23.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - 2023-24.pdf20 May 2025
Declaration in FORM BFile: Vighnaharta Affidavit B FORM NEW.pdf19 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE INVENTORY SOLD AND UNSOLD.pdf16 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf13 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf13 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf13 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf13 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf13 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf13 May 2025
Declaration about Commencement CertificateFile: CC declaration.pdf24 Mar 2025
CERSAI detailsFile: Cersai declaration.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA form 5 23-24.pdf24 Mar 2025
Building plan approvalFile: IOA.pdf10 Mar 2025
Copy of Layout Approval (in case of layout)File: output_1-4.pdf10 Mar 2025
Copy of Layout Approval (in case of layout)File: output_5-8.pdf10 Mar 2025
Copy of Layout Approval (in case of layout)File: output_9-11.pdf10 Mar 2025
Copy of Layout Approval (in case of layout)File: output_12-end.pdf10 Mar 2025
Building Plan Approval (IOD)File: IOA.pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: 11.pdf17 Nov 2023
Disclosure of sold/ booked inventoryFile: 123.pdf17 Nov 2023
Disclosure of sold/ booked inventoryFile: 1.pdf17 Nov 2023
Certificates of CA (Form 3)File: FORM 3,2023.pdf17 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: accountant certificate.pdf9 Nov 2023
Proforma of Agreement for saleFile: Agreement to be entered into between Pramoters and Allottees Final RERA.pdf9 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Eng Cert RERA.pdf25 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: VBPL Sale CC.pdf29 May 2018
Building plan approvalFile: IOD SALE BLDG.pdf31 Jul 2017
Layout approvalFile: LAYOUT Approval-10-MAY-2010.pdf31 Jul 2017
PAN CardFile: PAN CARD.pdf31 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf31 Jul 2017
Details of encumbrancesFile: Details of Encumbrances.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT Approval-10-MAY-2010.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD SALE BLDG.pdf31 Jul 2017
Declaration in FORM BFile: FORM B.PDF31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.PDF31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eNGINEER cERT.PDF31 Jul 2017
Certificates of CA (Form 3)File: CA CERT FORM 3.PDF31 Jul 2017
Proforma of Allotment letterFile: Agreement to be entered into between Pramoters and Allottees Final RERA.pdf31 Jul 2017

How this compares with Mumbai Suburban

59%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 88 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIJAYA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -6,700+ in Mumbai Suburban

2 kmVIJAYA HEIGHTSCompleted 33Lapsed / revoked 19Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED

VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED has 2 registrations on MahaRERA, including VIJAYA HEIGHTS and MODERN ENCLAVE. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VIJAYA HEIGHTS is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIJAYA HEIGHTS?

The registered promoter entity is VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIJAYA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIJAYA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIJAYA HEIGHTS?

The professionals named in the filing: Architect: SURESH GAIKAWAD; Engineer: NILESH DIVEKAR; Engineer: KRISHNAKUMAR LALJIBHAI GOHEL; Chartered Accountant: CHANDRAKANT BAGAL AND ASSOCIATES; Chartered Accountant: Nehali & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIJAYA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIJAYA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIJAYA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.