Home / Browse projects / Mumbai Suburban, Maharashtra / VIJAY LENYADRI CHS LTD

Registration lapsed No litigation declared Residential / Group Housing project

VIJAY LENYADRI CHS LTD

By S D BHALERAO CONSTRUCTIONS PVT LTD

RG-MH-01675 · RERA P51800007212 · Last updated on MahaRERA portal: 8 Sep 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 6 complaints at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 75%
6Complaints at MahaRERAon this registration
Jump to the 26 documents Report an error

VIJAY LENYADRI CHS LTD is a Residential / Group Housing project by S D BHALERAO CONSTRUCTIONS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007212 on 17 Aug 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 48 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameVIJAY LENYADRI CHS LTD
  • TypeResidential / Group Housing
  • Location
    • Sambar Road
    • Nehru Nagar
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007212
  • ReraGenie IDRG-MH-01675

Builder

  • NameS D BHALERAO CONSTRUCTIONS PVT LTD
  • Entity typeCompany
  • DirectorsSanjay Dattatray Bhalerao, Pratima Sanjay Bhalerao
  • Other registrations4 more →
  • Completed2 of 5
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed26 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VIJAY LENYADRINA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.

VIJAY LENYADRI: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area798 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3792.41
Proposed, not sanctioned3,164 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAkruti SMC, Near MSRTC Bus Depot, Khopat, Thane West

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEllora Project Consultants Pvt Ltd
EngineerAssociated Consultants
PartnerRole in project
S D BHALERAO CONSTRUCTIONS PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005149Dec 2019 → Dec 2020

Reason as filed by the promoterWe also wish to inform you following facts:- 1) IOD received on 01/10/2010. 2) Commencement Certificate received at various stages as detailed below: i. upto plinth on 23/12/2010 ii. upto 8th floor on 27/05/2013 iii. upto 12th floor on 12/05/2016 3) 60% work completed upto 11th floor on April-2018. The Vijay Lenyadri CHS Ltd. (said Society) had issued us termination notice dated 04/05/2018 through their Advocate Mr. Sumit Kothari. We raised the objection through our Advocate Mr. Vibhav Krishna of Juris Consillis. The Hon’able Justice G. S. Kulkarni has referred the matter to Arbitrator Mr. San

EXT51800010228Dec 2019 → Dec 2023

Reason as filed by the promoterIn continuation of negotiations with the existing Society Tenants/Members, we have ultimately resolved the dispute / litigation with the existing Society and executed the revised Consent Terms on 20/02/2020. Accordingly, we have restarted the construction activities under the Commencement Certificate No. CE/4346/BPES/AL dated 12/05/2016 issued by MCGM. Now the further approvals shall have to be obtained from MHADA as the approval Authority has been from MCGM to MHADA. Therefore, we will have to obtain all number of NOCs from various Departments as on current date as per the requirement of MHAD

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000141199Amey Suhas ManjrekarSanjay Dattatray Bhalerao03/12/2019
CC006000000192275Vaishali Sharad KatkarS D Bhalerao Construction Pvt Ltd24/01/2020
CC12400777Aadesh Murlidhar ChandurkarA B CONTRACTOR AND DEVELOPERS14/11/2024
CC12400841David Bandu AwaleS D BHALERAO CONSTRUCTIONS PVT LTD21/11/2024
CC12401148Arvind Narayan BhaleraoA B CONTRACTOR AND DEVELOPERS17/12/2024
CC12401150Pranoti Rajendra DateS D BHALERAO CONSTRUCTIONS PVT LTD17/12/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed26

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to LegalFile: Encumbrance for legal NN-63.pdf8 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Bank account.pdf8 Sep 2022
Deviation Report with respect to Allotment letterFile: Deviation report for Agreement NN-63.pdf8 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Deviation report for Agreement NN-63.pdf8 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A FY 2019-2020 NN-63.pdf7 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A FY 2020-2021 NN-63.pdf7 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 FY 2017-18 NN-63.pdf7 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-2019 NN-63.pdf7 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-2020 NN-63.pdf7 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-2021 NN-63.pdf7 Sep 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure Sold unsold NN-63.pdf20 Jul 2021
OtherFile: Declaration for update.pdf13 Nov 2017
Layout approvalFile: Declaration for layout.pdf27 Jul 2017
Details of encumbrancesFile: Encumbrances.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Declaration for layout.pdf27 Jul 2017
Declaration in FORM BFile: Affidavit.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 63.pdf27 Jul 2017
Certificates of CA (Form 3)File: Certificates of C A.pdf27 Jul 2017
Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale.pdf27 Jul 2017
Building plan approvalFile: Approval Plan.pdf16 Jul 2017
Copy of the legal title reportFile: Title Report.pdf16 Jul 2017
Building Plan Approval (IOD)File: Approval Plan.pdf16 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf16 Jul 2017
PAN CardFile: PAN.pdf2 Jun 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
PADMAVATI NAGARI BLDG 1 Wing C and DGut No 162 Village Pimpri Saddroddin Taluka Igatpuri Dist Nashik30CompletedDec 2013Late, Nov 2015
LAHOTI HOUSERaghoba Shankar Path Chendani Thane west38CompletedDec 2013Late, Feb 2014

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIJAY LENYADRI CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nehru Nagar6,700+ in Mumbai Suburban

2 kmVIJAY LENYADRI CHS LTDCompleted 116Lapsed / revoked 98Other 155Dot size: filed unitsN

Filed coordinates, straight-line distance. 369 registered projects within 2 km.

Builder: S D BHALERAO CONSTRUCTIONS PVT LTD

S D BHALERAO CONSTRUCTIONS PVT LTD has 5 registrations on MahaRERA, including PADMAVATI NAGARI BLDG NO 1 A and B wing and VIJAY LENYADRI CHS LTD. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VIJAY LENYADRI CHS LTD shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VIJAY LENYADRI CHS LTD is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIJAY LENYADRI CHS LTD?

The registered promoter entity is S D BHALERAO CONSTRUCTIONS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIJAY LENYADRI CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VIJAY LENYADRI CHS LTD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VIJAY LENYADRI CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIJAY LENYADRI CHS LTD?

The professionals named in the filing: Architect: Ellora Project Consultants Pvt Ltd; Engineer: Associated Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIJAY LENYADRI CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIJAY LENYADRI CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIJAY LENYADRI CHS LTD to a free account