Red flags

  • Completion date moved by 73 months, 4 of them under MahaRERA's automatic 4-month extension
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Apr 2029Possession promisedmoved 73 months from the original
16 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 85%
43 of 128Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

VIJAY ABODE is a Residential / Group Housing project by VIJAYBAHADUR SHIVMURAT SHARMA in Raigarh, Maharashtra, registered with MahaRERA as P52000020728 on 7 May 2019. Possession is promised by 30 Apr 2029. The completion date has moved by 73 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 85 of the 128 units on this registration are recorded sold or booked, and 16 of 44 construction stages are filed complete.

At a glance

Project

  • NameVIJAY ABODE
  • TypeResidential / Group Housing
  • Location
    • NEAR ST. GEORGE SCHOOL AT POST ADAI
    • PLOT NO 123 135 137 138 ADAI
    • Adai
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000020728
  • ReraGenie IDRG-MH-03154

Builder

  • NameVIJAYBAHADUR SHIVMURAT SHARMA
  • Entity typeIndividual
  • Declared earlier projects3 →

Key dates

this monthRegisteredMay 2019First promiseMar 2023Revised toApr 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 May 2019
  • Promised completion30 Apr 2029
  • Revised completionRevised to 30 Apr 2029 (originally 30 Mar 2023)
  • Buildings4 building records
  • Documents filed126 files

Current status

66%85 of 128 units booked
97.6%Work done, per cost certificate

Figures as on 5 Nov 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 2 - Wing A and Wing BNA5432032
Building 3 - Wing A and Wing BNA5432032
BUILDING 4 - Wing A and Wing BNA5432032
BUILDING 5 - Wing A and Wing BNA5432032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 5 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 85%.

Building 2 - Wing A and Wing B65%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Building 3 - Wing A and Wing B65%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
BUILDING 4 - Wing A and Wing B65%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
BUILDING 5 - Wing A and Wing B65%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 5 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed109

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots109
Closed/Covered109
BuildingClosed/CoveredTotal
Building 2 - Wing A and Wing B2828
Building 3 - Wing A and Wing B2525
BUILDING 4 - Wing A and Wing B2828
BUILDING 5 - Wing A and Wing B2828

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,870 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityThe City and Industrial Development Corporation of Maharashtra Limited
Permissible FSI4861.64
Proposed, not sanctioned4,862 sq m
Buildings approved6
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVashi Branch, 75, Vardhaman Market Sector 17, Navi Mumbai -400703
Estimated costRs 10.01 cr
Cost incurredRs 9.77 cr
Work done97.59%
BuildingWingEstimatedIncurred
Building 2 - Wing A and Wing BNARs 2.32 crRs 2.32 cr
Building 3 - Wing A and Wing BNARs 2.32 crRs 2.32 cr
BUILDING 4 - Wing A and Wing BNARs 2.32 crRs 2.32 cr
BUILDING 5 - Wing A and Wing BNARs 2.32 crRs 2.32 cr
-NARs 73.27 lakhRs 49.09 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSheetal Architects
EngineerAman Gupta
EngineerS K Consultants & Engineers
Chartered AccountantParth Gada
Chartered AccountantDattatray & Associates
Chartered AccountantRutuja Narsingh & Associates
PartnerRole in project
VIJAYBAHADUR SHIVMURAT SHARMA-

Extensions3

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Dec 2028 → Apr 2029

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EXT52000015193Mar 2023 → Mar 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19

EXT52000019166Mar 2023 → Dec 2028

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 66.67% allottees for purpose of extension of RERA registration period of the said project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Nov 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Nov 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2029

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Page 1 - Layout Plan (Highlighted) (Sanctioned and Permissible) (Parking).pdf5 Nov 2026
Building plan approvalFile: Page 2.pdf5 Nov 2026
Building plan approvalFile: Page 4 - Building 2 (Floor Plans) and Elevation.pdf5 Nov 2026
Building plan approvalFile: Page 5 - Building 3 (Floor Plans) and Elevation.pdf5 Nov 2026
Building plan approvalFile: Page 6 - Building 4 (Floor Plans) and Elevation.pdf5 Nov 2026
Building plan approvalFile: Page 7 - Building 5 (Floor Plans) and Elevation.pdf5 Nov 2026
Withdrawal Update Form 1File: Form 1 - Vijay Abode Sep 2026.pdf29 Oct 2026
Withdrawal Update Form 2File: Form 2 - Vijay Abode Sep 2026_compressed.pdf29 Oct 2026
Withdrawal Update Form 3File: Form 3 - Vijay Abode Sep 2026.pdf29 Oct 2026
Form 2A (FY 2025-2026)File: Form 2A 2025-2026.pdf17 Oct 2026
Form 5 (FY 2025-2026)File: Form 5 - FY 2025-2026 (Signed).pdf17 Oct 2026
Form 5 (FY 2024-2025)File: Form 5 - Vijay Abode FY 2024-25.pdf18 Sep 2026
Form 1File: Form 1 - Vijay Abode as on June 2025.pdf11 Sep 2026
Form 1File: Form 1 - Vijay Abode as on Sep 2025.pdf11 Sep 2026
Form 1File: Form 1 - Vijay Abode as on Dec 2025.pdf11 Sep 2026
Form 1File: Form 1 - Vijay Abode June 2026_compressed.pdf11 Sep 2026
Form 2File: Form 2 - Vijay Abode as on June 2025.pdf11 Sep 2026
Form 2File: Form 2 - Vijay Abode as on Sep 2025.pdf11 Sep 2026
Form 2File: Form 2 - Vijay Abode as on Dec 2025.pdf11 Sep 2026
Form 2File: Form 2 - Vijay Abode June 2026.pdf11 Sep 2026
Form 3File: Form 3 - Vijay Abode as on June 2025.pdf11 Sep 2026
Form 3File: Form 3 - Vijay Abode as on Sep 2025.pdf11 Sep 2026
Form 3File: Form 3 - Vijay Abode as on Dec 2025.pdf11 Sep 2026
Form 3File: Form 3 - Vijay Abode June 2026.pdf11 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular-29 Vijay Abode as on Dec 2025.pdf11 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular-29- Vijay Abode as on Sep 2025.pdf11 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Vijay Abode as on Dec 2025.pdf11 Sep 2026
Disclosure of Sold and Booked InventoryFile: Circular-29- Vijay Abode June 2026.pdf11 Sep 2026
Form 1File: Form 1 - Vijay Abode June 2026.pdf28 Jul 2026
Form 2File: Form 2 - Vijay Abode June 2026.pdf28 Jul 2026
Form 3File: Form 3 - Vijay Abode June 2026.pdf28 Jul 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Vijay Abode June 2026.pdf28 Jul 2026
Certificates of CA (Form 3)File: Form 3 - Vijay Abode as on June 2024.pdf27 Mar 2025
Certificates of CA (Form 3)File: Form 3 - Vijay Abode as on Sep 2024.pdf27 Mar 2025
Certificates of CA (Form 3)File: Form 3 - Vijay Abode as on Dec 2024.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Abode as on June 2024.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Abode as on Sep 2024.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Abode as on Dec 2024.pdf27 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Vijay Abode FY 2023-24.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf17 Feb 2025
Certificates of CA (Form 3)File: 14 Certificates of CA (Form 3).pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf20 Jul 2024
Certificates of CA (Form 3)File: rrrrrrrrrr.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Architects Certificate of Percentage of Completion of Work (Form 1) (1).pdf16 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Abode as on March 2024.pdf16 May 2024
Certificates of CA (Form 3)File: Form 3 - Vijay Abode as on March 2024.pdf16 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijay Abode Form 1 As on 31st December 2023_11zon.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: Circular 29_11zon.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf4 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate From 2_11zon.pdf19 Feb 2024
Certificates of CA (Form 3)File: From 3_11zon.pdf19 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Vijay Abode as on September 2023.pdf16 Feb 2024
Certificates of CA (Form 3)File: Form 3 - Vijay Abode as on Sep 2023.pdf16 Feb 2024
Declaration in FORM BFile: Affidavit cum Declaration.pdf14 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec.pdf14 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A 22-23.pdf14 Feb 2024
CERSAI detailsFile: Cersai Declaration.pdf14 Feb 2024
Disclosure of sold/ booked inventoryFile: Circular 29_11zon.pdf14 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf14 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: From 5 22-23.pdf14 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf14 Feb 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society.pdf10 Jan 2024
Status of ConveyanceFile: Conveyance.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Vijay Abode for FY 2022-23.pdf26 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Vijay Abode as on June 2023.pdf3 Aug 2023
Certificates of CA (Form 3)File: Form 3- Vijay Abode as on 30-06-2023.pdf3 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Vijay Abode as on March 2023.pdf6 May 2023
Certificates of CA (Form 3)File: Form 3- Vijay Abode as on 31-03-2023.pdf6 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Year of 19-20.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Year Of 20-2021.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Year Of 21-2022.pdf31 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijay Abode Form 1 - Mar 20.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijay Abode Form 1 - Mar 21.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijay Abode Form 1 - Dec 21.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijay Abode Form 1 - Jun 22.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijay Abode Form 1 - Sept 22.pdf29 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vijay Abode Form 1 - Dec 22.pdf29 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vijay Abode Mar 2020 - Form 2.pdf17 Mar 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ASHAPURA APARTMENTSPLOT NO 295 SEC 17 ULWE46CompletedAug 2015Aug 2015
DEEPAK APARTMENTSECTOR 17 ULWE9CompletedApr 2014Apr 2014
VIJAYDEEP APPARTMENTSSECTOR 29 RABALE GHANSOLI NAVI MUMBAI53CompletedApr 2009Apr 2009

How this compares with Raigarh

66%of this project is bookeddistrict median 28%
21%of Raigarh projects moved their completion datethis one moved by 73 months
25%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIJAY ABODE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PLOT NO 123 135 137 138 ADAI5,900+ in Raigarh

2 kmVIJAY ABODECompleted 47Lapsed / revoked 14Other 59Dot size: filed unitsN

Filed coordinates, straight-line distance. 120 registered projects within 2 km.

Builder: VIJAYBAHADUR SHIVMURAT SHARMA

VIJAYBAHADUR SHIVMURAT SHARMA has 1 registration on MahaRERA, including VIJAY ABODE. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if VIJAY ABODE is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIJAY ABODE?

The registered promoter entity is VIJAYBAHADUR SHIVMURAT SHARMA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIJAY ABODE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIJAY ABODE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIJAY ABODE?

The professionals named in the filing: Architect: Sheetal Architects; Engineer: Aman Gupta; Engineer: S K Consultants & Engineers; Chartered Accountant: Parth Gada; Chartered Accountant: Dattatray & Associates; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIJAY ABODE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIJAY ABODE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIJAY ABODE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.