Home / Browse projects / Mumbai Suburban, Maharashtra / VICTORY PLATINUM

Registration lapsed No litigation declared Others project

VICTORY PLATINUM

By PRASHANTI LAND DEVELOPERS PRIVATE LIMITED

RG-MH-48555 · RERA P51800008591 · Last updated on MahaRERA portal: 24 Aug 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 82 months past the filed date
  • 23 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2019Possession promised82 months past this date
21 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
23Complaints at MahaRERAon this registration
Jump to the 18 documents Report an error

VICTORY PLATINUM is a Others project by PRASHANTI LAND DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008591 on 19 Aug 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date. The completion date has moved by 12 months from the original filing. 23 complaints are on record with the regulator.

At a glance

Project

  • NameVICTORY PLATINUM
  • TypeOthers
  • Location
    • Greater Mumbai (M Corp.) (Part) (802794)
    • Mumbai
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008591
  • ReraGenie IDRG-MH-48555

Builder

  • NamePRASHANTI LAND DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorHIMANSHU NARENDRA SHAH
  • Declared earlier projects1 →

Key dates

82 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings3 building records
  • Documents filed18 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JINKU CHS LTD A WINGNA230000
JINKU CHS LTD B WINGNA210000
JINKU CHS LTD C WINGNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Aug 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

JINKU CHS LTD A WING97%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
JINKU CHS LTD B WING78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
JINKU CHS LTD C WING78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities16

As on 24 Aug 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
SUBSTATIONYes100%

Parking filed114

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots114
Open Space114
BuildingOpen SpaceTotal
JINKU CHS LTD A WING4242
JINKU CHS LTD B WING3030
JINKU CHS LTD C WING4242

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,302 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6964.0
Proposed, not sanctioned5,332 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBAI-BORIVALI WEST

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIQBAL NITIN & ASSOCIATES
EngineerFURKAN PETTIWALA
Chartered AccountantPatel Palkar & Associates LLP
Chartered AccountantBaser & Associates
PartnerRole in project
PRASHANTI LAND DEVELOPERS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000824Dec 2018 → Dec 2019

Reason as filed by the promoterFINISHING WORK IS PENDING DETAILED FACTS, REASONS AND PRAYER IS ATTACHED UNDER OTHER TAB

Litigation declared2

CaseCourtStatus
2200/2016CITY CIVIL COURT DINDOSHISUIT ONGOING
936/2016HIGH COURT OF JUDICATURE OF BOMBAYCLOSED

Complaints filed with MahaRERA23

Case no.ComplainantRespondentFiled
CC006000000182019Mrs. Vijayshree Ajay PandyaHimanshu Shah - Prahsanti Lan Developers Pvt Ltd31/12/2019
CC006000000194711Hinduja Leyland Finance LtdPrashanti land Developers Pvt Ltd04/11/2020
CC006000000195530SAMIR MANSUKH SANGOIPrashanti Land Developers Private Limited15/01/2021
CC006000000195746SHAILESH HIMMATLAL SHUKLA & REENA SHAILESH SHUKLAPRASHANTI LAND DEVELOPERS PRIVATE LIMITED25/01/2021
CC006000000195921PANKAJ S. VIRA/ASHA P. VIRA/CHIRAG P. VIRAPRASHANTI LAND DEVELOPERS PRIVATE LIMITED07/02/2021
CC006000000195927LEEPA/JATIN/JAIMIN MEHTAPRASHANTI LAND DEVELOPERS PVT. LTD.07/02/2021
CC006000000195920Ajay Hasmukh VastaniPrashanti Land Developers Private Limited07/02/2021
CC006000000195923MEERA KETAN DHAKANPRASHANTI LAND DEVELOPERS PRIVATE LIMITED07/02/2021
CC006000000195924Hitesh Rasiklal KadakiaPrashanti Land Developers Private Limited07/02/2021
CC006000000195926KETAN VINOD DHAKANPRASHANTI LAND DEVELOPERS PRIVATE LIMITED07/02/2021
CC006000000195928DHIRENDRA HARKISANDAS SHAHPRASHANTI LAND DEVELOPERS PRIVATE LIMITED07/02/2021
CC006000000195929Saumil Rohit KadakiaPrashanti Land Developers Private Limited07/02/2021
CC006000000196021Sandhya Prakash UnadkatPrashanti Land Developers Private Limited14/02/2021
CC006000000196026NILESH BHAVARLAL CHOPRA/BHAVARLAL S CHOPDA/PUSHPA B CHOPDAPRASHANTI LAND DEVELOPERS PRIVATE LIMITED14/02/2021
CC006000000196023ARTI PINAKIN SHUKLA/PINAKIN SHUKLAPRASHANTI LAND DEVELOPERS PVT LTD14/02/2021
CC006000000196027Pavan Navinchandra LakhaniPrashanti Land Developers Private Limited14/02/2021
CC006000000196025GEETA MAHENDRA JAIN/MAHENDRA J. JAIN/KINNARI M. JAINPRASHANTI LAND DEVELOPERS PRIVATE LIMITED14/02/2021
CC006000000196113MANISH VIPIN DESAI/BAKULA BHARAT SHAH/HETAL MANISH DESAIPRASHANTI LAND DEVELOPERS PRIVATE LIMITED21/02/2021
CC006000000196380ALOK SHAHPrashanti land developers Pvt ltd17/03/2021
CC006000000196583VICTORY PLATINUM B WING ALLOTTEES ASSOCIATIONPRASHANTI LAND DEVELOPERS PRIVATE LIMITED01/04/2021
CC006000000210040JIGNA PARESH SHAHPRASHANTI LAND DEVELOPERS PVT. LTD.17/02/2022
CC006000000303389ARHAM GLOBAL SERVICES LLPGEETA MAHENDRA JAIN21/11/2022
CC12501961Rajyog CorporationsPRASHANTI LAND DEVELOPERS PRIVATE LIMITED16/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed18

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrancesFile: RERA LETTER FROM PLDPL.pdf24 Aug 2019
Proforma of Allotment letterFile: PDF Rera Agreement.pdf11 Sep 2017
Layout approvalFile: Jinku Layout.pdf31 Jul 2017
Details of encumbrancesFile: Litigation Declaration.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Jinku Layout.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3 Jinku.pdf31 Jul 2017
OtherFile: Car Parking-Jinku.pdf31 Jul 2017
Building plan approvalFile: 10 IOD.pdf30 Jul 2017
PAN CardFile: PAN.pdf30 Jul 2017
Copy of the legal title reportFile: 1 TITLE Report.pdf30 Jul 2017
Details of encumbrancesFile: 2 Encumbrance.pdf30 Jul 2017
Building Plan Approval (IOD)File: 10 IOD.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 9 CC.pdf30 Jul 2017
Declaration in FORM BFile: 5 Form B Affidavit.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 Certificate of Architect.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Certificate of Engineer.pdf30 Jul 2017
Proforma of Allotment letterFile: 3 Allotment letter JINKU.pdf30 Jul 2017
Proforma of Allotment letterFile: 4 Agreement for Sale Declaration.pdf30 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VICTORY ELEGENCE MANISHAKASTUR PARK PLOT NO 29 SHIMPOLI ROAD BORIVALI WEST MUMBAI 40009226CompletedJan 2015Late, Jun 2016

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VICTORY PLATINUM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Greater Mumbai (M Corp.) (Part) (802794)6,700+ in Mumbai Suburban

2 kmVICTORY PLATINUMCompleted 118Lapsed / revoked 68Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 321 registered projects within 2 km.

Builder: PRASHANTI LAND DEVELOPERS PRIVATE LIMITED

PRASHANTI LAND DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including VICTORY PLATINUM. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that VICTORY PLATINUM shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VICTORY PLATINUM is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VICTORY PLATINUM?

The registered promoter entity is PRASHANTI LAND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VICTORY PLATINUM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VICTORY PLATINUM?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VICTORY PLATINUM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VICTORY PLATINUM?

The professionals named in the filing: Architect: IQBAL NITIN & ASSOCIATES; Engineer: FURKAN PETTIWALA; Chartered Accountant: Patel Palkar & Associates LLP; Chartered Accountant: Baser & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VICTORY PLATINUM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VICTORY PLATINUM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VICTORY PLATINUM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.