Home / Browse projects / Pune, Maharashtra / Vedant Phase 1

Registration lapsed No litigation declared Residential / Group Housing project

Vedant Phase 1

By EXCEL HOMES VENTURES

RG-MH-24317 · RERA P52100011359 · Last updated on MahaRERA portal: 7 May 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
2 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 70%
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

Vedant Phase 1 is a Residential / Group Housing project by EXCEL HOMES VENTURES in Pune, Maharashtra, registered with MahaRERA as P52100011359 on 31 Aug 2017. Possession was promised by 31 Dec 2022 and is now 46 months past that date. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameVedant Phase 1
  • TypeResidential / Group Housing
  • Location
    • KIRKATWADI
    • Haveli
    • Pune
    • 411024
  • Pincode411024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011359
  • ReraGenie IDRG-MH-24317

Builder

  • NameEXCEL HOMES VENTURES
  • Entity typePartnership
  • Partnersgaurav satish Kenjale, Akshay Dattatray Ranpise, vinit shashikant golande, Nikhil chandrashekhar athwale, Sagar uttamrao khude, Abhishekh kantilal pardeshi

Key dates

46 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 30 Dec 2019)
  • Buildings3 building records
  • Documents filed24 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CNA50000
DNA50000
ENA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 70%.

C22%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth70%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E12%
ActivityProgress
Excavation100%
Basement (if any)15%
Podiums (if any)0%
Plinth15%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed48

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots48
Closed/Covered48
BuildingClosed/CoveredTotal
C1616
D1616
E1616

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Namdeo Tukaram KaranjawaneKIRKATWADIPune
Rajendra Tukaram KaranjawaneKIRKATWADIPune
Nivrutti Sakharam KaranjawaneKIRKATWADIPune

Approvals and building plan

Permissible FSI4077.58
Proposed, not sanctioned4,078 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBibwewadi kondhwa Pune

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectWalhekar and Associates
PartnerRole in project
EXCEL HOMES VENTURES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005919Dec 2019 → Dec 2020

Reason as filed by the promoterReasons for delay 1). Real Estate industry in India is still labor intensive. And there was an acute shortage in labor supply for 2-3 months due to general election for Lok Sabha in 2019. 2). Due to shortage of drinking water in the summer of 2019, there was a city wise ban on use of water for construction purpose by civic bodies. Hence the whole construction activity came to a standstill for a couple of months. 3). Also due to heavy rainfall in Maharashtra during monsoon brought a flood like situation in the city. Kirkitwadi, location where the project is situated was severely affected by sam

EXT52100011476Dec 2019 → Dec 2022

Reason as filed by the promoterDue to after effect of COVID pandemic, labor force, necessary for carrying out construction activity, still havent returned back to active duty from their native places. With the current gradual restarting of economy, developer is confident to complete remaining work within next twelve months. After communicating the same to stake holders even they are of the opinion that an extension of twelve months would be in interest of all parties involved.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: sold Booked Inventory v1.pdf7 May 2022
CERSAI detailsFile: CERSAI Search Report 04052022.pdf7 May 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement-compressed.pdf2 May 2022
Declaration about Commencement CertificateFile: Declaration About Commencement.pdf30 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf30 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf30 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf30 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 RERA Audit FY 2018-19.pdf30 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 RERA Audit FY 2019-20.pdf30 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 RERA Audit FY 2020-21.pdf30 Apr 2022
Certificates of CA (Form 5)File: Vedant Phase I Form 5.pdf30 Sep 2018
Layout approvalFile: VEDANT SANCTION PLAN.pdf31 Jul 2017
Building plan approvalFile: VEDANT SANCTION PLAN.pdf31 Jul 2017
PAN CardFile: Ventures Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: serch title report kirkatwadi 1.pdf31 Jul 2017
Details of encumbrancesFile: NO Encumbrance Certificate.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: VEDANT SANCTION PLAN.pdf31 Jul 2017
Building Plan Approval (IOD)File: VEDANT SANCTION PLAN.pdf31 Jul 2017
Declaration in FORM BFile: Form B AFFIDIVATE.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture Certificate Vedant.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Vedant.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate 1.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certificate 1 2.pdf31 Jul 2017
Proforma of Allotment letterFile: Vedant Sale Agreement Draft FINAL.pdf31 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vedant Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KIRKATWADI13,700+ in Pune

Builder: EXCEL HOMES VENTURES

EXCEL HOMES VENTURES has 1 registration on MahaRERA, including Vedant Phase 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Vedant Phase 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Vedant Phase 1 is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vedant Phase 1?

The registered promoter entity is EXCEL HOMES VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vedant Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Vedant Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vedant Phase 1?

The professionals named in the filing: Architect: Walhekar and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vedant Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vedant Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vedant Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.