Home / Browse projects / Thane, Maharashtra / Vedant Millenia Happiness Phase II Wing E

Registered No litigation declared Residential / Group Housing project

Vedant Millenia Happiness Phase II Wing E

By MOHAN HARDASMAL THARWANI

RG-MH-58508 · RERA P51700047571 · Last updated on MahaRERA portal: 7 Aug 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 36 months from the original
0 of 11Construction stages donefurthest along: Excavation, 0%
55 of 55Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

Vedant Millenia Happiness Phase II Wing E is a Residential / Group Housing project by MOHAN HARDASMAL THARWANI in Thane, Maharashtra, registered with MahaRERA as P51700047571 on 9 Nov 2022. Possession is promised by 31 Dec 2029. The completion date has moved by 36 months from the original filing. 0 of the 55 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameVedant Millenia Happiness Phase II Wing E
  • TypeResidential / Group Housing
  • Location
    • BEHIND MAHA GANPATI MANDIR
    • TITWALA (EAST)
    • Titwala
    • Kalyan
    • Thane
    • 421605
  • Pincode421605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700047571
  • ReraGenie IDRG-MH-58508

Builder

  • NameMOHAN HARDASMAL THARWANI
  • Entity typeIndividual
  • GSTIN27AAOPT7033Q1ZQ
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations18 more →
  • Completed10 of 19
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredNov 2022First promiseDec 2026Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Nov 2022
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2026)
  • Buildings1 building record
  • Documents filed94 files

Current status

0%0 of 55 units booked
0.0%Work done, per cost certificate

Figures as on 7 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vedant Millenia Happiness Phase II Wing ENA8755055

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Vedant Millenia Happiness Phase II Wing E: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed42

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots42
Closed/Covered42

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area858 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Aug 2025

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal Corporation
Permissible FSI791.38
Proposed, not sanctioned791 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchULHASNAGAR-421002
Estimated costRs 9.26 cr
Work done0.0%
BuildingWingEstimatedIncurred
Vedant Millenia Happiness Phase II Wing ENARs 7.41 cr-
-NARs 1.85 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSATISH KANADE
ArchitectARCHITECTS Inc
EngineerAvanish and Associates
Chartered AccountantVERHANI & CO
Chartered AccountantAtul A Shetye
Chartered AccountantMANNAT & ASSOCIATES
PartnerRole in project
MOHAN HARDASMAL THARWANI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA06022619752Dec 2026 → Dec 2029

Reason as filed by the promoternow the construction have been started and it will take 3 to 4 years approximately to complete the same

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600032Bhakti AchrekarMOHAN HARDASMAL THARWANI09/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A - Millinea E Wing.pdf7 Aug 2026
Withdrawal Update Form 1File: Form 1 Millenia E Wing 30 JUNE 26..pdf21 Jul 2026
Withdrawal Update Form 2File: Form 2 Millenia E Wing 30 JUNE 26.pdf21 Jul 2026
Withdrawal Update Form 3File: Form 3 Millenia E Wing 30 JUNE 26.PDF21 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf25 May 2026
Withdrawal Update Form 2File: Form 2.pdf25 May 2026
Withdrawal Update Form 3File: Form 3.pdf25 May 2026
Layout approvalFile: Layout.pdf30 Apr 2026
Commencement certificateFile: APRROVAL LETTER.pdf30 Apr 2026
Building plan approvalFile: Building Plan Ground Floor.pdf30 Apr 2026
Building plan approvalFile: Building Plan 2nd floor.pdf30 Apr 2026
Building plan approvalFile: Building Area Diagram.pdf30 Apr 2026
Building plan approvalFile: Building Plan First and 3rd Floor.pdf30 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf30 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf30 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf30 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf20 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf6 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf6 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf6 Feb 2026
Form 5 (FY 2024-2025)File: FORM 5.pdf24 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf19 Dec 2025
Form 1File: Form 1.pdf19 Jul 2025
Form 2File: FORM 2.pdf19 Jul 2025
Form 3File: Form 3.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unosld.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vedant millenia happiness (phase -II) Wing-E.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed (1).pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: sold unsold.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VEDANT MILLENIA HAPPINESS WING E.pdf4 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Apr 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER 2.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 WING -E.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_compressed.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2 (A).pdf20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 5 Mill E wing.pdf16 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.PDF16 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 Mill E wing.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.PDF26 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf26 Sep 2023
Disclosure of sold/ booked inventoryFile: disclosure of sold unsold wing.pdf26 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf26 Sep 2023
Proforma of Agreement for saleFile: AFS.pdf28 Oct 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report_compressed_compressed (1)_compressed.pdf28 Oct 2022
Details of encumbrances concerned to FinanceFile: FINANCE ENCUMBRANCE_compressed.pdf13 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NEW ARCHITECT CERTIFICATE_compressed.pdf13 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NEW FORM 3_compressed.pdf13 Oct 2022
Proforma of Allotment letterFile: MILLENIA - E-wing (1).pdf13 Oct 2022
Proforma of Agreement for saleFile: MILLENIA - E-wing (1).pdf13 Oct 2022
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT_compressed.pdf13 Oct 2022
Layout approvalFile: SANCTIONED LAYOUT_compressed.pdf6 Oct 2022
Building plan approvalFile: GROUND FLOOR LAYOUT_compressed.pdf6 Oct 2022
Building plan approvalFile: E WING GR 1ST FLR SHEET_compressed.pdf6 Oct 2022
Layout approvalFile: E-WING TYPICAL FLOOR PLAN_compressed.pdf6 Oct 2022
PAN CardFile: Pan Card copy of Mohan Sir.pdf6 Oct 2022
Copy of the legal title reportFile: TITLE REPORT_compressed.pdf6 Oct 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VEDANT MILLENIA PHASE IBEHIND MAHAGANPATI MANDIR TITWALA402CompletedMar 2016Late, Jul 2016

How this compares with Thane

0%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 36 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vedant Millenia Happiness Phase II Wing E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TITWALA (EAST)7,600+ in Thane

2 kmVedant Millenia HappinesCompleted 39Lapsed / revoked 24Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 89 registered projects within 2 km.

Builder: MOHAN HARDASMAL THARWANI

MOHAN HARDASMAL THARWANI has 19 registrations on MahaRERA, including vedant nakshatra ABC phase 1 and vedant nakshatra M phase 2. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Vedant Millenia Happiness Phase II Wing E is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vedant Millenia Happiness Phase II Wing E?

The registered promoter entity is MOHAN HARDASMAL THARWANI, an individual as per the filing. Its GSTIN 27AAOPT7033Q1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vedant Millenia Happiness Phase II Wing E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Vedant Millenia Happiness Phase II Wing E?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Vedant Millenia Happiness Phase II Wing E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vedant Millenia Happiness Phase II Wing E?

The professionals named in the filing: Architect: SATISH KANADE; Architect: ARCHITECTS Inc; Engineer: Avanish and Associates; Chartered Accountant: VERHANI & CO; Chartered Accountant: Atul A Shetye; Chartered Accountant: MANNAT & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vedant Millenia Happiness Phase II Wing E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vedant Millenia Happiness Phase II Wing E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vedant Millenia Happiness Phase II Wing E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.