Home / Browse projects / Ahmednagar, Maharashtra / VEDA PRIVE II

Completed No litigation declared Residential / Group Housing project

VEDA PRIVE II

By VEDA VENTURES

RG-MH-00694 · RERA P52200000360 · Last updated on MahaRERA portal: 24 Dec 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Dec 2018Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

VEDA PRIVE II is a Residential / Group Housing project by VEDA VENTURES in Ahmednagar, Maharashtra, registered with MahaRERA as P52200000360 on 15 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2018.

At a glance

Project

  • NameVEDA PRIVE II
  • TypeResidential / Group Housing
  • Location
    • Ahmadnagar (M Corp.)
    • Nagar
    • Ahmednagar
    • 414001
  • Pincode414001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52200000360
  • ReraGenie IDRG-MH-00694

Builder

  • NameVEDA VENTURES
  • Entity typePartnership
  • PartnersVINAYKUMAR MAHAVIRPRASAD CHUDIWAL, KAVITA VINAYKUMAR CHUDIWAL, SHREYAS RAVIKUMAR KASLIWAL, SURBHI SHREYAS KASLIWAL
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017PromisedDec 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Jul 2017
  • Promised completion31 Dec 2018
  • Revised completionNone
  • Buildings1 building record
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VEDA PRIVE IINA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

VEDA PRIVE II: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes25%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,424 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NISA ENTERPRISESAhmadnagar (M Corp.)Ahmednagar

Approvals and building plan

Permissible FSI2450.2
Proposed, not sanctioned2,450 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchM-4, VIRWANI PLAZA AVENUE,11,EST STREET, PUNE, 411001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR PAVAN SHINDE AND ASSOCIATS MRPAVAN SHINDE
EngineerDESIGN WERKZ ENGINEERING PVT LTD THROUGH RAJESH MANKANI
PartnerRole in project
VEDA VENTURES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Aug 2021

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Veda Prive' II.pdf24 Dec 2021
Status of ConveyanceFile: 1 Deed of Declaration 1-15 pages.pdf6 Aug 2021
Status of ConveyanceFile: 2 Deed of Declaration 16-28 pages.pdf6 Aug 2021
Status of ConveyanceFile: 3 Deed of Declaration 29-42 pages.pdf6 Aug 2021
Status of ConveyanceFile: 4 Deed of Declaration 43-57 pages.pdf6 Aug 2021
Status of ConveyanceFile: 5 Deed of Declaration 58-70 pages.pdf6 Aug 2021
Status of ConveyanceFile: 6 Deed of Declaration 71-85 pages.pdf6 Aug 2021
Status of ConveyanceFile: 7 Deed of Declaration 86-100 pages.pdf6 Aug 2021
Status of ConveyanceFile: 8 Deed of Declaration 101-116 pages.pdf6 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 1 Deed of Declaration 1-15 pages.pdf5 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 2 Deed of Declaration 16-28 pages.pdf5 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 3 Deed of Declaration 29-42 pages.pdf5 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 4 Deed of Declaration 43-57 pages.pdf5 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 5 Deed of Declaration 58-70 pages.pdf5 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 6 Deed of Declaration 71-85 pages.pdf5 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 7 Deed of Declaration 101-116 pages.pdf5 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: 7 Deed of Declaration 86-100 pages.pdf5 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf2 Aug 2021
Certificates of CA (Form 5)File: Form 5.pdf30 Sep 2019
Certificates of CA (Form 5)File: Form-5.pdf30 Sep 2018
Status of ConveyanceFile: ANNEXURE ''I'' -COMPLETION CERTIFICATE.pdf11 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERCERTIFICATE18022019.pdf22 Mar 2018
Certificates of CA (Form 3)File: CACERTIFICATE.pdf22 Mar 2018
Layout approvalFile: SCAN-1-4.PDF10 Jul 2017
Building plan approvalFile: Commencement Certificate.pdf10 Jul 2017
PAN CardFile: PAN VV.pdf10 Jul 2017
Copy of the legal title reportFile: TITLE REPORT MERGED.pdf10 Jul 2017
Details of encumbrancesFile: EC VEDA.pdf10 Jul 2017
Copy of Layout Approval (in case of layout)File: SCAN-1-4.PDF10 Jul 2017
Building Plan Approval (IOD)File: Commencement Certificate.pdf10 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf10 Jul 2017
Declaration in FORM BFile: Form B.pdf10 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf10 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf10 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf10 Jul 2017
Proforma of Allotment letterFile: Unit aggrement.pdf10 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
VEDA PRIVEPLOT NO 132 TO 137A SAINAGAR NEAR NAKSHATRA LAWN BURUDGAON ROAD AHMEDNAGAR 41400116CompletedFeb 2014Late, May 2015

How this compares with Ahmednagar

7%of Ahmednagar projects moved their completion datethis one has not
28%of Ahmednagar registrations have lapsed or been cancelledthis one is completed

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep VEDA PRIVE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ahmadnagar (M Corp.)490+ in Ahmednagar

2 kmVEDA PRIVE IICompleted 3Lapsed / revoked 3Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 7 registered projects within 2 km.

Builder: VEDA VENTURES

VEDA VENTURES has 2 registrations on MahaRERA, including VEDA PRIVE II and CONCLAVE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What are my rights if VEDA PRIVE II is delayed beyond 31 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VEDA PRIVE II?

The registered promoter entity is VEDA VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VEDA PRIVE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VEDA PRIVE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VEDA PRIVE II?

The professionals named in the filing: Architect: AR PAVAN SHINDE AND ASSOCIATS MRPAVAN SHINDE; Engineer: DESIGN WERKZ ENGINEERING PVT LTD THROUGH RAJESH MANKANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VEDA PRIVE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VEDA PRIVE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VEDA PRIVE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.